The solution is saved in attached file ‘PartAQ1.mpp’.
The overall solution is saved and attached herewith as ‘PartAQ2.mpp’.
The resources over distribution issues can be settled either by including extra resources or by deferring the exercises. In any case, the issue remains where the exercises are in critical path the term can’t be expanded so the main choices remain are to include additional resources. Yet, there is likewise another choice accessible is to disperse the accessible resources inside the float accessible in the activity so the general term doesn’t gets affected yet the resources additionally gets leveled with in the accessible +ve float activities.
The solution file is saved and attached herewith as ‘PartAQ3_resources.mpp’.
To: The owner of WorkFast P/L (Mr. Chris Parsons)
to notify the highlights of the project ‘Family Friendly Financial Control System’. The highlights are as below:
The expected completion date of the project is 17th July 2018
Resource Name |
Cost |
Operations |
$22,800.00 |
Analyst |
$80,000.00 |
Database |
$58,800.00 |
Software Engineers |
$130,200.00 |
Telecommunications |
$21,600.00 |
Installation Team |
$33,320.00 |
Total Direct Labor Costs |
$346,720.00 |
The updated schedule is attached herewith as file ‘PartAQ3_resources.mpp’.
The staff shall report to me & I shall report to the owner (Mr. Chris Parsons) of Helpful Solutions P/L. All the project management activities need to be performed by me and my team but the overall control on the budget and cost of the project is not under me; rather it is with the client. The purchase of any hardware need to be organized but can’t purchase. It has to be purchased by the client as per the scope of the contract. So it is neither functional (as no other functional manager is there) and nor projectized (as the overall control of the project is not available with me) (Fremouw, 2017), it is a ‘Matrix Organization’.
Because in Matrix Organization, the horizontal reporting like I shall report to the owner of the company and to my organizational boss too. This kind of double reporting structure exists in Matric organization.
Project Risks (Winters, 2009):
Risk No. |
Risk Description |
Impact |
Likelihood of occurrence (Low, Medium, High) |
Degree of impact (Low, Medium, High) |
1 |
There is a risk of non-availability of the resources throughout the project life cycle |
The impact is high on the project, it at all it happens |
Medium |
High |
2 |
There is a risk of getting schedule overrun because of the resource constraints |
Again the impact would be high |
Medium |
High |
The highlighted changes are marked in the attached file The impact changes on duration of the schedule are as below:
Change |
Impact on Project duration |
By how much |
Explanation |
Increase duration from 3 person-weeks to 6 person-weeks for ‘5.6.1’ & ‘5.6.2’ & from 2 person-weeks to 4 person-weeks for ‘5.6.3’ |
There was no impact on the overall duration of the project |
0 days |
Original end date was = 17/Jul/2018 Revised due to 5.6.1 = -NIL- Revised due to 5.6.2 = -NIL- Revised due to 5.6.3 = – NIL- Since the activity 5.6.1, 5.6.2 and 5.6.3 was not in the critical path (Stelth, 2009) and the float was available more than the increased duration, so there was no change in the overall duration of the project. |
Allocation of additional DB to task ‘5.6.1’, ‘5.6.2’ & ‘5.6.3’ |
There was no impact on the overall duration of the project. But the individual durations of task 5.6.1, 5.6.2 & 5.6.3 got reduced |
0 days |
The duration of 5.6.1 & 5.6.2 became 15 from 30 & the duration of 5.6.3 became 10 from 20 because the additional DB absorbed the extra job of old DB and shared the % of volume equally |
Increase duration from 1 person-week to 2 person-weeks for 3.4 |
There was no impact on the overall duration of the project |
0 days |
Original end date was = 17/Jul/2018 Revised due to 3.4 = -NIL- Since the float available in 3.4 was more than the increased duration, it didn’t impacted the overall duration of the project. |
Reduction in time between first to second installation from 6 person-weeks to 4 person-weeks |
Duration decreased |
10 days |
The overall duration for the project decreased from 239 days to 229 days. Since both the activities ‘6.2 Installation at first new store’ and ‘6.3 Installation at second new store’ are in critical path, so the reduction in the duration of link or lag has directly reduced the overall duration of the project. |
The impact changes on cost of the schedule are as below:
Change |
Impact on Direct Labor Costs |
By how much |
Explanation |
Change in person-weeks required for tasks 5.6.1-5.6.3 |
Cost increased |
$380,320 – $346,720 = $33,600 |
Budgeted Cost to Complete = $346,720 Revised due to 5.6.1 = $359,320 Revised due to 5.6.2 = $371,920 Revised due to 5.6.3 = $380,320 Due to increase in duration the resource usage also increases, and the cost is directly proportional to the use of resources (Pmbook, 2017), so the cost increased. |
Allocation of additional DB to task 5.6.1, 5.6.2 & 5.6.3 |
No Change |
$0 |
Budget did not changed from $380,320 as the additional DB has reduced the duration by 50% so the increased cost of additional DB has been countered by the reduction of duration |
Change in person-weeks required for task 3.4 |
Cost increased |
$383,920 – $380,320 = $3,600 |
Overall cost before change in 3.4 = $380,320 But after the duration increased by 2 person-weeks because of the duration of resource usage the cost of the project also got increased |
Reduction in time between first to second installation from 6 person-weeks to 4 person-weeks |
No Change |
$0 |
Overall cost before change in duration of lag = $383,920 & now also same. This happened because we changed the lag duration not the duration of any activity & lag (Usmani, 2017) don’t need any resource either to increase or decrease, it is just a representation of the relationship between the activities. |
References
2020projectmanagement, 2017. What is the Critical Path? [Online] Available at: https://2020projectmanagement.com/2014/05/what-is-the-critical-path/ [Accessed 29 July 2017].
Fremouw, B., 2017. Functional Organizations vs Projectized Organizations. [Online] Passionate Project Management Available at: https://www.passionatepm.com/blog/functional-organizations-versus-projectized-organizations-pmp-concept-10 [Accessed 23 September 2017].
Pmbook, 2017. 5. Cost Estimation. [Online] Available at: https://pmbook.ce.cmu.edu/05_Cost_Estimation.html [Accessed 23 September 2017].
Stelth, P., 2009. Projects’ Analysis through CPM (Critical Path Method). School of Doctoral Studies (European Union) Journal, pp.10-51.
Usmani, F., 2017. Lead Time and Lag Time in Project Scheduling Network Diagram. [Online] PM Study Circle Available at: https://pmstudycircle.com/2013/02/lead-time-and-lag-time-in-project-scheduling-network-diagram/ [Accessed 23 September 2017].
Winters, L., 2009. Deadliest catch: risk identification in the vast Bering Sea. In PMI® Global Congress 2009. North America, Orlando, 2009.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download