RALS or Riverina Agriculture and Lifestyle Show were founded in the year 2000 by the BT and Sons farming Equipments. The show was organized in the month of November every year and it demonstrated the local business of the farmers, agricultural equipments and the lifestyle products manufactured by other companies. Coordination of the volunteers and media was required by the organization to demonstrate their live show. For the coordination they involved BT and sons, and later on Globex became a partner of the RALS because they have a strong engagement I the community and can manage the volunteers effectively. The management of the volunteers and the other activities like managing the donation and keeping records of the tickets were done manually and thus more time was required for the management of the whole process.
The report is prepared on the basis of implementation of rostering system on the RALS business process. The rostering process should be able to handle most of the operations of the volunteers like selling tickets, managing the donations, etc. which would reduce the number of volunteers and decease the time (Walker, 2015). For building the rostering system it is necessary to have a proper analysis on the current process and a scope management plan is built that includes the resources and the technology used for the project (Fitzsimmons & Fitzsimmons, 2013). A project schedule is also made to estimate the time required for the completion of the project. Finally a risk assessment and quality management plan is included in the report that states the various risk associated with the project and the quality of the system developed.
The main goal of the report is to have a proper analysis on the system requirement and resources available for the development of the rostering system for RALS. For the management of the project the MOV process is applied and this process covers the project in six steps such as:
For the development of the rostering system analysis of the information about the volunteers such as their name and address, roles, works for which organization, assigned task, etc. There is a need to give the project on time and the areas of impact of the project and are discussed in the following table
Rank |
Areas of impact |
Value |
Metric |
Time required |
1 |
Customer |
It increases the availability of the volunteers and thus providing better service to the customers |
It reduces the work of the volunteers and the management to keep records of the volunteers (Leach, 2014). |
3 months |
2 |
Strategy |
To acquire a greater percentage of share in the market providing a quality service to its customers. |
To increase the share value by 15 percent |
2 months |
3 |
Financial |
The organization saves money by investing on the agricultural investments and meeting all the requirements of the client. |
The expense is cut down to 30% |
|
4 |
Operation |
The organizational values are measured and the cost of operation for the business expansion is decreased (De Waal, 2013). |
The response time must be less and the customer should be highly satisfied using the service. |
6 months |
5 |
Social |
The communication between the client and the system should be efficient and all the information of the volunteers should be captured. |
It reduces the waiting time of the customer. |
3 months |
A better and faster rostering system can be obtained implementing the MOV in for the development of the automated system (Succar, Sher & Williams, 2013). The quality of information gained from the system is improved and the roles and the assigned task of the volunteers can be managed efficiently. The errors in the system would be reduced and it would take less time than the manual process (Schwalbe, 2015). With the implementation of the automated RALS information system it can gain ore profit and reduce the manpower for managing the system.
The personal information gathered for the RALS information system must be secured from any unauthorized access. The data sharing between the management and the administration should be limited and an encryption technique may be applied (Lin & Tain-Dow, 2015). The manual system is replaced applying the web-based system and thus the time taken to complete the business process is reduced. The project should involve all the processes and the role of the volunteer and the portal must be accessible to the client and the volunteer. The data base should be handled by the DBA (Database administrator) and he should update the database frequently to provide up to date details to the client (Burke, 2013). The system should be flexible to adopt any change in their requirement of the client and all the requirements of the client should be met. The requirements can be understood clearly by involving the stakeholders in the various stage of development.
Roles and responsibilities of the developers involved in the project.
Roles |
Responsibility |
Project Sponsor |
The sponsor is responsible for the collection of resources and money for the development of the project |
Project Manager |
The manager plans the project and divides the project into different parts like requirement analysis, planning, executing, design and project closure (Shahnazari, Pourzolfaghar & Mirza, 2013). |
Project Scheduler |
The scheduler divided the different parts of the development into time limits or the time it would take to complete the work. |
Risk management |
The risk manager finds the risk associated with the project and finds the ways to mitigate the risk (Woolliscroft et al., 2013) |
Designer |
The system designer analyses the requirement of the client and design the interface to meet the requirement (Haimes, 2015). |
Analyst |
The system analyst analyses the resource available for the development of the project |
Business consultant |
They give proper suggestion for the improvement of the project and finds the flaws in the system |
Financial Manager |
He is responsible for estimating and managing the budget of the project. |
There are many tools and technology that can be applied for the development of the project. Mid-map, UML techniques, database model tools, programming languages and different libraries and frameworks can be applied for the development of the project. The development of the project requires resources like desktops or laptops with high end configuration and internet connection for accessing different sources (Woolliscroft et al., 2013). Different networking protocol and database security techniques can also be applied for building the system. A PERT chart and a Gnatt chart can also be applied to estimate the cost and time required for the completion of the project.
The volunteers should be trained regarding the usage of the information system and upload of the necessary data. The volunteer information are entered into the system up to February 2017 and thus the employees and the stakeholders associated with the system would lack in information and thus it is necessary to provide them training for the proper utilization of the system.
Task Mode |
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
Auto Scheduled |
Riverina Rostering system development |
180 days |
Thu 9/22/16 |
Wed 5/31/17 |
||
Auto Scheduled |
Initialization phase |
29 days |
Thu 9/22/16 |
Tue 11/1/16 |
||
Auto Scheduled |
Developing the SRS document |
10 days |
Thu 9/22/16 |
Wed 10/5/16 |
Executive sponsor, Requirement analyst |
|
Auto Scheduled |
Feasibility study of the existing system |
7 days |
Thu 10/6/16 |
Fri 10/14/16 |
3 |
project manager, Requirement analyst |
Auto Scheduled |
Identification of the requirements of the desired system |
5 days |
Mon 10/17/16 |
Fri 10/21/16 |
3,4 |
Requirement analyst |
Auto Scheduled |
Utilization of the project specifications |
7 days |
Mon 10/24/16 |
Tue 11/1/16 |
3,5 |
Developer, Requirement analyst |
Auto Scheduled |
Meeting with the management team and visitors of show |
5 days |
Mon 10/24/16 |
Fri 10/28/16 |
4,5 |
Accountant, Executive sponsor, project manager |
Auto Scheduled |
Appointing of development vendor |
21 days |
Mon 10/31/16 |
Mon 11/28/16 |
||
Auto Scheduled |
Identification of the developement vendor |
5 days |
Mon 10/31/16 |
Fri 11/4/16 |
5,7 |
Accountant, project manager |
Auto Scheduled |
Analyzing the vendor capability and background |
10 days |
Mon 10/31/16 |
Fri 11/11/16 |
7 |
Accountant, Executive sponsor, project manager |
Auto Scheduled |
Planning of total time taken to complete |
7 days |
Mon 11/14/16 |
Tue 11/22/16 |
9,10 |
Executive sponsor, project manager |
Auto Scheduled |
Budget planning |
4 days |
Wed 11/23/16 |
Mon 11/28/16 |
11,10 |
Accountant |
Auto Scheduled |
Design Phase |
38 days |
Mon 11/14/16 |
Wed 1/4/17 |
||
Auto Scheduled |
Improving the labour management |
10 days |
Mon 11/14/16 |
Fri 11/25/16 |
10 |
Accountant, Executive sponsor |
Auto Scheduled |
Start to build the system |
18 days |
Mon 11/28/16 |
Wed 12/21/16 |
14 |
Developer, project manager |
Auto Scheduled |
Improvement of installation process |
5 days |
Thu 12/22/16 |
Wed 12/28/16 |
11,15 |
Developer |
Auto Scheduled |
Understanding the system requirements for next built |
5 days |
Thu 12/29/16 |
Wed 1/4/17 |
16 |
Developer, project manager |
Auto Scheduled |
Milestone: Completion of design phase |
0 days |
Thu 9/22/16 |
Thu 9/22/16 |
||
Auto Scheduled |
Implementation phase of the system at organization |
32 days |
Thu 1/5/17 |
Fri 2/17/17 |
||
Auto Scheduled |
Start implementation according to business objectives |
10 days |
Thu 1/5/17 |
Wed 1/18/17 |
17,18 |
Developer, project manager |
Auto Scheduled |
Modification in the first built of the system |
5 days |
Thu 1/19/17 |
Wed 1/25/17 |
20 |
Developer, Requirement analyst |
Auto Scheduled |
Collection of resources and equipments for the project |
12 days |
Thu 1/26/17 |
Fri 2/10/17 |
21 |
Accountant, project manager |
Auto Scheduled |
Verification of the equipments and resources |
5 days |
Mon 2/13/17 |
Fri 2/17/17 |
22 |
Developer, project manager |
Auto Scheduled |
Testing phase |
25 days |
Mon 2/20/17 |
Fri 3/24/17 |
||
Auto Scheduled |
test run of the system |
7 days |
Mon 2/20/17 |
Tue 2/28/17 |
22,23 |
Executive sponsor, project manager |
Auto Scheduled |
Carrying out the test plan |
8 days |
Wed 3/1/17 |
Fri 3/10/17 |
23,25 |
Software tester |
Auto Scheduled |
Analyzing the test result in real scenario |
8 days |
Mon 3/13/17 |
Wed 3/22/17 |
25,26 |
Risk manager, Software tester |
Auto Scheduled |
Presentation of the result |
2 days |
Thu 3/23/17 |
Fri 3/24/17 |
25,27 |
project manager, Software tester |
Auto Scheduled |
Milestone: acceptance of the test results by client |
0 days |
Thu 9/22/16 |
Thu 9/22/16 |
||
Auto Scheduled |
Risk management phase |
24 days |
Mon 3/27/17 |
Thu 4/27/17 |
||
Auto Scheduled |
Identification of the possible risks |
7 days |
Mon 3/27/17 |
Tue 4/4/17 |
28,29 |
Risk manager, Software tester |
Auto Scheduled |
presentation of the risks to the risk manager |
2 days |
Wed 4/5/17 |
Thu 4/6/17 |
31 |
project manager, Risk manager |
Auto Scheduled |
mitigation of the risks |
7 days |
Wed 4/5/17 |
Thu 4/13/17 |
31 |
Developer, Risk manager |
Auto Scheduled |
Registering the impacts of the risks |
5 days |
Fri 4/14/17 |
Thu 4/20/17 |
31,33 |
project manager, Risk manager |
Auto Scheduled |
Identify the impacts of the risks |
15 days |
Fri 4/7/17 |
Thu 4/27/17 |
32 |
project manager, Risk manager |
Auto Scheduled |
Milestone: Acceptance of the risk document by the client |
0 days |
Thu 9/22/16 |
Thu 9/22/16 |
||
Auto Scheduled |
Closure of the project |
24 days |
Fri 4/28/17 |
Wed 5/31/17 |
||
Auto Scheduled |
Evaluation of the functionality of the developed system |
9 days |
Fri 4/28/17 |
Wed 5/10/17 |
35 |
Executive sponsor, project manager |
Auto Scheduled |
Rolling out the finally developed project |
15 days |
Thu 5/11/17 |
Wed 5/31/17 |
38 |
Developer, project manager |
Auto Scheduled |
Milestone: Installation of the final system to the organization |
0 days |
Wed 5/31/17 |
Wed 5/31/17 |
39 |
It is accepted that the project finishes inside the evaluated time and in addition the estimated spending plan. It is likewise expected that the task is directed by tailing every one of the tenets and controls of the association. All the task colleagues ought to take after the rules so it will morally finish the venture arrangement without impacting anybody (Bavota et al, 2012). It is likewise accepted that the endorsement from the task supervisor will go inside few days in the wake of presenting the configuration of RALS rostering framework.
Risks |
Member associated with the risk |
Details |
Mitigation technique |
Technical risk |
System Analyst |
The network or the server may not work properly and this may cause the system to become down. |
The servers and the networks should be monitored regularly and there is a need to run maintenance at a regular internal of time (Schwalbe, 2015). |
Financial risk |
Financial Manager |
There may be extra expense and this may cause shortage in the budget plan. |
A proper budget plan is required to be made with some extra money kept for emergency conditions. |
Lack of resource |
Project Manager |
If the estimation is not calculated properly or the requirement is not understand it may delay the project progress (Burke, 2013). |
A proper analysis is required to be done and using of cost estimation tool can help to mitigate this issue. |
Loss of manpower |
Project Manager |
If any team member becomes ill or has less skill to manage the work it increases the pressure on the skilled workers and the manpower is lossed (Kerzner, 2013). |
To release the work pressure some extra team members must be reserved. |
Risk in privacy |
Project Manger |
The collected information about the volunteers should be kept securely during the development process as it may cause intruder to misuse their information (Walker, 2015). |
The digital signature and the information of the volunteers should be kept securely with some added protection. |
Project Name: RALS rotering project |
Project Manager Name |
||||
Type |
Reason |
Time taken |
Owner |
Method |
Status |
Expense Authorization |
The expense for the development of the project must be done from a single person and it reduces the chance of misuse. |
2 month |
Financial Manager |
Managing of the expense |
Open |
Documentation of the project |
The status of the project must be documented daily |
1 month |
Project manager |
Monitoring of the progress of the project |
Closed |
Work break down structure |
It makes easy to identify the task assigned. |
3 month |
Project Manager |
Inspection of the work of the development team |
Open |
Project plan |
A proper analysis is done on the requirement of the client. |
1 month |
Project Manager |
Review of the project that if it is developing based on the planning |
Closed |
Risk plan |
Review of the risk arising during the development of the project |
4 months |
Risk manager |
Review of the framework |
Open |
MOV |
It identifies the stakeholders associated with the project |
2 month |
Project manager |
monitoring |
Closed |
Training material |
Training manual is provided to the team members to increase their efficiency. |
3 month |
Project manager |
Presentation and journals |
Open |
The report concludes that the Riverina Agriculture and Lifestyle show activities to make a management system for removing their manual process and dependency on the volunteers. The current business process is automated and RALS outsource for the development of their process. The new information system would take nearly 6 month for its completion and the system would be capable of managing the volunteer information and provide effective service to the customers. It would also reduce the pressure from the staffs gather information about the different volunteers and agencies involved in the process it is necessary to develop the rostering system. The report discusses about the development of the project and the involvement of the team members for conducting the project development.
Bavota, G., De Lucia, A., Fasano, F., Oliveto, R., & Zottoli, C. (2012, June). Teaching software engineering and software project management: An integrated and practical approach. In Proceedings of the 34th International Conference on Software Engineering (pp. 1155-1164). IEEE Press.
Burke, R. (2013). Project management: planning and control techniques.New Jersey, USA.
De Waal, A. (2013). Strategic Performance Management: A managerial and behavioral approach. Palgrave Macmillan.
Fitzsimmons, J., & Fitzsimmons, M. (2013). Service management: Operations, strategy, information technology. McGraw-Hill Higher Education.
Haimes, Y. Y. (2015). Risk modeling, assessment, and management. John Wiley & Sons.
Kerzner, H. R. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Leach, L. P. (2014). Critical chain project management. Artech House.
Lin, L. M., & Tain-Dow, L. E. E. (2015). Symbolic Economy and Creative Management: Cultural and Creative Industries Urging for New Approaches.Journal of Cultural Management and Policy, 57.
McNeil, A. J., Frey, R., & Embrechts, P. (2015). Quantitative risk management: Concepts, techniques and tools. Princeton university press.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.
Shahnazari, M., Pourzolfaghar, Z., & Mirza, M. N. (2013, January). A Review of Project Managerial Aspects Influenced by Emotional Intelligence. InECMLG2013-Proceedings For the 9th European Conference on Management Leadership and Governance: ECMLG 2013 (p. 475). Academic Conferences Limited.
Succar, B., Sher, W., & Williams, A. (2013). An integrated approach to BIM competency assessment, acquisition and application. Automation in Construction, 35, 174-189.
Walker, A. (2015). Project management in construction. John Wiley & Sons.
Woolliscroft, P., Relich, M., Caganova, D., Cambal, M., Sujanova, J., & Makraiova, J. (2013, October). The implications of tacit knowledge utilisation within project management risk assessment. In International Conference on Intellectual Capital and Knowledge Management and Organisational Learning(p. 645). Academic Conferences International Limited.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download