Projects are differentiated with other endeavors because they possess certain characteristics’ (Burke 2013, p.13). Some of the characteristics for a project include: having a life cycle with a start and end process, it has a budget because it consumes resources; it is participative because it involves interaction with stakeholders, projects are faced with risks which need to be managed or mitigated, tasks in a project are non-repetitive, projects are faced with three constraints of time, scope and resources which need to be managed, and projects have a goal to be achieved that is distinctive from other projects. ‘The characteristics make the project to be a unique activity in different environments that is located’ (Verzuh 2015, p.67).
Scope statement defines the requirements to accomplish a project outcome successfully’ (Gido & Clements 2014, p.67). It provides a boundary of items to be included in execution of the project. ‘It is a useful planning tool in explaining what to be accomplished and to be delivered by the project team’ (Verzuh 2015, p.78). The scope statement should include items like project objectives, deliverables, requirements, approvals, assumptions, milestones, charter, inclusion and exclusions. It is prepared during initiation phase of the project agreed by all stakeholders.
Project Gantt chart and critical path method are scheduling tools used in allocation of time resource in projects. ‘Gantt charts show a sequence and relationship between project activities against scheduled time’ (Pinto 2014, p.56). The critical path analysis provides the shortest or longest path or steps to accomplish a project goal. The schedule for Gantt chart and critical path can be derived using MS project software. Figure 1 and 2 show Gantt chart and critical path respectively.
The critical path is indicated using the red color. The critical path computation follows task (a) to (c) to (f) = 2days + 3days +6days = 10 days. The critical path is 10 days for the computation.
There is several factors that need to be considered when developing a budget for a project. ‘The first item to be considered is the approach that will be followed in estimating requirements for example parametric, bottom-up and top bottom approaches’ (Zulch 2014, p.56). The approach chosen will guide the type of project to be formulated. The other critical factors to be considered are availability of resources, costs of estimates, tools for budgeting process, and baseline information of the project. The baseline information provides for the scope and nature of the project (Zulch 2014, p.56). Tools for budgeting process represent technical or operative inputs that can aid budget development.
Project management teams after identifying, assessing risks they need to formulate ways to manage the risk known as risk responses. Risk responses include activities performed by project teams that could enhance opportunities and reduce threats to project delivery. ‘Risk responses are part of the phases of risk management process, (Kloppenborg 2014, p.34). Examples of risks responses that can be used in projects include: transferring by sharing risk consequences with a different external party, avoiding project activities that could lead to risks, exploiting positive consequences originating from positive risks, acceptance of consequences of risks through tolerance, and identifying methods that can be used to treat the risks.
Project managers can utilize quality planning outputs (quality metrics, checklists, process improvements plans, quality management plans), as part of the methods to ensure successful accomplishment of the project (Heagney 2016, p.56). The planning outputs will enable activities to be monitored, evaluated and controlled in terms of quality. Most dominantly the quality management plan is usually developed in project management. The quality management plan outlines how quality will be assured, evaluated and controlled. ‘Quality plans can be aided using inputs like scope statements, project management plan, organizational resource plans, and stakeholder registers’ (Kloppenborg 2014, p.67). Several quality tools and techniques can be used at each phase of the project to manage quality. Examples of the tools and techniques include: benchmarking, control charts, cost of quality, cost-benefit analysis, statistical sampling, six-sigma etc. ‘The tools and techniques for quality can be assessed on appropriateness and chosen based on the needs or nature of the project’ Thamhain 2014, p.67).
This report focuses on Hotel Communication Company using project methodologies, techniques and tools to install, test and commission information technology (IT) and communication infrastructure for a contract awarded by a client City Towers hotel in Docklands area of London. The report will provide project activities, skills and competences that will be used by the project manager to successfully deliver the project goal. The report outlined follows the project life cycle steps of initiation, planning, execution, control and project closure.
This stage involves coming up with items that define the conceptualization of the project. ‘The project manager of the project will prepare a statement of work, a project charter, and list of managing the stakeholders’ (Bryde & Volm 2013, p.973).
IT and infrastructure project statement of work |
|
Date submitted: |
2/12/2017 |
Project name: |
IT and communication infrastructure project |
Prepared by: |
Xx (project manager) |
1. Summary of work requested and benefits The contract to be implemented will involve installation, testing and commissioning IT and communication infrastructure for a new hotel towers. The project will be beneficial in making facilities for marketing and making bookings for hotel rooms. It will be useful in security features in the hotel. |
It is a document that fully describes the needs of accomplishing the project to make it official and acceptable. The project charter will specify project summary, objectives, requirements, deliverables, and assumptions for accomplishing the project.
Project title |
Development of IT and communication infrastructure |
Project owner |
City towers hotel |
Project manager |
Xx (project manager) |
Project duration |
3 months |
Project budget |
$67,095.00 |
Project objectives |
a. To develop IT application system that will be used for bookings and marketing functions in hotels b. To design IT infrastructure provisions for radio and TV usage in hotels c. To provide IT aided facilities for CCTV, meeting rooms and conference center functions in hotels |
Project requirements |
The requirements include: software applications, computer and IT accessories, resource persons |
Project deliverables |
‘They represent what specifics to be considered to accomplish project objectives’ (PMI 2013, p.67). They will include: drafting a plan, creating a budget, sourcing a service and product provider, design, testing and commissioning of IT infrastructures, provisions for maintenance and controls, and project closure. |
Project assumptions |
The project assumes that the product will be acceptable by the client and create a competitive edge in the market. |
‘Stakeholders are individuals and institutions that directly or indirectly affected by the performance of the project’ (Bourne 2015, p.56). The project summary of stakeholders identified was managed using the stakeholder lists presented in table 3.
Table 3 Stakeholder lists
Primary role/position |
Interest/objective |
Communication strategy/mode |
Project sponsor |
Improved quality product and services delivered |
Regular: briefing, formal meetings and reports |
IT infrastructure manager |
Provision of computer, IT related infrastructure |
Regular: Formal meetings, emails and site visits |
Project manager/project team |
Management of project |
Frequently: Formal and informal meetings, reports, phone calls |
IT technical experts |
Consultancy on IT related functions |
Occasionally: Meetings, briefings, reports |
Hotel employees |
Users of the product/service |
Occasionally: Briefing’s, meetings |
‘The phase involves development of different plans detailing how the project will be implemented or executed in achieving its objectives’ (Schwalbe 2015, p.35). The plans to be formulated will cover management of costs, resources, quality, risks, schedules, and procurements.
‘It involves resource budgeting and costing of the requirements of the project’ (Heagney 2016, p, 56). Costs form one of the constraints of the project proper planning to be done to accomplish the intended goals. The top down approach was employed from unknown figure to a known total figure. The estimating and budget involves development of IT and communication infrastructure for City Towers hotels. Table 4 shows a summary of the resource estimates to be used in IT and communication infrastructure project.
Table 4 Project cost estimates
No. |
Items |
Units |
Total amount ($) |
3 |
Direct consumption expenses |
– |
1000 |
4 |
Software application purchase |
– |
5000 |
5 |
Computer accessories |
Assorted |
15000 |
7 |
Design, testing & commissioning fees/expertise consultancy fees |
– |
25000 |
8. |
Technological infrastructure |
20000 |
|
9 |
Contract charges |
– |
145 |
10 |
Software patent & licensing |
– |
300 |
11 |
Contingencies expenses |
– |
500 |
12 |
Internet charges |
Assorted |
150 |
Totals |
67,095.00 |
The budget was created with assumptions that prices of the items will not be affected by economic or existing market changes. ‘The budget consisted of both direct and indirect costs’ (PMI 2013, p.45).
Quality is an important component when ensuring that the products will be accepted and approved by the final user. ‘The project will ensure that quality is planned, assured and controlled’ (Gido & Clements 2014, p.86). Quality planning will involve use of quality lists and checklists to ensure standards and specifications are followed.
Quality deliverables: ‘the following are quality deliverables that the project will tend to achieved during the project delivery’ (Pritchard 2013, p.4). The software applications are designed to meet current and future needs of the hotel, materials and infrastructures to be bought according to required specifications, a right service provider and consultants chosen in an open and accountable process. Project assurance: to ensure that the planned quality measures are maintained consistently the project team will follow the project processes and activities based on professional checklists. Table 5 presents a summary of quality checklists that will be followed to ensure quality is maintained and achieved during the project life cycle.
Table 5 Quality checklists
Activities and functions |
Status |
Comments |
|
Done |
Not done |
||
Good sourcing of service providers done well |
|||
IT and Computer infrastructures bought as per specifications |
|||
Software applications and programs reflect current and future needs |
|||
Maintenance and repair cautions are in place |
|||
Provisions for monitoring and audits are in place |
|||
A process of escalation is in place |
‘Quality controls are important in ensuring what is achieved is maintained, corrected and lessons learnt from them’ (Kendrick 2013, p.32). The project manager will employ variance reporting for schedule, costs, and performance (operative, technical) to control quality issues.
The project manager will employ a competitive bidding process as the only method of sourcing materials, services and requirements of the project. Identification of needs and requirements will be done, an open bidding process will be done to identify the suitable bidders, evaluation of prospective bids will be done competitively, awarding of contract will be given, and payment done after accomplishment of tasks. Items/materials/services to be included in procurement plan include: sourcing software developer, provision of computer and IT technologies, design, testing and commissioning of the project.
‘Risks are occurrences that can either affect positively or negatively the performance of a project’ (Andrew 2014, p.34). The project manager of the IT and communication infrastructure project will need to identify, evaluate and manage the risks that would likely affect the project.
Through brainstorming with relevant parties the following are risks likely to affect the delivery of the project included: non co-operation among the users (A), systems failure (B), and changes in technological market (C). Through a probability/impact matrix the already identified risks were evaluated to facilitate ranking of them. ‘The evaluation is based on the probability of it occurring and the impact of the risk if it occurs’ (Andrew 2014, p.56). Table 7 shows the probability/impact matrix for the project.
Table 6 Probability/impact matrix
B |
A |
|
C |
Ranking for the risks evaluated in table 7 will follow the sequence of 1st =A, 2nd=B, 3rd=C. Risks can be managed using a risk register. It is a tool used to manage the risks identified. Table 8 shows the risk register for the project
Table 7 Risk register for IT and computer infrastructure project
Rank |
Risk |
Description |
Root Cause |
Potential Responses |
Risk Owner |
Probability |
Impact |
1 |
Non co-operation among users |
The users may resist in work structures due to new changes |
It may result if they are not involved |
Trainings and involvement in project activities |
Project manager and sponsor |
High |
High |
2 |
Technological changes in the market |
New technological implementation may be affected by changes in the market of new technologies |
It results when a non-researched item is implemented |
The team will ensure that items that can be upgraded are used to caution any changes |
IT infrastructure manager |
high |
low |
3 |
Systems application & program failure |
The systems or program installed may fail to perform as required |
It results when the software app or program was not designed or tested well. |
Proper design and testing need to be done before any commissioning |
It infrastructure manager and project manager |
Low |
High |
Prepared by…………………………………………………………. Date prepared………………………………..
Approved by…………………………………………………………Date approved……………………………….
Dates for reviews 1st …………………………….2nd ……………………………..3rd…………………………….
‘Project scheduling involves a process in which activities are broken down into smaller manageable units and relationship created between them’ (Nazari 2016, p.56). The project will employ milestones, work breakdown and Gantt charts to schedule activities.
‘The milestone is a summary of key events to be implemented by the project’ (Lock 2014, p.61). It created to follow a key deliverables of the project. The project milestones are presented in table 9.
Table 8 Project milestone
Milestones |
Time line (Events start on) |
Drafting plan |
1/12/2017 |
Creation of a budget |
5/12/2017 |
Sourcing a service provider |
15/12/2017 |
Designing of the product |
20/12/2017 |
Testing of the project |
10/01/2018 |
Commissioning of IT infrastructure |
23/01/2018 |
Maintenance and evaluations |
25/01/2018 |
Project closure |
Takes place on 10/02/2018 |
‘The work breakdown structure (WBS) is a scheduling tool that breaks project into smaller work packages and tasks that can facilitate allocation of resources’ (Phillips 2013, p.33). The Gantt chart shows the sequence of project activities showing relationship them. ‘Both Gantt chart and Work breakdown structure will be developed using MS project software’ (Rainer 2014, p.34).
It is a phase in which the project manager of the IT and communication infrastructure project will ensure activities are done according to the plans. The phase involves: direct and manage project execution, execution of quality, acquisition and development of project team, monitoring and evaluation, management and status reporting. Table 10 shows a summary of execution plan of various project activities.
Table 9 Project implementation & execution plan
Project activity/item |
Methodology of execution and implementation |
Direct and manage project execution |
It involves carrying out the project management plan to enable final product is achieved. The project manager will employ expert judgments and PMIS to manage the project execution process. Export will include: consultants providing opinions. |
Execution of quality |
The quality assurance plan is used to execute because it specifies the standards in which quality will be tested, described and corrective measures done. The project manager will employ a quality assurance plan in form quality audits. ‘The audits will be informed of inspections and reviews of performance of the project’ (Kendrick 2013, p.46). |
Project information reporting |
The process involves a means in which reporting and distribution of information will be done or will be executed. The project manager will provide information to the right persons. A communication plan outlining meetings and reports will be used. |
Monitoring and evaluation |
The process is executed in order to efficiently communicate bad and good information among the project stakeholders. The monitoring will take place use expert judgments to collect information of the progress of the project. Evaluation will take place periodically after different phase of the project. |
Acquiring, managing and developing project teams |
It involves the methodology in which employees will be acquired in the project to form project teams. The project manager will source right employees by interviewing method. The output will include resource calendar’s and staff assignments. Work performance, evaluation, target and appraisals are tools and techniques are employed (Cummings & Worley 2014, p.34). |
The project manager of IT and computer infrastructure project will ensure change is managed and controlled to reduce consequences resulting to scope, budget and schedules. A change request form will be formulated to manage. Approvals will be done before the change is accepted. Table 8 shows the IT and communication infrastructure project change request form.
Table 9 change request form
Change request form Change requested by………………………Date of request……………………………. |
||
Type of change |
Effect of change in project |
Remarks |
1. 2. |
||
Approved status: accepted ( ) Rejected ( ) |
‘Stakeholders require knowledge on the status of the project in terms of performance’ (Larson 2011, p.72). Reports can be done depending with the user’s needs and agreements. A variance report mechanism will be employed in the IT and communication infrastructure project indicating the difference of what had been planned and actual performance. Table 11 shows a presentation of how performance variance report would be presented as part of control measure.
Table 11 performance variance report
Metrics performance |
Planned metrics |
Actual metrics |
Comments |
Technical/operative Work was managed and executed as per the required specifications |
|||
Schedules/plans Schedules for time and resources were followed duly |
|||
Cost/budgets/estimate The work performance estimates were done as per the specified budgets provided. |
Project closure will take place for the IT and communication infrastructure project after the final evaluation and reporting has been done. The conclusion will encompass payments and contract closures. Once the client is contented with the performance of the project handing over will take place and the project is closed down (Wysocki 2014, p.67). The project will be aided by the project closure checklist presented in table 12.
Table 12 Project closure checklists
No. |
Items/activities |
Status of activity |
Remarks |
|
Done |
Not done |
|||
1 |
Performance report developed |
|||
2 |
Stakeholders are informed on closure |
|||
3 |
Accounts closed |
|||
4 |
Payments and contracts closed |
|||
5 |
Disposal of assets |
|||
6 |
Filing of relevant documents |
|||
7 |
Commissioning of project |
|||
8 |
Post evaluation of the project performance |
|||
9 |
Handing over of the project |
Reference lists
Andrew, F 2014, Effects of risk management in projects. New York: Mc Graw Hill.
Bourne, L 2015, Making projects work:effective stakeholder and communication management. New Delhi: CRC press.
Bryde, B & Volm, H 2013, The project benefits of building information modelling. International Journal of project management, 31(7), 971-980.
Burke, R 2013, Project management: planning and control tecniques. New Jersey: Wiley publishers.
Cummings, H & Worley, F 2014, Human resource management and planning techniques. Chicago: Cengage Learning.
Gido, H & Clements, T 2014, Successful project management. Chicago: Nelson Education.
Heagney, J 2016, Fundamentals of project management. AMACOM: American management association .
Hedman, K 2013, Project management professional exam study guide. Indianapolis: Wiley.
Hegney, A 2016, Managing the team. In Fundamentals of Project Management. New York, Atlanta: Amacom Division of American Management Association International.
Kendrick, T 2013, The project management tool kit: 100 tips and techniques for getting the job done right. . AMACOM Div: American management Assn.
Kloppenborg, T 2014, Contemporary project management. London: Nelson Education.
Larson, E 2011, Project management: the managerial process. New York: Mc Graw Hill.
Lock, M 2014, The essentials of project management. New York: Ashgate publishing Ltd.
Nazari, A 2016, Developing a social media communication plan. Strategic integration of social media into project management practice, 194-217.
Phillips, J 2013, PMP, project management professional (certification study guides). New York: Mc Graw Hill.
Pinto, M. 2014, Project team communication and cross?functional cooperation in new program development. Journal of product innovation management, 7(3), 200-278.
PMI, 2013, A guide to project management body of knowledge . Newtown Square: PA: PMI.
Pritchard, C 2013, The project management communication toolkit. New York: Artech House
Rainer, R 2014. Management information systems. New York: Wiley publishing.
Schwalbe, K 2015, Information technology project management . New York: Cengage learning.
Thamhain, H 2014, Team building in project management. New York, United States: John Wiley & Sons, Inc.
Verzuh, E 2015, The fast forward MBA in project management. New York: John Wiley & Sons.
Wysocki, R 2014, Effective project management: traditional agile. Indianapolis: Wiley.
Zulch, B 2014, Leadership communication in project management. Procedia Social and behavioural sciences, 172-181.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download