The project mainly reflects on the “wedding event” that was mainly organized for Tony and Peggy Sue who generally decided to outsource the entire wedding event to a company. It is identified that in order to organize their wedding event with the involvement of family members, both Tony and due wanted to make it a big wedding. It is found that both the weeding and the reception party will be arranged in outdoor by including plenty of foods, music and dance. It is assumed that the event of the wedding will be organized by 30th June 2019. The objectives of the project are reflected below:
The project specifications for organizing the wedding event for Tony and Peggy Sue is generally reflected below:
Human resources: The people who are generally engaged with the wedding event are listed below:
Budget: It is identified that in order to finish the wedding successfully, the amount of budget which is required will be around $91,400.
Timeline: The time that is needed in order to organize the wedding event will be around 130 days.
Required materials: The materials as well as resources required for organizing the wedding plan are reflected below:
The wedding event was organized for Tony and Peggy Sue who wants to get married on 30th June. The big wedding was organized by a company that must have plenty of food, dance and music opportunity for the guests who generally includes the family and friends of Tony and Peggy Sue. It is found that the entire plan must be developed by 30th June that is wedding day.
The main goal is to organize an event for the wedding of Tony and Peggy Sue who generally wants the involvement of family and friends with plenty of food, music and dance in order to make their weeding day a special one.
The in-scope includes:
The out-scope of the project includes:
The assumptions which are made while handling the project work are generally illustrated below:
Availability of stakeholders: It is assumed that the stakeholders who are mainly associated with the project will generally available during the period in which the wedding plan will be implemented.
Easily available resources: The needed resources as well as other materials that are generally required for decorating the venue will be easily available in the market.
Budget: It is assumed that the approved budget will be enough for executing the entire project successfully.
The WBS for the wedding event of Tony and Peggy Sue is provided below.
Figure 1: Work breakdown structure
(Source: Created by Author)
The Gantt chart which is given below showcases on the timeline that is required for organizing the event for completing the work of the project. The figure below reflects that the wedding plan will be successfully completed before 30th June.
Figure 2: Gantt chart
(Source: Created by Author)
The human resources who organizes the wedding event is generally reflected below with their roles and responsibilities within the project.
The risk management plan for the project is generally reflected in the table which is generally given below:
Risk |
Description |
Impact |
Probability |
Mitigation |
Improper schedule |
If the project timeline is not tracked regularly then the chances of schedule slippage is quite high. |
High |
High |
It is very much necessary to track the schedule of the project regularly for finishing the work on time. |
Inappropriate budget |
If the allocated budget for organizing the wedding is not enough then budget related challenges can occur. |
High |
High |
It is quite necessary to analyze the cost of the resource before initiating with the project work. |
Improper management |
If the entire project is not managed properly then the project does not get finish on time. |
Medium |
High |
It is necessary to hire experienced team members for finishing the work of the project. |
The communication plan that is generally developed for communicating between the project team members is reflected below:
Audience |
Message |
Vehicle |
Frequency |
Responsible |
Team members |
The objectives must be discussed by the project manager so that the work can be done successfully. |
Face to face conversation |
Before project initiation |
Project manager |
Project manager |
The team leaders inform about the status of the project to the project manager. |
Face to face, |
One in a month |
Team leaders |
Financial manager |
The team leader generally provides information about the need of the budget for the project |
Face to face, email |
Whenever needed |
Team leaders |
Project team leader |
The team members provide proper information as well as details about the risks and challenges that they generally face while undertaking the project so that the risk and challenges associated with the project can be resolved. |
Face to face/email |
When necessary |
Team members |
The resources which are generally needed for organizing the entire plan for the project are generally needed to be assigned with the project activities as per the skills and knowledge of the team members. It is identified that the table which is generally provided below helps in focuses on the resources which are generally assigned for finishing each of the project activities quite successfully within the expected time as well as budget.
WBS |
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
0 |
Organizing a wedding |
130 days |
Tue 01-01-19 |
Sun 30-06-19 |
||
1 |
Initial Planning |
50 days |
Tue 01-01-19 |
Mon 11-03-19 |
||
1.1 |
Selection of the wedding date |
15 days |
Tue 01-01-19 |
Mon 21-01-19 |
Client |
|
1.2 |
Consultation with the wedding planner |
10 days |
Tue 22-01-19 |
Mon 04-02-19 |
2 |
Client |
1.3 |
Making plan for the wedding |
20 days |
Tue 05-02-19 |
Mon 04-03-19 |
3 |
Planner |
1.4 |
Accumulating the needed resources |
5 days |
Tue 05-03-19 |
Mon 11-03-19 |
4 |
Project Manager |
1.5 |
Project kick off |
0 days |
Mon 11-03-19 |
Mon 11-03-19 |
5 |
|
2 |
Venue Booking and Invitation |
40 days |
Tue 05-03-19 |
Mon 29-04-19 |
||
2.1 |
Selection and booking of venue for wedding and reception |
10 days |
Tue 12-03-19 |
Mon 25-03-19 |
6 |
Event Manager |
2.2 |
Reviewing the plan with the clients |
6 days |
Tue 05-03-19 |
Tue 12-03-19 |
4 |
Planner |
2.3 |
Getting approval |
1 day |
Wed 13-03-19 |
Wed 13-03-19 |
9,6 |
Client |
2.4 |
Guest list |
10 days |
Tue 26-03-19 |
Mon 08-04-19 |
10,8 |
Event Manager |
2.5 |
Sending invitation to the guests |
15 days |
Tue 09-04-19 |
Mon 29-04-19 |
11 |
Event Manager |
2.6 |
Initiation and Planning Phase Completed |
0 days |
Mon 29-04-19 |
Mon 29-04-19 |
12 |
|
3 |
Human Resource Management |
16 days |
Tue 30-04-19 |
Tue 21-05-19 |
||
3.1 |
Selecting vendor and sorting food items for wedding dinner |
8 days |
Tue 30-04-19 |
Thu 09-05-19 |
13 |
Resource Manager, Vendor Cost [1] |
3.2 |
Cameron and video man hire |
2 days |
Tue 30-04-19 |
Wed 01-05-19 |
13 |
Event Manager, Cameraman Pay [1], Videographer Pay [1] |
3.3 |
Try-outs for wedding dress and placing order |
7 days |
Tue 30-04-19 |
Wed 08-05-19 |
13 |
Client, Dress Cost [1] |
3.4 |
Booking for the musical instruments and other requirements including lightening |
8 days |
Thu 02-05-19 |
Mon 13-05-19 |
16 |
Event Manager, Band Pay [1] |
3.5 |
RSVP from guests is received |
4 days |
Tue 14-05-19 |
Fri 17-05-19 |
18 |
Event Manager |
3.6 |
Booking Solemniser/Wedding Priest |
2 days |
Mon 20-05-19 |
Tue 21-05-19 |
19 |
Event Manager, Solemniser pay [1] |
4 |
Venue Arrangement |
28 days |
Wed 22-05-19 |
Fri 28-06-19 |
||
4.1 |
Consultation with decorator to decorate |
6 days |
Wed 22-05-19 |
Wed 29-05-19 |
20 |
Project Manager |
4.2 |
Theme selection for wedding and reception |
9 days |
Thu 30-05-19 |
Tue 11-06-19 |
22 |
Client |
4.3 |
Arranging flowers and other decorative items |
3 days |
Wed 12-06-19 |
Fri 14-06-19 |
23 |
Resource Manager, Decoration Items [1] |
4.4 |
Decorating the Wedding Venue as per theme |
8 days |
Wed 12-06-19 |
Fri 21-06-19 |
23 |
Workers, Contractors |
4.5 |
Deciding for seating |
5 days |
Mon 24-06-19 |
Fri 28-06-19 |
25 |
Workers, Chairs [1], Tables [1] |
4.6 |
Making Appointment with Marriage Registrar on wedding day |
1 day |
Thu 30-05-19 |
Thu 30-05-19 |
22 |
Event Manager, Registrar Cost [1] |
4.7 |
Reviewing the arrangements |
5 days |
Mon 24-06-19 |
Fri 28-06-19 |
27,25 |
Event Manager, Contractors |
5 |
Wedding day |
1 day |
Sun 30-06-19 |
Sun 30-06-19 |
||
5.1 |
Reaching the venue |
1 hr |
Sun 30-06-19 |
Sun 30-06-19 |
28 |
Client |
5.2 |
Reviewing the preparations |
1 hr |
Sun 30-06-19 |
Sun 30-06-19 |
30 |
Event Manager, Project Manager |
5.3 |
Guests welcome |
20 mins |
Sun 30-06-19 |
Sun 30-06-19 |
31 |
Speaker [1] |
5.4 |
Carrying out wedding ceremony |
4 hrs |
Sun 30-06-19 |
Sun 30-06-19 |
32 |
Solemniser |
5.5 |
Dance by the couples |
10 mins |
Sun 30-06-19 |
Sun 30-06-19 |
33 |
Band |
5.6 |
Cutting the cake |
18 mins |
Sun 30-06-19 |
Sun 30-06-19 |
34 |
Cake [1] |
5.7 |
Wedding Dinner/Lunch |
70 mins |
Sun 30-06-19 |
Sun 30-06-19 |
35 |
Food and Beverages [1] |
The table which is generally given blow mainly reflects on the cost of the resources that are required for the project work. The cost for the human resources is provided in per/hour format whereas the cost of the needed materials is provided. The entire cost that is needed helps in calculating the cost that is associated with the project.
Resource Name |
Type |
Max. Units |
Std. Rate |
Client |
Work |
100% |
$0.00/hr |
Project Manager |
Work |
100% |
$100.00/hr |
Event Manager |
Work |
100% |
$80.00/hr |
Planner |
Work |
100% |
$70.00/hr |
Resource Manager |
Work |
100% |
$75.00/hr |
Workers |
Work |
100% |
$60.00/hr |
Contractors |
Work |
100% |
$70.00/hr |
Decoration Items |
Material |
$1,500.00 |
|
Cameraman Pay |
Material |
$1,260.00 |
|
Videographer Pay |
Material |
$1,300.00 |
|
Vendor Cost |
Material |
$1,200.00 |
|
Dress Cost |
Material |
$1,179.00 |
|
Band Pay |
Material |
$621.00 |
|
Solemniser pay |
Material |
$700.00 |
|
Chairs |
Material |
$600.00 |
|
Tables |
Material |
$800.00 |
|
Registrar Cost |
Material |
$800.00 |
|
Speaker |
Material |
$500.00 |
|
Solemniser |
Cost |
||
Band |
Cost |
||
Cake |
Material |
$200.00 |
|
Food and Beverages |
Material |
$600.00 |
The entire timescale that is generally developed in order to organize as well as manage the wedding event is reflected below in the table. It is found that the entire time that is generally required for organizing the wedding will be around 130 days and therefore the entire plan will be ready before 30th June which is the wedding date.
WBS |
Task Name |
Duration |
Start |
Finish |
0 |
Organizing a wedding |
130 days |
Tue 01-01-19 |
Sun 30-06-19 |
1 |
Initial Planning |
50 days |
Tue 01-01-19 |
Mon 11-03-19 |
1.1 |
Selection of the wedding date |
15 days |
Tue 01-01-19 |
Mon 21-01-19 |
1.2 |
Consultation with the wedding planner |
10 days |
Tue 22-01-19 |
Mon 04-02-19 |
1.3 |
Making plan for the wedding |
20 days |
Tue 05-02-19 |
Mon 04-03-19 |
1.4 |
Accumulating the needed resources |
5 days |
Tue 05-03-19 |
Mon 11-03-19 |
1.5 |
Project kick off |
0 days |
Mon 11-03-19 |
Mon 11-03-19 |
2 |
Venue Booking and Invitation |
40 days |
Tue 05-03-19 |
Mon 29-04-19 |
2.1 |
Selection and booking of venue for wedding and reception |
10 days |
Tue 12-03-19 |
Mon 25-03-19 |
2.2 |
Reviewing the plan with the clients |
6 days |
Tue 05-03-19 |
Tue 12-03-19 |
2.3 |
Getting approval |
1 day |
Wed 13-03-19 |
Wed 13-03-19 |
2.4 |
Guest list |
10 days |
Tue 26-03-19 |
Mon 08-04-19 |
2.5 |
Sending invitation to the guests |
15 days |
Tue 09-04-19 |
Mon 29-04-19 |
2.6 |
Initiation and Planning Phase Completed |
0 days |
Mon 29-04-19 |
Mon 29-04-19 |
3 |
Human Resource Management |
16 days |
Tue 30-04-19 |
Tue 21-05-19 |
3.1 |
Selecting vendor and sorting food items for wedding dinner |
8 days |
Tue 30-04-19 |
Thu 09-05-19 |
3.2 |
Cameron and video man hire |
2 days |
Tue 30-04-19 |
Wed 01-05-19 |
3.3 |
Try-outs for wedding dress and placing order |
7 days |
Tue 30-04-19 |
Wed 08-05-19 |
3.4 |
Booking for the musical instruments and other requirements including lightening |
8 days |
Thu 02-05-19 |
Mon 13-05-19 |
3.5 |
RSVP from guests is received |
4 days |
Tue 14-05-19 |
Fri 17-05-19 |
3.6 |
Booking Solemniser/Wedding Priest |
2 days |
Mon 20-05-19 |
Tue 21-05-19 |
4 |
Venue Arrangement |
28 days |
Wed 22-05-19 |
Fri 28-06-19 |
4.1 |
Consultation with decorator to decorate |
6 days |
Wed 22-05-19 |
Wed 29-05-19 |
4.2 |
Theme selection for wedding and reception |
9 days |
Thu 30-05-19 |
Tue 11-06-19 |
4.3 |
Arranging flowers and other decorative items |
3 days |
Wed 12-06-19 |
Fri 14-06-19 |
4.4 |
Decorating the Wedding Venue as per theme |
8 days |
Wed 12-06-19 |
Fri 21-06-19 |
4.5 |
Deciding for seating |
5 days |
Mon 24-06-19 |
Fri 28-06-19 |
4.6 |
Making Appointment with Marriage Registrar on wedding day |
1 day |
Thu 30-05-19 |
Thu 30-05-19 |
4.7 |
Reviewing the arrangements |
5 days |
Mon 24-06-19 |
Fri 28-06-19 |
5 |
Wedding day |
1 day |
Sun 30-06-19 |
Sun 30-06-19 |
5.1 |
Reaching the venue |
1 hr |
Sun 30-06-19 |
Sun 30-06-19 |
5.2 |
Reviewing the preparations |
1 hr |
Sun 30-06-19 |
Sun 30-06-19 |
5.3 |
Guests welcome |
20 mins |
Sun 30-06-19 |
Sun 30-06-19 |
5.4 |
Carrying out wedding ceremony |
4 hrs |
Sun 30-06-19 |
Sun 30-06-19 |
5.5 |
Dance by the couples |
10 mins |
Sun 30-06-19 |
Sun 30-06-19 |
5.6 |
Cutting the cake |
18 mins |
Sun 30-06-19 |
Sun 30-06-19 |
5.7 |
Wedding Dinner/Lunch |
70 mins |
Sun 30-06-19 |
Sun 30-06-19 |
The strategies that are generally needed to be followed for successfully executing the project activities are generally elaborated below.
Proper planning: It is very much necessary to develop proper plan for the wedding event that must include information as well as details about the project so that the team members who are involved with the project work can easily understand the work and can be able to execute it successfully. It is identified that appropriate information generally assists in accomplishing the goals and project objectives quite successfully.
Hiring experienced and skilled leaders: It is very much necessary to hire experienced as well as skilled project managers who must have the capability of managing the project work quite successfully for implementing the work of the project. It is found that experienced team members can easily handle the situation of the project and are able to execute the project work quite effectively.
Building high performing team: It is one of the responsibilities of the project manager to build high performing team of the project so that the team members of the project can actively work within the project in order to execute the objectives quite successfully without facing any challenges or issues within the organization.
Tracking the project: It is very much necessary to track the project quite successfully in order to get proper information about the status of the project on a regular basis so that the work that is associated with the project can generally be finished within the expected time as well as budget. This generally assists in implementing the project quite successfully.
Praising team effort: If the project manager takes the responsibility of praising the effort of the team then they will get inspired and work successfully in order to meet the goals as well as objectives of the project very much successfully.
The measures that are generally developed in order to monitor as well as evaluate the progress of the project are generally elaborated below:
Clarifying the expectations: It is very much necessary to clarify the expectations of the clients while performing the project in order to make sure that the work that is associated with the project can be completed successfully as per the expectations of the clients.
Setting proper regular as well as monitoring intervals: It is quite necessary to monitor the progress of the project on a regular basis by checking the project status for making sure that the entire project will be completed within the assumed time. In addition to this, monitoring progress helps in analyzing the risks and challenges which are associated with the project so that the challenges can be resolved by taking proper steps.
Analyzing whether the project goals are achieved: It is very much necessary to check whether the objectives and goals of the project are achieved or not. If the project goals and objectives are achieved then it can be ensured that the project is on the right track and it be finished successfully.
Percent complete: It is quite necessary to analyze the progress of the project in order to gather information related with the percentage complete. If proper information related with percentage complete is generally gathered then it can be ensured that the project is on the right track and it will get completed successfully within the expected time as well as budget.
Badewi, A. (2016). The impact of project management (PM) and benefits management (BM) practices on project success: Towards developing a project benefits governance framework. International Journal of Project Management, 34(4), 761-778.
Cagliano, A. C., Grimaldi, S., & Rafele, C. (2015). Choosing project risk management techniques. A theoretical framework. Journal of Risk Research, 18(2), 232-248.
Conforto, E. C., Amaral, D. C., da Silva, S. L., Di Felippo, A., & Kamikawachi, D. S. L. (2016). The agility construct on project management theory. International Journal of Project Management, 34(4), 660-674.
Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., & de Almeida, L. F. M. (2014). Can agile project management be adopted by industries other than software development?. Project Management Journal, 45(3), 21-34.
Costantino, F., Di Gravio, G., & Nonino, F. (2015). Project selection in project portfolio management: An artificial neural network model based on critical success factors. International Journal of Project Management, 33(8), 1744-1754.
Drouin, N., Sankaran, S., & Muller, R. (2016). The nature of organizational project management and its role as an organizational capability. Manageable Cooperation?.
Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), 291-298.
Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), 1377-1392.
Kaiser, M. G., El Arbi, F., & Ahlemann, F. (2015). Successful project portfolio management beyond project selection techniques: Understanding the role of structural alignment. International Journal of Project Management, 33(1), 126-139.
Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.
Kucharska, W., & Kowalczyk, R. (2016). Trust, collaborative culture and tacit knowledge sharing in project management–A relationship model.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A. M. E., & Villanueva, P. (2014). Project risk management methodology for small firms. International journal of project management, 32(2), 327-340.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.
Sánchez, M. A. (2015). Integrating sustainability issues into project management. Journal of Cleaner Production, 96, 319-330.
Serra, C. E. M., & Kunc, M. (2015). Benefits realisation management and its influence on project success and on the execution of business strategies. International Journal of Project Management, 33(1), 53-66.
Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), 278-290.
Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), 1382-1394.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download