ADCO Constructions plans to construct a building in Australia. ADCO Constructions hire a project management team who will assist to construct the building ethically and efficiently. The Project Manager and his team will prepare the project plan. ADCO Constructions and the associated stakeholders will perform the project activities according to the project plan. The primary objective of this project is to prepare a project plan.
iii. The project plan must define the entire budget of the project. Thus the cost of every activity can be known from the project plan. The electric equipment, hardware equipment and can be high and out of range. Proper budget scheduling can assist in cost management. Thus the stakeholders may have to purchase the machinery parts at the relatively high price, but they can optimise the overall budget.
vii. The project plan must conduct the financial plan for the entire project. The project may require extra funds to carry out the project activities. They can know the funds or the money required to conduct the project activities pretty early with the help of the project plan. In this way, they can optimise the budget of every activity and the entire project.
viii. The project plan must manage the timeline of the project. The project plan also includes the slack time. From the slack time, it can be calculated that a particular activity can be extended to a certain period.
The project manager and his team are responsible for handing over the building constructing project to the client. The project deliverables contain the list of project activities that will be conducted sequentially. The client can get to know the project activities that they are going to get. In this the case, the client can get to every work activities associated with building construction (Sansakorn & An, 2015). They can know in details the budget for every activity of the project. The client can get to know that for which activity how much money is going to be spent. If the client approves and is willing to pay, the project manager and his team can work on the project. The client and can review the deliverables. In this case, the client can view the scope of the construction department and the schedule of values. The raw materials used for the project can be viewed (Muhwezi, Acai & Otim, 2014). The client can know the raw materials used for constructing the building. The client can know the two important aspects of the project that is the time and the cost. The client can review the contract plans. They can view the contract plans made for the project. The contract plans include the sales agreement, construction agreement, contract specifications for the building and the contract site plan for erecting the building (Jung et al., 2018). The entire contract plan will require about seven weeks to get completed, and the total budget for the project will be around 25 thousand dollars. The documentation review of the project contains the finalising plans, finalising specifications for the building, preparation and entire construction design of the building (Cao et al., 2015). The documentation review will get completed within 8 weeks. The bids and contracts for the project contain the copies of plans, receiving bids and detail review of bids. The bids and contracts also include the sub-contractor agreements, lot-stake out scheduling. The bids and contract must meet the requirements for the sediment control inspection. The bids and contracts for the project will take about thirty-one weeks to complete (Enshassi, Ayash & Mohamed, 2018). It will require about 84 thousand dollars to complete the bids and contracts and receive the permission.
Foundation includes the digging footings and installation of reinforcing. It includes several tasks like the inspection of footings, pin footings, pour footings. The builders will put the building blocks. The masons will construct the building using sand, stock, block and mortar (Mancini et al., 2017). After that, the builders will build the waterproofing and the draining tile. The waterproofing tiles and the drain tiles will be built after that. In this way, the structure of the building will be constructed.
Later on, they will build deck frame for the first floor of the building. Later on, the first floor of the building will be constructed (Akomah & Jackson, 2016). The builders will design the deck frame for the second floor after the entire complete budget for the project will be an ion of the first floor. Next, they will build wall floor of the building as well. After finishing work, the basement will be framed. The entire foundation will take around 40 weeks (Kerosuo et al., 2015). The budget of the foundation will be around 74 thousand dollars. The doors and windows will be installed after that preparing the basement of the building.
After the basic foundation is done, the concrete slab will be installed. The builder will install the basement slab of the building. At first, the basement slab is prepared after that the slab will be treated with termite (Tezel et al., 2017). The pest controller is responsible for the termite treatment. The civil engineer, the construction subcontractor and the project manager are responsible for inspecting the slabs of them in details. The concrete slab installation will take about 5 weeks and total cost allocated for the foundation
After concrete slab installation, the mechanical subcontractor will setup HVAC and will form the layout. He will design the layout the will measure the HVAC for the construction (Marzouk & El-Rasas, 2014). The HVAC setup will require about 2 weeks and the budget required to conduct the project is 15 hundred dollars.
The plumber will then set up the plumbing rough-ins and inspection of rough-ins. He will inspect the plumbing rough-ins (Mohd Nawi et al., 2018). The plumbing rough-ins will require about 2 weeks, and it will require a budget of about 12 hundred dollars.
The electric rough-in will be set up by the electric boxes. The electrician is responsible for setting up the electric rough-in and the electric rough-wire. The telephone lines and an alarm signal will be set up by the mechanical subcontractor (Belay, Tekeste & Ambo et al., 2017). This simple setup will take about 1 week, and it will require about 2 thousand dollars. Builder and mason will work on roofing paper, implementation of roof shingles. The roofing will take about 2 weeks’ time and the builder and mason, and it will require a budget of about 4 thousand dollars. The hardware subcontractor and the builder will inspect the BGE Energy, will install the ceramic tiles (Victoria, Perera & Davies, 2016). The construction subcontractor will install hardware in the bathrooms and will install mirrors. The cleaning staff will take the responsibility to clean the building windows. They will conduct the rough cleaning. All these tasks will need about 5 weeks’ time, and it will take around 4 thousand dollars.
Finally, the project will be handed over to the client. The entire project will take around 90 weeks to complete. The estimated project cost is around $250,000. The client will have to approve the deliverables (Fung, 2015). If he is satisfied with the deliverables, he will approve the project deadline and the project budget. The project manager and his team start working on the construction project based on the deliverables confirmation from client’s end.
Minister of Public Works sets the technical requirements provisions. All the mentioned technical requirements for the project must be according to the local zoning plan of Australia. The technical requirements of the construction area depend on the following factors- building structure, the things which are related to building design, security, comfort, ability and safety (Hyari, El-Mashaleh & Rababeh, 2015). There are several policies and regulations which maintains the provisions of the technical requirements of the building construction are as follows-
Space
The spaces used for the day-to-day activities will have a direct as well as indirect contact with the air (Kibert, 2016). The spaces will have a direct or indirect impact on natural lighting in sufficient quantities.
A building structure, Building components and the Building materials
The Building strata must be well planned and must be built along with the building structure and the construction components. The construction materials that have been planned to use in for erecting the building must meet the construction requirements (Odimabo, Oduoza & Suresh, 2017). The requirements must comply with the building standards.
Strata Title Completeness
The new building must be provided with the clean water system, gas networks. The construction must be in made in such a way such that the building or the construction area must have proper water drainage system. The construction area must have the proper wastewater drainage system as well (Y?lmaz & Kan?t, 2018). The building must have well-built channels and landfills. The building must have the proper channels installed and landfills. The construction area must have telephone networks installed. The builders must build communication equipment in the building. The building also must have proper transport facility installed. The building must have stairs, escalators and the elevators. Also, the building must have facilities like laundry space (Hu et al., 2016). The builders must keep in mind the safety measures of the building that is why they need to implement lightning rods, alarm system and the tight smoke doors. The project manager and the construction department must ensure the safety of the building that is why they must install fire extinguishers and smoke-tight doors. The buildings also must have the electric generators.
Strata Title Units
The title units of Strata can be established above or below the land surface. The strata must be placed above the land surface. The Strata title must have a standard size that can be well accounted (Tabassi et al., 2016). The Strata must have a standard size that must be accounted. The Strata Title must fulfil the requirements regarding function and usage. The building construction must be carried out in such a way such that it supports the smoothness and prosperity of the residents in Australia. The project manager will have to ensure that the stakeholders, the workers carry out construction project activities efficiently (Udawatta et al., 2015). It is the responsibility of the project manager and the other stakeholders of the project to ensure that the residents carry out daily activities smoothly.
The project manager and his team members are responsible for looking after the comforts and the luxury of the residents of the building. The project stakeholders must prepare stairs, elevators, hallways so that the customers can perform the daily activities conveniently (Larsen et al., 2015). The dwellers of the buildings require the common facilities like the dimension, quality, capacity and good location, the project manager and his team will have to keep in mind and construct the building according to that.
Density and Layout of the Building
The construction area must be used effectively. The building layout must be prepared in such a way that it ensures the smoothness of the daily activities. The health aspects, ventilation, lighting must be considered to ensure the safety of the residents, building as well as the environment (Senouci, Ismail & Eldin, 2016). The project manager and the stakeholders must construct the building in a fashion such that the residents can lead a good life.
Environmental Infrastructure
ADCO Constructions must provide the residents with a healthy environment. The project manager and the stakeholders are responsible for constructing roadways and parking lots to facilitate the residents of the building (Mok, Shen & Yang, 2015). They must construct parks and gardens. The residents can enjoy a good time over there. The children can play in the garden. Thus there is a need to set up an environmental infrastructure there within the building campus.
Sanctions
Australia Minister of Public Works has prepared some guidelines and policies. ADCO Constructions is bound to follow those guidelines. If ADCO Constructions fail to follow the rules and the policies, then they will have to pay a heavy penalty. The project manager and the stakeholders will have to adopt the policies (Montaser & Moselhi, 2014). If anyone fails or violates any policies, he will be threatened with imprisonment of ten years and will have to huge fines.
iii. The project manager will assign the builders, masons, plumbers, electrician and all of them will contribute to the project (Ryu, Son & Kim, 2016). The resources defined within the project plan will perform. Any other resources which are not mentioned in the project plan are out of scope.
There are several limits and exclusions for a building construction project. The project stakeholders, builders and the project team members of ADCO Constructions can face limits and exclusions while conducting the construction activities (Yeung, Ng & Wong, 2017). Completed operations, residential exclusions, excluded operations, subcontracted work exclusion, employee theft, intentional and illegal acts are some of the project exclusions.
Completed Operations
The labourers working at the construction site must ensure that they are getting appropriate coverage. The insurance carriers have made this type of coverage an option for the agents and the agents have to request specially for the coverage.
Residential Exclusions
The insurance contractors do not like the residential contractors, and there may be certain reasons for that. That is why the insurance contractors include an extra page in the policy paper (He et al., 2015). The last paper of the page contains the ‘Residential Exclusions’.
Excluded Operations
There are many policies out there which exclude the specific operations like the roofing, condominium, apartments and the townhomes (Schaufelberger & Holm, 2017). The policies also exclude the demolition, work over 3 stories, roofing and others.
The stakeholders’ work
The builders, mason, plumber are responsible for erecting the building. If any building falls, the stakeholders will have to pay the penalty. ADCO Constructions will have to pay for the injuries; they will have to pay for all the injuries (Lindgren, Widén & Emmitt, 2018). After ADCO Constructions takes the responsibility of construction of building after someone else, then ADCO can get insurance to rework. The insurance carriers will allow a limited amount of rework coverage,
Pollution
The pollution policy can be helpful to safeguard oneself. The project manager and his team must take the initiative to exclude the pollution (Francom & El Asmar, 2015). The air pollution can cause severe harm to the project manager and his team. The pollution can adversely affect the project activities, and they can suffer heavy loss.
Illegal Acts
The insurance carriers can deny any claims if the project stakeholders conduct any ill-acts or illegal acts.
Employee Theft
If any criminal breaks in and steal any confidential and sensitive data then the property policy will pay some handful of money to the stakeholders. The project member can steal the sensitive information. The issue can be mitigated with the help of the specific crime policy (Cao et al., 2016). The policy is very costly. ADCO Constructions will have to spend heavy for adopting this policy.
Customers’ feedback plays a major role in the project. The reviews from the residents and the dwellers of the buildings will help project plan to prepare a better project plan. ADCO Constructions and the builders, masons, plumber, electrician, mechanical subcontractor, a civil engineer can work efficiently and can satisfy the needs of both the local residents and the dwellers of the buildings (Rumane, 2016). The customers will give them both positive and negative feedback. The local residents may face certain issues and may complain. The project manager must consider all these factors and if possible must make appropriate changes if feasible. The project may harm the society and environment in some way, can increase the pollution. However, the project manager must take into consideration all these staffs carefully (Love, Teo & Morrison, 2018). The dwellers may want to shift doors and windows, may want to change the interior decoration. The project manager must listen to them and fulfil their demand, in this way dwellers can be satisfied. In this way the customers’ reviews can help ADCO Constructions, project manager and his team to work better.
Project Acronym |
CONSTRAINT AND ASSUMPTION LOG |
||||||
Company Name |
ADCO Constructions |
Project ID |
|||||
ID |
Category |
Constraint/Assumption |
Responsible Party |
Due Date |
Actions |
Status |
Comments |
01 |
Planning |
Near about 20 stakeholders will be allocated for the Building Construction Project |
Project Manager |
NA |
Pending |
||
02 |
Executing |
Cleaning for the Building will be conducted only after the entire construction work for the building gets completed |
Cleaning Staff |
NA |
Open |
||
03 |
Planning |
The stakeholders of this Building Construction project will be paid in accordance with the average salary of the construction workers of Australia |
Project Manager |
NA |
Pending |
||
04 |
Planning |
The vendors will purchase construction materials as per requirements |
Department of Construction |
NA |
Pending |
||
05 |
Planning/Executing |
The painting works will take approximately 6 weeks’ time to get completed |
Painter and Decorator |
NA |
Open |
||
06 |
Executing |
Completion date: 20 Nov 19 |
Every stakeholder associated with the project |
NA |
Pending |
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
Cost |
Time and Cost Management in Building Construction |
89 wks |
Thu 08-03-18 |
Wed 20-11-19 |
$240,480.00 |
||
Building Construction by ADCO Constructions |
89 wks |
Thu 08-03-18 |
Wed 20-11-19 |
$240,480.00 |
||
Contract Plans |
7 wks |
Thu 08-03-18 |
Wed 25-04-18 |
$23,240.00 |
||
Sales Agreement |
3 wks |
Thu 08-03-18 |
Wed 28-03-18 |
Department of Sales |
$2,400.00 |
|
Construction Agreement |
3 wks |
Thu 08-03-18 |
Wed 28-03-18 |
Client,Project Manager |
$3,000.00 |
|
Building Contract Plans |
3 wks |
Thu 29-03-18 |
Wed 18-04-18 |
4 |
Civil Engineer,Construction Subcontractor,Department of Construction |
$7,200.00 |
Contract Specifications for the building |
4 wks |
Thu 29-03-18 |
Wed 25-04-18 |
4 |
Construction Subcontractor,Department of Construction |
$6,080.00 |
Contract Site Plan for erecting the building |
3 wks |
Thu 29-03-18 |
Wed 18-04-18 |
4 |
Construction Subcontractor,Department of Construction |
$4,560.00 |
Documentation Review for the Building and Approval |
8 wks |
Thu 26-04-18 |
Wed 20-06-18 |
$15,720.00 |
||
Finalising Plans for the Building and Preparation of Documentation |
3 wks |
Thu 26-04-18 |
Wed 16-05-18 |
4,5,6 |
Department of Construction,Project Manager |
$5,400.00 |
Finalising Specifications for the Building and Preparation of Documents |
3 wks |
Thu 26-04-18 |
Wed 16-05-18 |
6 |
Project Manager |
$3,000.00 |
Entire Construction Design of the Building |
3 wks |
Thu 17-05-18 |
Wed 06-06-18 |
9,10 |
Civil Engineer |
$2,640.00 |
Revised Plans Approval for the Building |
2 wks |
Thu 07-06-18 |
Wed 20-06-18 |
9,10,11 |
Client,Project Manager |
$2,000.00 |
Print Building Construction Design |
1 wk |
Thu 07-06-18 |
Wed 13-06-18 |
11 |
Civil Engineer,Department of Construction,Project Manager |
$2,680.00 |
Bids and Contracts |
31 wks |
Thu 17-05-18 |
Wed 19-12-18 |
$84,440.00 |
||
Preparing Copies of Plans |
2 wks |
Thu 21-06-18 |
Wed 04-07-18 |
12,9 |
Project Manager,Civil Engineer,Department of Construction |
$5,360.00 |
Preparing Copies for Specifications |
2 wks |
Thu 17-05-18 |
Wed 30-05-18 |
10 |
Project Manager,Department of Construction |
$3,600.00 |
Receiving Bids |
2 wks |
Thu 21-06-18 |
Wed 04-07-18 |
12 |
Project Manager |
$2,000.00 |
Detailed Review of Bids |
3 wks |
Thu 05-07-18 |
Wed 25-07-18 |
17 |
Project Manager,Civil Engineer,Builder |
$7,560.00 |
Execution of Subcontractor Agreements for Building Construction |
2 wks |
Thu 26-07-18 |
Wed 08-08-18 |
15,16,18 |
Construction Subcontractor,Department of Construction |
$3,040.00 |
Building Construction Permits |
3 wks |
Thu 21-06-18 |
Wed 11-07-18 |
12 |
Civil Engineer,Project Manager,Builder |
$7,560.00 |
lot stake-out scheduling |
2 wks |
Thu 12-07-18 |
Wed 25-07-18 |
20 |
Builder,Department of Construction |
$2,880.00 |
Meet requirements for the Sediment Control Inspection |
2 wks |
Thu 12-07-18 |
Wed 25-07-18 |
20 |
Builder,Sediment Controlling Inspector |
$2,720.00 |
Filing Grading Permit Application |
2 wks |
Thu 26-07-18 |
Wed 08-08-18 |
21,22 |
Project Manager,Builder,Civil Engineer,Department of Construction |
$6,640.00 |
Issuing Grading Permit |
2 wks |
Thu 09-08-18 |
Wed 22-08-18 |
23 |
Civil Engineer,Department of Construction,Project Manager |
$5,360.00 |
Approving Building Construction |
4 wks |
Thu 23-08-18 |
Wed 19-09-18 |
20,24 |
Client,Department of Construction |
$3,200.00 |
Approving Pay Permit Fees |
4 wks |
Thu 20-09-18 |
Wed 17-10-18 |
24,25 |
Client |
$0.00 |
Site Work |
5 wks |
Thu 18-10-18 |
Wed 21-11-18 |
25,26 |
Builder,Civil Engineer,Construction Subcontractor,Department of Construction,Mechanical Subcontractor,Project Manager,Field Superintendent |
$27,800.00 |
Clearance of lot |
2 wks |
Thu 22-11-18 |
Wed 05-12-18 |
27 |
Builder |
$1,280.00 |
Stripping Stockpile and Topsoil |
2 wks |
Thu 22-11-18 |
Wed 05-12-18 |
27 |
Builder,Construction Subcontractor |
$2,720.00 |
Excavation of Stake lot |
2 wks |
Thu 06-12-18 |
Wed 19-12-18 |
28 |
Builder,Construction Subcontractor |
$2,720.00 |
Foundation |
40 wks |
Thu 06-12-18 |
Wed 11-09-19 |
$73,760.00 |
||
Digging Footings and Installation of Reinforcing |
3 wks |
Thu 06-12-18 |
Wed 26-12-18 |
27,28 |
Builder,Mechanical Subcontractor |
$4,080.00 |
Inspection of Footings |
2 wks |
Thu 27-12-18 |
Wed 09-01-19 |
32 |
Builder,Mechanical Subcontractor |
$2,720.00 |
Pin Fotings |
2 wks |
Thu 10-01-19 |
Wed 23-01-19 |
33 |
Builder,Mechanical Subcontractor |
$2,720.00 |
Pour Footings |
2 wks |
Thu 24-01-19 |
Wed 06-02-19 |
34 |
Builder,Mechanical Subcontractor |
$2,720.00 |
Sand, Stock Block and Mortar |
3 wks |
Thu 07-02-19 |
Wed 27-02-19 |
34,35 |
Mason,Builder |
$3,720.00 |
Foundation of Build Block |
3 wks |
Thu 28-02-19 |
Wed 20-03-19 |
36 |
Builder,Construction Subcontractor |
$4,080.00 |
Foundation Certification |
3 wks |
Thu 21-03-19 |
Wed 10-04-19 |
37 |
Civil Engineer,Department of Construction |
$5,040.00 |
Fill Block Cores |
3 wks |
Thu 21-03-19 |
Wed 10-04-19 |
37 |
Builder,Construction Subcontractor,Mason |
$5,880.00 |
Delivery of Steel for Building Construction |
3 wks |
Thu 11-04-19 |
Wed 01-05-19 |
38 |
Supplier |
$1,800.00 |
Deivery of Lumber for Building Construction |
3 wks |
Thu 11-04-19 |
Wed 01-05-19 |
38 |
Supplier |
$1,800.00 |
Building Waterproofing and Drain Tile |
2 wks |
Thu 11-04-19 |
Wed 24-04-19 |
38,39 |
Builder,Civil Engineer |
$3,040.00 |
Carpentry works of the Building |
2 wks |
Thu 25-04-19 |
Wed 08-05-19 |
42 |
Painter and Decorator |
$1,200.00 |
Setting Steel |
4 wks |
Thu 02-05-19 |
Wed 29-05-19 |
40 |
Builder,Department of Construction |
$5,760.00 |
Framing of deck for the first floor of the Building |
2 wks |
Thu 30-05-19 |
Wed 12-06-19 |
44 |
Construction Subcontractor |
$1,440.00 |
Framing of walls for the first floor of the Building |
2 wks |
Thu 13-06-19 |
Wed 26-06-19 |
45 |
Construction Subcontractor,Department of Construction |
$3,040.00 |
Framing of Deck for the second floor of the Building |
2 wks |
Thu 27-06-19 |
Wed 10-07-19 |
45,46 |
Builder,Construction Subcontractor,Department of Construction |
$4,320.00 |
Framing of walls for the second floor of the Building |
2 wks |
Thu 11-07-19 |
Wed 24-07-19 |
47 |
Builder,Department of Construction,Department of Sales |
$4,480.00 |
Setting up of Roof trusses |
3 wks |
Thu 25-07-19 |
Wed 14-08-19 |
47,48 |
Mechanical Subcontractor |
$2,160.00 |
Framing of Roof |
2 wks |
Thu 15-08-19 |
Wed 28-08-19 |
49 |
Builder,Mechanical Subcontractor |
$2,720.00 |
Installation of Plywood for Roof for the Building |
2 wks |
Thu 29-08-19 |
Wed 11-09-19 |
50 |
Builder,Mechanical Subcontractor,Painter and Decorator |
$3,920.00 |
Installation of Doors and Windows of the Building |
1 wk |
Thu 29-08-19 |
Wed 04-09-19 |
50 |
Builder,Mechanical Subcontractor |
$1,360.00 |
Framing the Basement |
2 wks |
Thu 21-03-19 |
Wed 03-04-19 |
37 |
Builder,Construction Subcontractor,Department of Construction,Mechanical Subcontractor |
$5,760.00 |
Concrete Slab Installation |
5 wks |
Thu 04-04-19 |
Wed 08-05-19 |
$3,880.00 |
||
Preparation of Basement Slab of the Building |
2 wks |
Thu 04-04-19 |
Wed 17-04-19 |
53 |
Builder |
$1,280.00 |
Termite Treatment for the Slab |
2 wks |
Thu 18-04-19 |
Wed 01-05-19 |
55 |
Pest Controller |
$0.00 |
Detailed Inspection of the slabs |
1 wk |
Thu 02-05-19 |
Wed 08-05-19 |
55,56 |
Civil Engineer,Construction Subcontractor,Project Manager |
$2,600.00 |
H.V.A.C |
2 wks |
Thu 09-05-19 |
Wed 22-05-19 |
$1,440.00 |
||
Layout and Measurement of the HVAC |
1 wk |
Thu 09-05-19 |
Wed 15-05-19 |
57 |
Mechanical Subcontractor |
$720.00 |
HVAC Set up |
1 wk |
Thu 16-05-19 |
Wed 22-05-19 |
59 |
Mechanical Subcontractor |
$720.00 |
Plumbing Rough-in |
2 wks |
Thu 23-05-19 |
Wed 05-06-19 |
$1,200.00 |
||
Plumbing Rough-in |
1 wk |
Thu 23-05-19 |
Wed 29-05-19 |
60 |
Plumber |
$600.00 |
Inspection of Plumbing Rough-in |
1 wk |
Thu 30-05-19 |
Wed 05-06-19 |
62 |
Plumber |
$600.00 |
Electric Rough-in |
3 wks |
Thu 04-04-19 |
Wed 24-04-19 |
$1,440.00 |
||
Setting up of Electric Boxes |
2 wks |
Thu 04-04-19 |
Wed 17-04-19 |
53 |
Electrician |
$960.00 |
Electrical Rough-wire |
1 wk |
Thu 18-04-19 |
Wed 24-04-19 |
65 |
Electrician |
$480.00 |
Rough-ins |
1 wk |
Thu 18-04-19 |
Wed 24-04-19 |
$2,160.00 |
||
Telephone Rough-ins |
1 wk |
Thu 18-04-19 |
Wed 24-04-19 |
65 |
Mechanical Subcontractor |
$720.00 |
Audio Visual Rough-in |
1 wk |
Thu 18-04-19 |
Wed 24-04-19 |
65 |
Mechanical Subcontractor |
$720.00 |
Rough-in of Alarm System |
1 wk |
Thu 18-04-19 |
Wed 24-04-19 |
65 |
Mechanical Subcontractor |
$720.00 |
Roofing |
2 wks |
Thu 18-04-19 |
Wed 01-05-19 |
$4,080.00 |
||
Implementing Roofing Paper |
1 wk |
Thu 18-04-19 |
Wed 24-04-19 |
55 |
Department of Construction,Builder,Mason |
$2,040.00 |
Implementing Roof Shingles |
1 wk |
Thu 25-04-19 |
Wed 01-05-19 |
72 |
Builder,Department of Construction,Mason |
$2,040.00 |
Exterior Finishes |
2 wks |
Thu 18-04-19 |
Wed 01-05-19 |
$2,480.00 |
||
Exterior Trim |
1 wk |
Thu 18-04-19 |
Wed 24-04-19 |
55 |
Builder,Mason |
$1,240.00 |
Brick Work |
1 wk |
Thu 25-04-19 |
Wed 01-05-19 |
75 |
Builder,Mason |
$1,240.00 |
Insulation |
18 wks |
Thu 11-04-19 |
Wed 14-08-19 |
$10,080.00 |
||
Draft & Fire Set up |
1 wk |
Thu 11-04-19 |
Wed 17-04-19 |
38 |
Builder,Hardware Subcontractor |
$1,240.00 |
Insulation of Batt |
1 wk |
Thu 11-04-19 |
Wed 17-04-19 |
38 |
Builder,Hardware Subcontractor |
$1,240.00 |
Inspection of BGE Energy |
1 wk |
Thu 11-04-19 |
Wed 17-04-19 |
38 |
Builder,Hardware Subcontractor |
$1,240.00 |
Floor Finishes |
2 wks |
Thu 11-07-19 |
Wed 24-07-19 |
47 |
Builder,Department of Construction |
$2,880.00 |
Implementing Ceramic Tiles |
2 wks |
Thu 25-07-19 |
Wed 07-08-19 |
81 |
Builder,Department of Construction |
$2,880.00 |
Installation of Carpet |
1 wk |
Thu 08-08-19 |
Wed 14-08-19 |
82 |
Painter and Decorator |
$600.00 |
Painting |
6 wks |
Thu 25-07-19 |
Wed 04-09-19 |
$3,600.00 |
||
Trim Coating |
2 wks |
Thu 25-07-19 |
Wed 07-08-19 |
48 |
Painter and Decorator |
$1,200.00 |
Drywall Coating |
2 wks |
Thu 08-08-19 |
Wed 21-08-19 |
85 |
Painter and Decorator |
$1,200.00 |
Doors and Windows Coating |
2 wks |
Thu 22-08-19 |
Wed 04-09-19 |
86 |
Painter and Decorator |
$1,200.00 |
Hardware installation |
2 wks |
Thu 05-09-19 |
Wed 18-09-19 |
$3,360.00 |
||
Door Installation |
1 wk |
Thu 05-09-19 |
Wed 11-09-19 |
87 |
Construction Subcontractor |
$720.00 |
Hardware installation of Bathrooms |
1 wk |
Thu 12-09-19 |
Wed 18-09-19 |
89 |
Construction Subcontractor,Hardware Subcontractor |
$1,320.00 |
Mirrors installation |
1 wk |
Thu 12-09-19 |
Wed 18-09-19 |
89 |
Construction Subcontractor,Hardware Subcontractor |
$1,320.00 |
Cleaning |
3 wks |
Thu 12-09-19 |
Wed 02-10-19 |
$1,200.00 |
||
Building Windows Cleaning |
1 wk |
Thu 12-09-19 |
Wed 18-09-19 |
89 |
Cleaning Staff |
$400.00 |
Rough Cleaning |
2 wks |
Thu 19-09-19 |
Wed 02-10-19 |
93 |
Cleaning Staff |
$800.00 |
Project Closure |
7 wks |
Thu 03-10-19 |
Wed 20-11-19 |
$8,400.00 |
||
Project Handover |
3 wks |
Thu 03-10-19 |
Wed 23-10-19 |
94 |
Department of Sales,Project Manager |
$5,400.00 |
Client’s Agreement |
2 wks |
Thu 24-10-19 |
Wed 06-11-19 |
96 |
Client |
$0.00 |
Documentation Review for the Building and Approval |
1 wk |
Thu 07-11-19 |
Wed 13-11-19 |
96,97 |
Project Manager |
$1,000.00 |
Resource Release |
2 wks |
Thu 07-11-19 |
Wed 20-11-19 |
97 |
Project Manager |
$2,000.00 |
Task Name |
Expected Start |
Time and Cost Management in Building Construction |
Thu 08-03-18 |
Building Construction by ADCO Constructions |
Thu 08-03-18 |
Milestone 1: Completing the Contract Plans |
Wed 18-04-18 |
Milestone 2: Completing the Documentation Review for the Building and Approval |
Wed 13-06-18 |
Milestone 3: Completion of Bids and Contracts |
Wed 19-12-18 |
Milestone 4: Completion of Foundation |
Wed 03-04-19 |
Milestone 5: Completion of Concrete Slab Installation |
Wed 08-05-19 |
Milestone 6: Completion of HVAC |
Wed 22-05-19 |
Milestone 7: Completion of Plumbing Rough-in |
Wed 05-06-19 |
Milestone 8: Completion of Electric Rough-wire |
Wed 24-04-19 |
Milestone 9: Completion of Rough-in |
Wed 24-04-19 |
Milestone 10: Completion of Roofing |
Wed 01-05-19 |
Milestone 11: Completing the Exterior Finishes |
Wed 01-05-19 |
Milestone 12: Completion of Insulation |
Wed 14-08-19 |
Milestone 15: Completion of Cleaning |
Wed 02-10-19 |
Milestone 16: Completion of Project |
Wed 20-11-19 |
WBS |
Task Name |
Duration |
Start |
Finish |
0 |
Time and Cost Management in Building Construction |
89 wks |
Thu 08-03-18 |
Wed 20-11-19 |
1 |
Building Construction by ADCO Constructions |
89 wks |
Thu 08-03-18 |
Wed 20-11-19 |
1.1 |
Contract Plans |
7 wks |
Thu 08-03-18 |
Wed 25-04-18 |
1.2 |
Documentation Review for the Building and Approval |
8 wks |
Thu 26-04-18 |
Wed 20-06-18 |
1.3 |
Bids and Contracts |
31 wks |
Thu 17-05-18 |
Wed 19-12-18 |
1.4 |
Foundation |
40 wks |
Thu 06-12-18 |
Wed 11-09-19 |
1.5 |
Concrete Slab Installation |
5 wks |
Thu 04-04-19 |
Wed 08-05-19 |
1.6 |
H.V.A.C |
2 wks |
Thu 09-05-19 |
Wed 22-05-19 |
1.7 |
Plumbing Rough-in |
2 wks |
Thu 23-05-19 |
Wed 05-06-19 |
1.8 |
Electric Rough-in |
3 wks |
Thu 04-04-19 |
Wed 24-04-19 |
1.9 |
Rough-ins |
1 wk |
Thu 18-04-19 |
Wed 24-04-19 |
1.10 |
Roofing |
2 wks |
Thu 18-04-19 |
Wed 01-05-19 |
1.11 |
Exterior Finishes |
2 wks |
Thu 18-04-19 |
Wed 01-05-19 |
1.12 |
Insulation |
18 wks |
Thu 11-04-19 |
Wed 14-08-19 |
1.13 |
Painting |
6 wks |
Thu 25-07-19 |
Wed 04-09-19 |
1.14 |
Hardware installation |
2 wks |
Thu 05-09-19 |
Wed 18-09-19 |
1.15 |
Cleaning |
3 wks |
Thu 12-09-19 |
Wed 02-10-19 |
1.16 |
Project Closure |
7 wks |
Thu 03-10-19 |
Wed 20-11-19 |
References
Ajayi, S. O., & Oyedele, L. O. (2018). Waste-efficient materials procurement for construction projects: A structural equation modelling of critical success factors. Waste Management.
Akomah, B. B., & Jackson, E. N. (2016). Factors Affecting the Performance of Contractors on Building Construction Projects: Central Region, Ghana. International Journal of Innovative Research and Development, 5(10).
Azhar, S., Khalfan, M., & Maqsood, T. (2015). Building information modelling (BIM): now and beyond. Construction Economics and Building, 12(4), 15-28.
Bakshan, A., Srour, I., Chehab, G., & El-Fadel, M. (2015). A field based methodology for estimating waste generation rates at various stages of construction projects. Resources, Conservation and Recycling, 100, 70-80.
Bakshan, A., Srour, I., Chehab, G., & El-Fadel, M. (2015). A field based methodology for estimating waste generation rates at various stages of construction projects. Resources, Conservation and Recycling, 100, 70-80.
Belay, M. D., Tekeste, E. A., & Ambo, S. A. (2017). Investigation of Major Success Factors on Building Construction Projects Management System in Addis Ababa, Ethiopia. American Journal of Civil Engineering, 5(3), 155-163.
Cao, D., Li, H., Wang, G., & Zhang, W. (2016). Linking the motivations and practices of design organizations to implement building information modeling in construction projects: Empirical study in China. Journal of Management in Engineering, 32(6), 04016013.
Cao, D., Wang, G., Li, H., Skitmore, M., Huang, T., & Zhang, W. (2015). Practices and effectiveness of building information modelling in construction projects in China. Automation in Construction, 49, 113-122.
Chen, Y. Q., Zhang, S. J., Liu, L. S., & Hu, J. (2015). Risk perception and propensity in bid/no-bid decision-making of construction projects. Engineering, Construction and Architectural Management, 22(1), 2-20.
Choi, B., Lee, H. S., Park, M., Cho, Y. K., & Kim, H. (2014). Framework for work-space planning using four-dimensional BIM in construction projects. Journal of Construction Engineering and Management, 140(9), 04014041.
Collins, W., Parrish, K., & Gibson Jr, G. E. (2017). Development of a project scope definition and assessment tool for small industrial construction projects. Journal of Management in Engineering, 33(4), 04017015.
Enshassi, A., Ayash, A., & Mohamed, S. (2018). Key barriers to the implementation of energy management strategies in building construction projects. International Journal of Building Pathology and Adaptation, (just-accepted), 00-00.
Francom, T. C., & El Asmar, M. (2015). Project quality and change performance differences associated with the use of building information modeling in design and construction projects: Univariate and multivariate analyses. Journal of Construction Engineering and Management, 141(9), 04015028.
Fung, I. W. H. (2015). Off-campus Experiential e-Learning for Students during Construction Site Visits: Development of Innovative Mobile App in Safety Audit for Civil and Construction Projects.
He, Q., Luo, L., Hu, Y., & Chan, A. P. (2015). Measuring the complexity of mega construction projects in China—A fuzzy analytic network process analysis. International Journal of Project Management, 33(3), 549-563.
Heravi, A., Coffey, V., & Trigunarsyah, B. (2015). Evaluating the level of stakeholder involvement during the project planning processes of building projects. International Journal of Project Management, 33(5), 985-997.
Hong, J., Shen, G. Q., Feng, Y., Lau, W. S. T., & Mao, C. (2015). Greenhouse gas emissions during the construction phase of a building: a case study in China. Journal of Cleaner Production, 103, 249-259.
Hu, Z. Z., Zhang, J. P., Yu, F. Q., Tian, P. L., & Xiang, X. S. (2016). Construction and facility management of large MEP projects using a multi-Scale building information model. Advances in Engineering Software, 100, 215-230.
Hwang, B. G., Zhao, X., & Toh, L. P. (2014). Risk management in small construction projects in Singapore: Status, barriers and impact. International Journal of Project Management, 32(1), 116-124.
Hyari, K. H., El-Mashaleh, M. S., & Rababeh, S. M. (2015). Framework for Managing the Traffic Impacts of Building Construction Projects. Journal of Construction in Developing Countries, 20(2), 97.
Islam, M. S., Nepal, M. P., Skitmore, M., & Attarzadeh, M. (2017). Current research trends and application areas of fuzzy and hybrid methods to the risk assessment of construction projects. Advanced Engineering Informatics, 33, 112-131.
Islam, M. S., Razwanul, I., & Mahmud, M. T. (2017). Safety Practices and Causes of Fatality in Building Construction Projects: A Case Study for Bangladesh. Jordan Journal of Civil Engineering, 11(2).
Jadhav, S., & Patil, U. (2015). Rework in Building Construction Projects: A Review. International Journal of Global Technology Initiatives, 4(1), A25-A29.
Jung, M., Park, M., Lee, H. S., & Chi, S. (2017). Agent-Based Lift System Simulation Model for High-Rise Building Construction Projects. Journal of Computing in Civil Engineering, 31(6), 04017064.
Jung, M., Park, M., Lee, H. S., & Chi, S. (2018). Multimethod Supply Chain Simulation Model for High-Rise Building Construction Projects. Journal of Computing in Civil Engineering, 32(3), 04018007.
Kannan, J. R., Rai, A., Szpytko, J., & Pandya, Y. C. (2017). Project Zeus: video based behavioural modelling of non-linear transportation system for improved planning &urban construction projects. Journal of KONES, 24.
Kelly, J., Male, S., & Graham, D. (2014). Value management of construction projects. John Wiley & Sons.
Kerosuo, H., Miettinen, R., Paavola, S., Mäki, T., & Korpela, J. (2015). Challenges of the expansive use of Building Information Modeling (BIM) in construction projects. Production, 25(2), 289-297.
Kibert, C. J. (2016). Sustainable construction: green building design and delivery. John Wiley & Sons.
Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2015). Factors affecting schedule delay, cost overrun, and quality level in public construction projects. Journal of Management in Engineering, 32(1), 04015032.
Lawal, A. A. (2017). Stochastic Risk Analysis Framework for Building Construction Projects. World Academy of Science, Engineering and Technology, International Journal of Civil, Environmental, Structural, Construction and Architectural Engineering, 10(11), 1478-1482.
Lim, B. T., & Loosemore, M. (2017). The effect of inter-organizational justice perceptions on organizational citizenship behaviors in construction projects. International Journal of Project Management, 35(2), 95-106.
Lindgren, J., Widén, K., & Emmitt, S. (2018). Construction projects as mechanisms for knowledge integration: mechanisms and effects when diffusing a systemic innovation. Engineering Construction and Architectural Management.
Love, P. E., Teo, P., & Morrison, J. (2018). Unearthing the nature and interplay of quality and safety in construction projects: An empirical study. Safety Science, 103, 270-279.
Mahamid, I. (2016). Factors contributing to poor performance in construction projects: studies of Saudi Arabia. Australian Journal of Multi-Disciplinary Engineering, 12(1), 27-38.
Mancini, M., Wang, X., Skitmore, M., & Issa, R. (2017). Editorial for IJPM special issue on advances in building information modeling (BIM) for construction projects. International Journal of Project Management, 35(4), 656-657.
Martínez-Aires, M. D., Rubio Gámez, M. C., & Gibb, A. (2016). The impact of occupational health and safety regulations on prevention through design in construction projects: Perspectives from Spain and the United Kingdom. Work, 53(1), 181-191.
Marzouk, M. M., & El-Rasas, T. I. (2014). Analyzing delay causes in Egyptian construction projects. Journal of advanced research, 5(1), 49-55.
Mohd Nawi, M. N., Lee, A., Othman Mydin, M. A., Osman, W. N., & Rofie, M. K. (2018). Supply Chain Management (SCM): Disintegration Team Factors in Malaysian Industrialised Building System (IBS) Construction Projects. International Journal of Supply Chain Management, 7(1), 140-143.
Mok, K. Y., Shen, G. Q., & Yang, J. (2015). Stakeholder management studies in mega construction projects: A review and future directions. International Journal of Project Management, 33(2), 446-457.
Montaser, A., & Moselhi, O. (2014). RFID indoor location identification for construction projects. Automation in Construction, 39, 167-179.
Muhwezi, L., Acai, J., & Otim, G. (2014). An assessment of the factors causing delays on building construction projects in Uganda. International Journal of Construction Engineering and Management, 3(1), 13-23.
Muhwezi, L., Acai, J., & Otim, G. (2014). An assessment of the factors causing delays on building construction projects in Uganda. International Journal of Construction Engineering and Management, 3(1), 13-23.
Musa, A. M., Abanda, F. H., Oti, A. H., Tah, J. H. M., & Boton, C. (2016). The Potential of 4D modelling software systems for risk management in construction projects.
Naoum, S. (2015). Productivity in construction projects. Design Economics for the Built Environment: Impact of Sustainability on Project Evaluation, 93-106.
Nasirzadeh, F., Khanzadi, M., & Rezaie, M. (2014). Dynamic modeling of the quantitative risk allocation in construction projects. International Journal of Project Management, 32(3), 442-451.
Nawi, M. N. M., Lee, A., Azman, M. N. A., & Kamar, K. A. M. (2014). Fragmentation issue in Malaysian industrialised building system (IBS) projects. Journal of Engineering Science and Technology, 9(1), 97-106.
Ngacho, C., & Das, D. (2014). A performance evaluation framework of development projects: An empirical study of Constituency Development Fund (CDF) construction projects in Kenya. International Journal of Project Management, 32(3), 492-507.
Odimabo, O. O., Oduoza, C., & Suresh, S. (2017). Methodology for Project Risk Assessment of Building Construction Projects Using Bayesian Belief Networks. International Journal of Construction Engineering and Management.
Petri, I., Beach, T., Rana, O. F., & Rezgui, Y. (2017). Coordinating multi-site construction projects using federated clouds. Automation in Construction, 83, 273-284.
Pham, H., Kim, S. Y., Luu, T. V., & Lam, P. S. (2017). Causal Relationships among Factors Affecting the Buildability in Executing Construction Projects in Vietnam. Proceedings of Engineering and Technology Innovation, 5, 31-36.
Pirzadeh, P., Lingard, H., Blismas, N., Mills, T., & Kleiner, B. (2015). Proactive evaluation of occupational health and safety performance in construction projects using the hierarchy of controls concept. In CIB W099: Safety and Health in Construction (pp. 438-448). CIB.
Rao, B. P., Shekar, S. C., Jaiswal, N., Jain, A., & Saxena, A. D. (2016). Delay Analysis of Construction Projects. Journal of Information Technology and Economic Development, 7(1), 15.
Reyes, J. P., San-José, J. T., Cuadrado, J., & Sancibrian, R. (2014). Health & Safety criteria for determining the sustainable value of construction projects. Safety science, 62, 221-232.
Rumane, A. R. (2016). Quality management in construction projects. CRC Press.
Ryu, H., Son, K., & Kim, J. M. (2016). Loss prediction model for building construction projects using insurance claim payout. Journal of Asian Architecture and Building Engineering, 15(3), 441-446.
Salah, A., & Moselhi, O. (2015). Contingency modelling for construction projects using fuzzy-set theory. Engineering, Construction and Architectural Management, 22(2), 214-241.
Sansakorn, P., & An, M. (2015). Development of Risk Assessment and Occupational Safety Management Model for Building Construction Projects. World Academy of Science, Engineering and Technology, International Journal of Civil, Environmental, Structural, Construction and Architectural Engineering, 9(9), 1240-1247.
Schaufelberger, J. E., & Holm, L. (2017). Management of construction projects: A constructor’s perspective. Taylor & Francis.
Selvakumar, S., & Jeykumar, R. K. C. (2015). Environmental impact assessment for building construction Projects. Advanced Science and Technology Letters, 89, 15-19.
Senouci, A., Alsarraj, A., Gunduz, M., & Eldin, N. (2017). Analysis of change orders in Qatari construction projects. International Journal of Construction Management, 17(4), 280-292.
Senouci, A., Ismail, A. A., & Eldin, N. (2016, June). Time and Cost Overrun in Public Construction Projects in Qatar’. In Creative Construction Conference, Budapest (pp. 25-28).
Sethuraman, V., Perera, B. A. K. S., & Sumanarathna, D. M. G. A. N. M. (2016, April). Factors influencing procurement adoption in construction: Building vs infrastructure projects. In Moratuwa Engineering Research Conference (MERCon), 2016 (pp. 277-282). IEEE.
Sha’ar, K. Z., Assaf, S. A., Bambang, T., Babsail, M., & Fattah, A. A. E. (2017). Design–construction interface problems in large building construction projects. International Journal of Construction Management, 17(3), 238-250.
Shahu, R. B. (2016). Flexibility Cost and its Application for Construction Projects. EuroEconomica, 35(1).
Simpeh, E. K., Ndihokubwayo, R., Love, P. E., & Thwala, W. D. (2015). A rework probability model: a quantitative assessment of rework occurrence in construction projects. International Journal of Construction Management, 15(2), 109-116.
Tabassi, A. A., Argyropoulou, M., Roufechaei, K. M., & Argyropoulou, R. (2016). Leadership Behavior of Project Managers in Sustainable Construction Projects. Procedia Computer Science, 100, 724-730.
Tezel, A., Gosling, J., Kumar, M., & Koskela, L. (2017). Transition from Engineer-to-Order (EtO) to Assembly-to-Order (AtO) in Civil Infrastructure Projects: An Exploration of the Highways Supply Chain.
Tezel, B. A., Aziz, Z. U. H., Koskela, L. J., & Tzortzopoulos Fazenda, P. (2016). Visual management condition in highways construction projects in England.
Udawatta, N., Zuo, J., Chiveralls, K., & Zillante, G. (2015). Improving waste management in construction projects: An Australian study. Resources, Conservation and Recycling, 101, 73-83.
Victoria, M. F., Perera, S., & Davies, A. (2016). Design economics for dual currency management in construction projects.
Yang, J. B., & Chen, C. C. (2015). Causes of Budget Changes in Building Construction Projects: An Empirical Study in Taiwan. The Engineering Economist, 60(1), 1-21.
Yang, R. J., Zou, P. X., & Wang, J. (2016). Modelling stakeholder-associated risk networks in green building projects. International journal of project management, 34(1), 66-81.
Yeo, Z., Ng, R., & Song, B. (2016). Technique for quantification of embodied carbon footprint of construction projects using probabilistic emission factor estimators. Journal of Cleaner Production, 119, 135-151.
Yeo, Z., Ng, R., & Song, B. (2016). Technique for quantification of embodied carbon footprint of construction projects using probabilistic emission factor estimators. Journal of Cleaner Production, 119, 135-151.
Yeung, T., Ng, A., & Wong, P. (2017). Essential site coordination problems in Hong Kong building projects. In AUBEA 2017 (pp. 189-197). RMIT University.
Y?lmaz, M., & Kan?t, R. (2018). A practical tool for estimating compulsory OHS costs of residential building construction projects in Turkey. Safety Science, 101, 326-331.
Zhang, S., Sulankivi, K., Kiviniemi, M., Romo, I., Eastman, C. M., & Teizer, J. (2015). BIM-based fall hazard identification and prevention in construction safety planning. Safety science, 72, 31-45.
Zhang, X., Wu, Y., Shen, L., & Skitmore, M. (2014). A prototype system dynamic model for assessing the sustainability of construction projects. International Journal of Project Management, 32(1), 66-76.
Zolfani, S. H., Pourhossein, M., Yazdani, M., & Zavadskas, E. K. (2017). Evaluating construction projects of hotels based on environmental sustainability with MCDM framework. Alexandria Engineering Journal.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download