The principles of project management had been a keen source for forming an effective project plan along with improved functional and development operations (Pappas et al. 2017). The alignment of the composite operations for forming the successful list of project activities considering the project resource usage is a major component for the alignment of the operations and development. The use of project operations would align to the deployment of the operations and functions aligning to the specific project management operations.
The following assignment is a project report based on the case study of Marks & Spencer in Kendal and their undertaking of the project of Relocation of their Store. The project would incorporate both event management and construction project principles and operations. The assignment comprise of five sections and the completion of the five sections would result in forming the final project deliverable of report. The identification of the principles and theories of project management were based for studying the project completion requirements.
The project management is deployed for aligning the development of the operations and forming a set of activities that is capable for forming the complete project operations (Rothe, Heywood, Christersson and Sarasoja 2015). The project management principles and theoretical foundations that would be used for the project of Relocation of Marks & Spencer store to Kendal are,
Principle 1: Vision and Mission |
The articulation of the vision and mission for the project is aligned successfully for forming the clarifying the expected outcomes. |
Principle 2: Business Objectives |
Two to three goals/objectives of the project must be set in order to overcome the possibility of diversion from the main objective |
Principle 3: Standards of Engagement |
Some standards must be kept for ensuring that the operations of the project are formed cohesively with the alignment of the project operations |
Principle 4: Intervention and Execution Strategy |
The intervention and execution strategy is aligned for forming the development of the cohesive operational development. |
Principle 5: Organizational Alignment |
The operations must be aligned with the strategic alignment of the business development |
Principle 6: Measurement and Accountability |
The analysis of the project operations can be done based on the simplified functional development with the help of using measuring operations and functions. |
According to Ismail et al. (2014), the personal skills required for the research, analysis, and evaluation of work for the project of Relocation of Marks & Spencer store to Kendal are communication, critical thinking, attention for detailing, technical skills, planning knowledge, collection of data, and safety assessment.
The project plan for the project of Relocation of Marks & Spencer store to Kendal is given in the table below,
WBS |
Task Name |
Duration |
Start |
Finish |
0 |
Managing a Store Relocation Project: Marks & Spencer in Kendal |
100 days |
Mon 4/2/18 |
Fri 8/17/18 |
1 |
Project Initiation |
23 days |
Mon 4/2/18 |
Wed 5/2/18 |
1.1 |
Development of Project initiation documents |
3 days |
Wed 4/4/18 |
Fri 4/6/18 |
1.2 |
Project Charter documentation |
3 days |
Wed 4/25/18 |
Fri 4/27/18 |
1.3 |
Analysis of Client’s Requirements |
2 days |
Mon 4/2/18 |
Tue 4/3/18 |
1.4 |
Project Kick off meeting |
1 day |
Wed 5/2/18 |
Wed 5/2/18 |
2 |
Project Planning |
22 days |
Mon 4/9/18 |
Tue 5/8/18 |
2.1 |
Schedule Planning |
4 days |
Mon 4/9/18 |
Thu 4/12/18 |
2.2 |
Stakeholder Registration |
2 days |
Mon 4/30/18 |
Tue 5/1/18 |
2.3 |
Quality Management Planning |
4 days |
Thu 5/3/18 |
Tue 5/8/18 |
2.4 |
Resource Usage Planning |
4 days |
Fri 4/13/18 |
Wed 4/18/18 |
2.5 |
Risk Management Planning |
4 days |
Thu 4/19/18 |
Tue 4/24/18 |
2.6 |
Plan Phase Completed |
0 days |
Tue 5/8/18 |
Tue 5/8/18 |
3 |
Project Execution |
73 days |
Thu 5/3/18 |
Mon 8/13/18 |
3.1 |
Documentation and Analysis Phase |
7 days |
Thu 5/3/18 |
Fri 5/11/18 |
3.1.1 |
Submission of change address forms to PO |
2 days |
Thu 5/10/18 |
Fri 5/11/18 |
3.1.2 |
Identifying Relocation Requirements |
3 days |
Thu 5/3/18 |
Mon 5/7/18 |
3.1.3 |
Consulting Movers and Packers for relocation |
1 day |
Thu 5/3/18 |
Thu 5/3/18 |
3.1.4 |
Hiring Transportation Contractor |
1 day |
Fri 5/4/18 |
Fri 5/4/18 |
3.1.5 |
Filling and Sending RFQ to required persons |
2 days |
Tue 5/8/18 |
Wed 5/9/18 |
3.2 |
Packing Phase |
6 days |
Fri 5/4/18 |
Fri 5/11/18 |
3.2.1 |
Files and Important Documents are packed |
1 day |
Fri 5/4/18 |
Fri 5/4/18 |
3.2.2 |
Drives, relocatable inventory, and other items are packed |
2 days |
Mon 5/7/18 |
Tue 5/8/18 |
3.2.3 |
Computer Devices and portable electronics are also packed |
4 days |
Fri 5/4/18 |
Wed 5/9/18 |
3.2.4 |
Existing Stock are transferred to warehouse |
5 days |
Mon 5/7/18 |
Fri 5/11/18 |
3.2.5 |
Packed boxes are labeled |
1 day |
Thu 5/10/18 |
Thu 5/10/18 |
3.2.6 |
Boxes are loaded into the moving trucks |
3 hrs |
Fri 5/11/18 |
Fri 5/11/18 |
3.3 |
Construction Phase |
60 days |
Tue 5/8/18 |
Mon 7/30/18 |
3.3.1 |
Selection of appropriate site |
2 days |
Tue 5/8/18 |
Wed 5/9/18 |
3.3.2 |
Site Clearing and Groundworks |
5 days |
Thu 5/10/18 |
Wed 5/16/18 |
3.3.3 |
Basement Works |
13 days |
Thu 5/17/18 |
Mon 6/4/18 |
3.3.3.1 |
Basement Structure is constructed |
6 days |
Thu 5/17/18 |
Thu 5/24/18 |
3.3.3.2 |
Basement is divided into sections |
3 days |
Thu 5/17/18 |
Mon 5/21/18 |
3.3.3.3 |
Cold Hold, Refrigeration Plant, Goods Reception, and Stock Room is made |
6 days |
Thu 5/17/18 |
Thu 5/24/18 |
3.3.3.4 |
Basement and Underground parking is made |
4 days |
Fri 5/25/18 |
Wed 5/30/18 |
3.3.3.5 |
Entrance to basement is carved out |
3 days |
Thu 5/31/18 |
Mon 6/4/18 |
3.3.4 |
Ground Floor Works |
10 days |
Tue 6/5/18 |
Mon 6/18/18 |
3.3.4.1 |
Ground Floor Structure is made |
6 days |
Tue 6/5/18 |
Tue 6/12/18 |
3.3.4.2 |
Coldrooms and goods lift is made |
4 days |
Wed 6/13/18 |
Mon 6/18/18 |
3.3.4.3 |
Sales Section is made |
2 days |
Wed 6/13/18 |
Thu 6/14/18 |
3.3.4.4 |
Food Keeping area is made |
2 days |
Fri 6/15/18 |
Mon 6/18/18 |
3.3.4.5 |
Entrance to store, Staff entrance, and connection to basement is carved out |
3 days |
Wed 6/13/18 |
Fri 6/15/18 |
3.3.5 |
Mezzanine Floor Works |
6 days |
Mon 6/18/18 |
Mon 6/25/18 |
3.3.5.1 |
EPoS is made |
4 days |
Tue 6/19/18 |
Fri 6/22/18 |
3.3.5.2 |
Admin Room is made |
3 days |
Tue 6/19/18 |
Thu 6/21/18 |
3.3.5.3 |
Kitchen and Dining room is made |
4 days |
Mon 6/18/18 |
Thu 6/21/18 |
3.3.5.4 |
Toilets are constructed |
2 days |
Fri 6/22/18 |
Mon 6/25/18 |
3.3.6 |
Final Electrical and Mechanical works |
27 days |
Fri 6/22/18 |
Mon 7/30/18 |
3.3.6.1 |
High level electrical, mechanical and sprinkler services are installed |
1 wk |
Mon 6/25/18 |
Fri 6/29/18 |
3.3.6.2 |
CCTV and Air Conditioners are installed |
4 days |
Mon 7/2/18 |
Thu 7/5/18 |
3.3.6.3 |
Design features are installed |
5 wks |
Fri 6/22/18 |
Thu 7/26/18 |
3.3.6.4 |
Vinyl Flooring, Carpets are layed, and Ceiling tiles are dropped |
3 days |
Tue 6/26/18 |
Thu 6/28/18 |
3.3.6.5 |
Fire Safety and Health Safety is Installed |
2 days |
Fri 7/27/18 |
Mon 7/30/18 |
3.4 |
Unpacking Phase |
10 days |
Tue 7/31/18 |
Mon 8/13/18 |
3.4.1 |
Boxes are received at the new location |
1 day |
Tue 7/31/18 |
Tue 7/31/18 |
3.4.2 |
Unpacking of the boxes |
1 day |
Tue 7/31/18 |
Tue 7/31/18 |
3.4.3 |
Placing all required essentials at proper places |
2 days |
Wed 8/1/18 |
Thu 8/2/18 |
3.4.4 |
Stock is arranged at the new location |
4 days |
Wed 8/1/18 |
Mon 8/6/18 |
3.4.5 |
Cubicles and other items are aligned |
5 days |
Tue 8/7/18 |
Mon 8/13/18 |
3.4.6 |
Procurement is completed |
0 days |
Mon 8/13/18 |
Mon 8/13/18 |
4 |
Final Documentation and Closure |
4 days |
Tue 8/14/18 |
Fri 8/17/18 |
4.1 |
Development of final documents |
3 days |
Tue 8/14/18 |
Thu 8/16/18 |
4.2 |
Submission of final documents |
1 day |
Fri 8/17/18 |
Fri 8/17/18 |
4.3 |
Review and Sign off |
1 day |
Fri 8/17/18 |
Fri 8/17/18 |
4.4 |
Project Closed |
0 days |
Fri 8/17/18 |
Fri 8/17/18 |
Table 1: Project Plan
The Schedule for the project of Relocation of Marks & Spencer store to Kendal is shown in the Gantt chart below,
The controlling of the project of Relocation of Marks & Spencer store to Kendal can be done by using project control cycle comprising of 4 phase cycle namely Plan, Monitor, Review, and Control (Shi et al. 2015). The Plan phase incorporates the development and implementation of the control plan. The control plan is formed for listing some set of activities that would be helpful for the deployment of the effective operational development. The monitor process is carried on for analysing whether the project operations are carrying out successfully. The control plan is monitored and reviewed for ensuring that the project is completed successfully (Binder, Aillaud and Schilli 2014). The control phase is characterized by the implementation of the specific corrective actions required for controlling process.
Figure 1: Project Control Plan
(Source: Zhao, Zuo and Zillante 2017, pp.-145)
The project of Relocation of Marks & Spencer store to Kendal is helpful for listing the development of the relocation of the project for forming the new store of Marks & Spencer at Kendal. The Project success criteria includes the following points,
Project Time: The project has set of some specific timeline for completing the project and ensuring that the project is successful (Heizer 2016). The project is upper-bounded by the time period of 6 months that signifies that the project should be completed on or before 6 months of time. The site would be available for the contractor after 14th February and some other time boundaries on project were,
Project Cost: The cost budget for the project of Relocation of Marks & Spencer store to Kendal can be shown below,
Resource Name |
Duration/Unit |
Standard Rate |
Total |
Documenter |
112 |
$61.00 |
$6,832.00 |
Analyst |
40 |
$55.00 |
$2,200.00 |
Project Manager |
48 |
$125.00 |
$6,000.00 |
Planner |
128 |
$60.00 |
$7,680.00 |
Mover 1 |
35 |
$80.00 |
$2,800.00 |
Mover 2 |
35 |
$80.00 |
$2,800.00 |
Transporter |
40 |
$100.00 |
$4,000.00 |
Mover 3 |
40 |
$80.00 |
$3,200.00 |
Mover 4 |
64 |
$80.00 |
$5,120.00 |
Contractor |
64 |
$115.00 |
$7,360.00 |
Workers |
288 |
$95.00 |
$27,360.00 |
Civil Engineer |
296 |
$120.00 |
$35,520.00 |
Technician |
136 |
$105.00 |
$14,280.00 |
Perimeter Panelling |
1 |
$500.00 |
$500.00 |
Trims |
1 |
$548.00 |
$548.00 |
Skirting |
1 |
$550.00 |
$550.00 |
Coving |
1 |
$500.00 |
$500.00 |
Conince and Lightning |
1 |
$1,000.00 |
$1,000.00 |
Carpets |
1 |
$500.00 |
$500.00 |
Tiles |
1 |
$500.00 |
$500.00 |
Automatic Doors |
1 |
$1,600.00 |
$1,600.00 |
Integrated AC |
1 |
$2,600.00 |
$2,600.00 |
Refrigeration Machine |
1 |
$4,200.00 |
$4,200.00 |
EPoS system |
1 |
$2,300.00 |
$2,300.00 |
Fire Extinguisher |
1 |
$500.00 |
$500.00 |
First Aid Kit |
1 |
$550.00 |
$550.00 |
CCTV |
1 |
$2,000.00 |
$2,000.00 |
Construction Raw Materials |
1 |
$7,000.00 |
$7,000.00 |
Total Budget |
$150,000 |
The interactive systems comprise of using mediums of transferring the information in between the people and system for taking effective decision making process (Binder 2015). The integration of the effective models for the transmission of the information is done for forming the assurance of information transmission in the organization. The information transmission is carried on for ensuring that the transmission would be aligned for listing the modification of the supportive and attractive operations (Niazi et al. 2016). The carrying out of the functions is formed so that the operations would allow the listing of the operations for development.
Conclusion
It can be concluded from the assignment that the deployment of the operations were aligned for forming the management of the proportional influence of the project operations. The project had been helped in successful listing of the operations that are capable for completing the relocation of the project for the alignment of the operations. The analysis of the successive development facts had provided the role for the continuation of the project system integration. The analysis had provided the role for the management of the operations and carrying out the successful completion of the project activities.
References
Binder, J., 2015. An investigation into the requirements and practices for global project management in the information systems department of a global organization (Doctoral dissertation, Heriot-Watt University).
Binder, J., Aillaud, L.I. and Schilli, L., 2014. The project management cocktail model: An approach for balancing agile and ISO 21500. Procedia-Social and Behavioral Sciences, 119, pp.182-191.
De Felice, F., Petrillo, A. and Silvestri, A., 2015. Offshoring: Relocation of production processes towards low-cost countries through the project management & process reengineering performance model. Business Process Management Journal, 21(2), pp.379-402.
Flouris, T.G. and Lock, D., 2016. Aviation project management. Routledge.
Harris, E., 2017. Strategic project risk appraisal and management. Routledge.
Heizer, J., 2016. Operations Management, 11/e. Pearson Education India.
Ismail, D., Majid, T.A., Roosli, R. and Ab Samah, N., 2014. Project management success for post-disaster reconstruction projects: International NGOs perspectives. Procedia Economics and Finance, 18, pp.120-127.
Lock, M.D., 2014. The essentials of project management. Ashgate Publishing, Ltd..
Newton, R., 2016. Project management step by step: how to plan and manage a highly successful project. Pearson UK.
Niazi, M., Mahmood, S., Alshayeb, M., Riaz, M.R., Faisal, K., Cerpa, N., Khan, S.U. and Richardson, I., 2016. Challenges of project management in global software development: A client-vendor analysis. Information and Software Technology, 80, pp.1-19.
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and technology. Taylor & Francis.
Pappas, D., Chalvatzis, K.J., Guan, D. and Li, X., 2017. Industrial Relocation and CO 2 Emission Intensity: Focus on the Potential Cross-Country Shift from China to India and SE Asia. Energy Procedia, 142, pp.2898-2904.
Rothe, P., Heywood, C., Christersson, M. and Sarasoja, A.L., 2015. Office relocation management in Finland–challenges and service opportunities. Property Management, 33(4), pp.348-366.
Shi, Q., Liu, Y., Zuo, J., Pan, N. and Ma, G., 2015. On the management of social risks of hydraulic infrastructure projects in China: A case study. International Journal of Project Management, 33(3), pp.483-496.
Turner, R., 2016. Gower handbook of project management. Routledge.
Zhao, Z.Y., Zuo, J. and Zillante, G., 2017. Transformation of water resource management: a case study of the South-to-North Water Diversion project. Journal of Cleaner Production, 163, pp.136-145.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download