This assignment is aimed at providing essential scheduling, cost, and resource management options based on building and construction operations. It is a major important aspect that suitable project management concepts and techniques are relevant for formulating effective operational decisions. The project management principles are efficient for implementing more advanced yet innovative list of operations (Brown et al. 2016). This particular assignment is useful for providing appropriate business decision-making and proper situation analysis with budget and resource management (Everett et al. 2017). Milestones and scheduling is added in the assignment for providing overview of the activities and how those should be completed to reach towards the business objectives.
Furthermore, the assignment is prepared to study a particular case scenario for Vopak tank farm, Houston Ship Channel. Main deliverable is to re-construct and repair existing three tanks in Vopak tank farm, Houston Ship Channel. Moreover, the critical evaluation is conducted in the assignment for better insights of project management application and achievement of deliverables.
Stakeholder Name |
Estimated Cost |
$2,208.00 |
|
$2,040.00 |
|
Construction Engineers |
$560.00 |
$240.00 |
|
Technicians |
$448.00 |
Supervisors |
$648.00 |
Contractor |
$1,064.00 |
Workers |
$1,760.00 |
Government |
$0.00 |
Table 1: Budget planning
(Source: Created by author)
Budget planning is prepared as per some assumptions in practice for projects. The assumptions are mentioned as following:
Name |
Start |
Finish |
Remaining Work |
Project Manager |
Thu 01-06-17 |
Tue 14-11-17 |
184 hrs |
Planning Manager |
Mon 05-06-17 |
Tue 11-07-17 |
136 hrs |
Construction Engineers |
Mon 19-06-17 |
Tue 27-06-17 |
56 hrs |
Construction Architects |
Thu 10-08-17 |
Mon 14-08-17 |
24 hrs |
Technicians |
Fri 29-09-17 |
Fri 10-11-17 |
56 hrs |
Supervisors |
Tue 19-09-17 |
Mon 13-11-17 |
72 hrs |
Contractor |
Fri 21-07-17 |
Mon 30-10-17 |
152 hrs |
Workers |
Tue 15-08-17 |
Wed 08-11-17 |
352 hrs |
Government |
Wed 15-11-17 |
Wed 15-11-17 |
8 hrs |
Table 2: List of resources and their work hours as per Scheduling
(Source: Created by author)
The work assumptions for the project are taken as:
The schedule planning is prepared along with following timeline setup (Love et al. 2014). The timeline shows major activities along with setting suitable time with sub-activities.
Task Name |
Duration |
Start |
Finish |
Tankers Construction |
121 days |
Thu 01-06-17 |
Thu 16-11-17 |
Project Initialization |
12 days |
Thu 01-06-17 |
Fri 16-06-17 |
Idea of Construction proposal |
2 days |
Thu 01-06-17 |
Fri 02-06-17 |
Project Charter preparation |
5 days |
Mon 05-06-17 |
Fri 09-06-17 |
Charter submission to government and sponsors |
2 days |
Mon 12-06-17 |
Tue 13-06-17 |
Operation Approval |
3 days |
Wed 14-06-17 |
Fri 16-06-17 |
Project Planning |
24 days |
Mon 19-06-17 |
Thu 20-07-17 |
Construction requirement analysis |
7 days |
Mon 19-06-17 |
Tue 27-06-17 |
Resource collection |
15 days |
Wed 28-06-17 |
Tue 18-07-17 |
Project plan preparation |
10 days |
Wed 28-06-17 |
Tue 11-07-17 |
Plan review activity |
2 days |
Wed 19-07-17 |
Thu 20-07-17 |
Construction of Site |
42 days |
Fri 21-07-17 |
Mon 18-09-17 |
Site leveling |
6 days |
Fri 21-07-17 |
Fri 28-07-17 |
Site cementing |
8 days |
Mon 31-07-17 |
Wed 09-08-17 |
Infrastructure implementation plan |
3 days |
Thu 10-08-17 |
Mon 14-08-17 |
Boundary construction |
10 days |
Tue 15-08-17 |
Mon 28-08-17 |
Wall and roof construction |
15 days |
Tue 29-08-17 |
Mon 18-09-17 |
Construction of Tankers |
39 days |
Tue 19-09-17 |
Fri 10-11-17 |
Tanker specification analysis |
3 days |
Tue 19-09-17 |
Thu 21-09-17 |
Tank base construction |
5 days |
Fri 22-09-17 |
Thu 28-09-17 |
Assembling base parts |
2 days |
Fri 29-09-17 |
Mon 02-10-17 |
Installation of shell plates |
3 days |
Tue 03-10-17 |
Thu 05-10-17 |
Piping of drainage |
7 days |
Fri 06-10-17 |
Mon 16-10-17 |
Wall coating |
3 days |
Tue 17-10-17 |
Thu 19-10-17 |
Accessories Installation |
2 days |
Fri 20-10-17 |
Mon 23-10-17 |
Platform and rail building |
5 days |
Tue 24-10-17 |
Mon 30-10-17 |
Connection piping for three tanks |
4 days |
Tue 31-10-17 |
Fri 03-11-17 |
Preparation of Passages |
3 days |
Mon 06-11-17 |
Wed 08-11-17 |
Environmental Safety Implementation |
2 days |
Thu 09-11-17 |
Fri 10-11-17 |
Project Closure |
4 days |
Mon 13-11-17 |
Thu 16-11-17 |
Tanker testing |
1 day |
Mon 13-11-17 |
Mon 13-11-17 |
Approval of deliverables |
1 day |
Tue 14-11-17 |
Tue 14-11-17 |
Government approval |
1 day |
Wed 15-11-17 |
Wed 15-11-17 |
Functionality confirmation |
1 day |
Thu 16-11-17 |
Thu 16-11-17 |
Stakeholder sign-off |
0 days |
Thu 16-11-17 |
Thu 16-11-17 |
Table 3: Schedule Planning
(Source: Created by author)
Figure 4: Gantt chart
(Source: Created by author)
The model provides a framework for the project activities in order to deliver quality system to meet with business expectations and manage of decisions. The life cycle consists of five phrases such as planning, analysis, design, implementation and maintenance. This particular project work is also developed with use of this life cycle model (Sippel et al., 2015). The benefits of this model are that formal review is done at end of each of the phrases. It creates system documentation. The documentation makes sure that the system requirements are traced with the business requirements. Schedule development becomes easier as it helps to manage the activities of the project (Brown et al. 2016). Therefore, use of Ms Project becomes easier with use of SDLC functions. Disadvantage is that documentation is expensive and it is time consuming. The users are not able to evaluate the products as well as assess of the particular product if they meet with business requirements. The project objectives should meet with the client’s requirements.
Ms Project is used for this particular project work for developing the plan, assigning of the resources to their respective tasks, tracking the project progress, managing the project budget and analyzing the workloads. It creates of budget for each of the project activities as well as rate of resources (Everett et al. 2017). As well as the resources are assigned to the tasks, then there is a calculation of cost based on their work rates. In order to calculate the total time taken to complete the project, Gantt chart is used for evaluation of the project activities. Project timeline helps to estimate the total duration and track the project progress. As compared to other tool, Ms Project usage is very efficient to meet with project objectives. With use of this particular Ms-Project software, time phase budget, WBS, Gantt chart as well as critical path are analyzed easily.
Resource planning is prepared while considering each activity along with durations (Loh and Loh 2016). The primary resources are included in the project as Project Manager, Planning Manager, Construction Engineers, Construction Architects, Technicians, Supervisors, Contractor, Workers, and Government.
Task Name |
Duration |
Start |
Finish |
Resource Names |
Tankers Construction |
121 days |
Thu 01-06-17 |
Thu 16-11-17 |
|
Project Initialization |
12 days |
Thu 01-06-17 |
Fri 16-06-17 |
|
Idea of Construction proposal |
2 days |
Thu 01-06-17 |
Fri 02-06-17 |
Project Manager |
Project Charter preparation |
5 days |
Mon 05-06-17 |
Fri 09-06-17 |
Planning Manager |
Charter submission to government and sponsors |
2 days |
Mon 12-06-17 |
Tue 13-06-17 |
Planning Manager |
Operation Approval |
3 days |
Wed 14-06-17 |
Fri 16-06-17 |
Project Manager |
Project Planning |
24 days |
Mon 19-06-17 |
Thu 20-07-17 |
|
Construction requirement analysis |
7 days |
Mon 19-06-17 |
Tue 27-06-17 |
Construction Engineers |
Resource collection |
15 days |
Wed 28-06-17 |
Tue 18-07-17 |
Project Manager |
Project plan preparation |
10 days |
Wed 28-06-17 |
Tue 11-07-17 |
Planning Manager |
Plan review activity |
2 days |
Wed 19-07-17 |
Thu 20-07-17 |
Project Manager |
Construction of Site |
42 days |
Fri 21-07-17 |
Mon 18-09-17 |
|
Site leveling |
6 days |
Fri 21-07-17 |
Fri 28-07-17 |
Contractor |
Site cementing |
8 days |
Mon 31-07-17 |
Wed 09-08-17 |
Contractor |
Infrastructure implementation plan |
3 days |
Thu 10-08-17 |
Mon 14-08-17 |
Construction Architects |
Boundary construction |
10 days |
Tue 15-08-17 |
Mon 28-08-17 |
Workers |
Wall and roof construction |
15 days |
Tue 29-08-17 |
Mon 18-09-17 |
Workers |
Construction of Tankers |
39 days |
Tue 19-09-17 |
Fri 10-11-17 |
|
Tanker specification analysis |
3 days |
Tue 19-09-17 |
Thu 21-09-17 |
Supervisors |
Tank base construction |
5 days |
Fri 22-09-17 |
Thu 28-09-17 |
Workers |
Assembling base parts |
2 days |
Fri 29-09-17 |
Mon 02-10-17 |
Technicians |
Installation of shell plates |
3 days |
Tue 03-10-17 |
Thu 05-10-17 |
Technicians |
Piping of drainage |
7 days |
Fri 06-10-17 |
Mon 16-10-17 |
Workers |
Wall coating |
3 days |
Tue 17-10-17 |
Thu 19-10-17 |
Supervisors |
Accessories Installation |
2 days |
Fri 20-10-17 |
Mon 23-10-17 |
Supervisors |
Platform and rail building |
5 days |
Tue 24-10-17 |
Mon 30-10-17 |
Contractor |
Connection piping for three tanks |
4 days |
Tue 31-10-17 |
Fri 03-11-17 |
Workers |
Preparation of Passages |
3 days |
Mon 06-11-17 |
Wed 08-11-17 |
Workers |
Environmental Safety Implementation |
2 days |
Thu 09-11-17 |
Fri 10-11-17 |
Technicians |
Project Closure |
4 days |
Mon 13-11-17 |
Thu 16-11-17 |
|
Tanker testing |
1 day |
Mon 13-11-17 |
Mon 13-11-17 |
Supervisors |
Approval of deliverables |
1 day |
Tue 14-11-17 |
Tue 14-11-17 |
Project Manager |
Government approval |
1 day |
Wed 15-11-17 |
Wed 15-11-17 |
Government |
Functionality confirmation |
1 day |
Thu 16-11-17 |
Thu 16-11-17 |
|
Stakeholder sign-off |
0 days |
Thu 16-11-17 |
Thu 16-11-17 |
Table 5: Resource Planning and allocation
(Source: Created by author)
Conclusion
From this assignment, the conclusion can be drawn that use of project management techniques and tools can increase development with faster outcomes. The assignment stated that major outcomes can be operational with project once, the approval is confirmed. Principles of construction industry are supplemented with suitable operations and activities.
Brown, W., Evans, G. and Carpenter, L., 2016, July. Case Histories of the Resolution of Bolted Joint Leakage in the Oil and Gas Industry. In ASME 2016 Pressure Vessels and Piping Conference (pp. V003T03A006-V003T03A006). American Society of Mechanical Engineers.
Centner, T.J. and Petetin, L., 2015. Permitting program with best management practices for shale gas wells to safeguard public health. Journal of environmental management, 163, pp.174-183.
Everett, D., Mink, R., Linn, T. and Wood, J., 2017. Designing to Sample the Unknown: Lessons from OSIRIS-REx Project Systems Engineering.
Guerin, T., 2014. Root causes of fluid spills from earthmoving plant and equipment: Implications for reducing environmental and safety impacts. Engineering Failure Analysis, 45, pp.128-141.
Loh, H.P. and Loh, N., 2016. Hydraulic Fracturing and Shale Gas: Environmental and Health Impacts. In Advances in Water Resources Management (pp. 293-337). Springer International Publishing.
Love, P.E., Edwards, D.J., Irani, Z. and Forcada, N., 2014. The latent causes of rework in floating production storage and offloading projects. Journal of Civil Engineering and Management, 20(3), pp.315-329.
Nolan, D.P., 2014. Handbook of fire and explosion protection engineering principles: for oil, gas, chemical and related facilities. William Andrew.
Robinson, D., 2014, September. Development of a Middle East Centric Greenhouse Gas Emissions Reduction Strategy. In SPE Middle East Health, Safety, Environment & Sustainable Development Conference and Exhibition. Society of Petroleum Engineers.
Semple, J., 2014. Natural gas powered locomotives. CORE 2014: Rail Transport For A Vital Economy, p.470.
Sippel, M., Kopp, A., Mattsson, D., Freund, J., Tapeinos, I. and Koussios, S., 2015. Final Results of Advanced Cryo-Tanks Research Project CHATT.
Tomlinson, K., 2017. Oil and gas companies and the management of social and environmental impacts and issues.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download