This project is based on the development and implementation of a new strategic path for Netflix. Netflix is an online video streaming company that provides services to over 150 countries around the world. Initially, the company started out with video rentals service where the customers were provided with online copies of DVDs on rental basis. However, the company slowly adopted movie streaming services that could be viewed if the users subscribed to the services by paying a certain amount of money. With further development in the customer base and significant increase in popularity, Netflix also started streaming TV series that they produced in their own production house.
In spite of the popularity of Netflix around the world, users are slowly becoming concerned about the extremely high subscription prices. Furthermore, availability of free download websites like torrents provide better alternative to the users rather than paying high amount of subscription money to Netflix every month. Hence, Netflix needs new business strategy to solve these problems and maintain the current hold in video streaming market. In this report, a project charter has provided that aims to address the project plan requirements for deployment of new business strategy of Netflix.
This project is based on the development and implementation of a new strategic plan for Netflix in order to address the issues currently arising in their existing business strategies and policies. It has been found that in spite of massive popularity of Netflix all over the world as well as increasing number of subscriptions every year, there is also growing concern due to the high subscription prices that the users have to pay. From an analysis, it has been found that the increase in the number of customers for 2017 has been much less than the previous year. This is mainly because there are other alternatives like pirated movie websites, torrents and other sites where the users can download the TV series or movies for free or at minimal costs whereas at Netflix website / app, they have to pay very high subscription fees each month. On the other hand, Netflix being only a video streaming business has to recover a huge amount of expenses encountered during the production of the originals (TV series and movies). Netflix has also developed its own production house where the Netflix Originals movies and series are filmed. These costs have to be recovered through streaming revenue and the subscription money paid by the customers.
The project scope includes the following.
Accordingly, the objectives of the project are as follows.
The list of stakeholders and their duties for this project is prepared in the following table.
Name |
Designation |
Role |
Reed Hastings |
CEO / Project Manager |
To approve, manage, control and supervise the project |
Jonathan Hendricks |
Finance Manager |
To manage and allocate project funds |
David Thompson |
Business Strategies Manager |
To manage and control project as per company’s business strategies and alignment |
James Hudson |
Systems Manager |
To manage hardware and software operations and implementations |
Matias Hernandez |
Procurement Manager |
To procure necessary resources required for the purpose of the project |
Eddie Charlton |
Consultancy Manager |
To consult with various agencies for implementation of new systems like ERP, SAP, etc. |
The work breakdown structure for the project is shown in the following diagram.
Figure 1: Work Breakdown Structure of the Project
(Source: Created by Author)
The estimated project schedule and the duties of the stakeholders in the project are shown in the following table.
Task Name |
Duration |
Start |
Finish |
Resource Names |
Development and Implementation of New Business System for Netflix |
300 days |
Mon 02-04-18 |
Fri 24-05-19 |
|
Survey, Discussion, Analysis |
66 days |
Mon 02-04-18 |
Mon 02-07-18 |
|
Initial Survey |
15 days |
Mon 02-04-18 |
Fri 20-04-18 |
Business Strategies Manager, Project Manager, Systems Manager |
Collection of Survey Data |
15 days |
Mon 23-04-18 |
Fri 11-05-18 |
Business Strategies Manager, Project Manager, Systems Manager |
Analysis of Survey Data |
30 days |
Mon 14-05-18 |
Fri 22-06-18 |
Business Strategies Manager, Project Manager, Systems Manager |
Board Meeting |
2 days |
Mon 25-06-18 |
Tue 26-06-18 |
Business Strategies Manager, Project Manager, Systems Manager, Consultancy Manager, Finance Manager |
Identification of Issues |
2 days |
Wed 27-06-18 |
Thu 28-06-18 |
Business Strategies Manager, Project Manager, Systems Manager, Consultancy Manager, Finance Manager |
Identification of the Grievances of the Customers |
1 day |
Fri 29-06-18 |
Fri 29-06-18 |
Business Strategies Manager, Project Manager, Systems Manager, Consultancy Manager, Finance Manager |
Identification of Possible Solutions |
1 day |
Fri 29-06-18 |
Fri 29-06-18 |
Business Strategies Manager, Project Manager, Systems Manager, Consultancy Manager, Finance Manager |
Checking Business Feasibility of the Solutions |
1 day |
Fri 29-06-18 |
Fri 29-06-18 |
Business Strategies Manager, Project Manager, Systems Manager, Consultancy Manager, Finance Manager |
Reaching a Final Conclusion |
1 day |
Fri 29-06-18 |
Fri 29-06-18 |
Business Strategies Manager, Project Manager, Systems Manager, Consultancy Manager, Finance Manager |
Decide a Solution for Implementation |
1 day |
Mon 02-07-18 |
Mon 02-07-18 |
Business Strategies Manager, Project Manager, Systems Manager, Consultancy Manager, Finance Manager |
End of First Meeting |
0 days |
Mon 02-07-18 |
Mon 02-07-18 |
|
Second Meeting and Approval |
9 days |
Tue 03-07-18 |
Fri 13-07-18 |
|
Second Board Meeting |
1 day |
Tue 03-07-18 |
Tue 03-07-18 |
Business Strategies Manager, Consultancy Manager, Project Manager, Systems Manager |
Discussion Regarding the Chosen Plan |
1 day |
Wed 04-07-18 |
Wed 04-07-18 |
Business Strategies Manager, Consultancy Manager, Project Manager, Systems Manager |
Estimation of Overall Budget for Project |
1 day |
Thu 05-07-18 |
Thu 05-07-18 |
Business Strategies Manager, Consultancy Manager, Project Manager, Systems Manager |
Estimation of Overall Timeline for Project |
1 day |
Fri 06-07-18 |
Fri 06-07-18 |
Business Strategies Manager, Consultancy Manager, Project Manager, Systems Manager |
Discussion Regarding Project Feasibility |
1 day |
Mon 09-07-18 |
Mon 09-07-18 |
Business Strategies Manager, Consultancy Manager, Project Manager, Systems Manager |
Preparation of Project Proposal |
4 days |
Tue 10-07-18 |
Fri 13-07-18 |
Business Strategies Manager, Consultancy Manager, Project Manager, Systems Manager |
Project Approval |
0 days |
Fri 13-07-18 |
Fri 13-07-18 |
|
Planning for the Project |
29 days |
Mon 16-07-18 |
Thu 23-08-18 |
|
Development of Project Charter |
4 days |
Mon 16-07-18 |
Thu 19-07-18 |
Business Strategies Manager, Consultancy Manager, Systems Manager |
Preparation of Accurate Project Timeline |
2 days |
Fri 20-07-18 |
Mon 23-07-18 |
Business Strategies Manager, Consultancy Manager, Systems Manager |
Preparation of Accurate Project Budget |
2 days |
Tue 24-07-18 |
Wed 25-07-18 |
Business Strategies Manager, Consultancy Manager, Systems Manager |
Estimation of Resources Required for the Project |
1 day |
Thu 26-07-18 |
Thu 26-07-18 |
Business Strategies Manager, Consultancy Manager, Systems Manager |
Develop and Approve Project Scope |
1 day |
Fri 27-07-18 |
Fri 27-07-18 |
Business Strategies Manager, Consultancy Manager, Systems Manager |
Meet with Business Solutions Consultancy |
5 days |
Mon 30-07-18 |
Fri 03-08-18 |
Business Strategies Manager, Consultancy Manager, Systems Manager |
Prepare a Deployment Plan |
3 days |
Mon 06-08-18 |
Wed 08-08-18 |
Business Strategies Manager, Consultancy Manager, Systems Manager |
Analyze Risks Associated with Project |
5 days |
Thu 09-08-18 |
Wed 15-08-18 |
Business Strategies Manager, Consultancy Manager, Systems Manager |
Prepare Addressing Plan for the Risks |
2 days |
Thu 16-08-18 |
Fri 17-08-18 |
Business Strategies Manager, Consultancy Manager, Systems Manager |
Final Feasibility Tests |
3 days |
Mon 20-08-18 |
Wed 22-08-18 |
Business Strategies Manager, Consultancy Manager, Systems Manager |
Project Ready for Initiation |
1 day |
Thu 23-08-18 |
Thu 23-08-18 |
Business Strategies Manager, Consultancy Manager, Systems Manager |
Go Ahead from CEO |
0 days |
Thu 23-08-18 |
Thu 23-08-18 |
|
Initiation of the Project |
30 days |
Fri 24-08-18 |
Thu 04-10-18 |
|
Appointment of Project Stakeholders |
5 days |
Fri 24-08-18 |
Thu 30-08-18 |
Project Manager |
Deployment of Project Team |
2 days |
Fri 31-08-18 |
Mon 03-09-18 |
|
Allocate Duties to Each Team Member and Stakeholder |
1 day |
Tue 04-09-18 |
Tue 04-09-18 |
Project Team Leader |
Hand Over Project Schedule to the Stakeholders |
1 day |
Wed 05-09-18 |
Wed 05-09-18 |
Project Manager |
Procurement of Project Funds |
5 days |
Thu 06-09-18 |
Wed 12-09-18 |
Procurement Manager |
Provide the Funds to the Finance Manager’s Account |
1 day |
Thu 13-09-18 |
Thu 13-09-18 |
Procurement Manager |
Recruit System Development Team |
3 days |
Fri 14-09-18 |
Tue 18-09-18 |
Systems Manager |
Team Meeting |
1 day |
Wed 19-09-18 |
Wed 19-09-18 |
Project Manager, Project Team Leader, System Development Team, Systems Manager, Testing Team |
Discuss Project Roadmap |
1 day |
Thu 20-09-18 |
Thu 20-09-18 |
Project Manager, Project Team Leader, System Development Team, Systems Manager, Testing Team |
Selection of Personal Roles and Responsibilities in Project |
1 day |
Fri 21-09-18 |
Fri 21-09-18 |
Project Manager, Project Team Leader, System Development Team, Systems Manager, Testing Team |
Allocation of Budget to the Teams |
2 days |
Mon 24-09-18 |
Tue 25-09-18 |
Project Manager, Project Team Leader, System Development Team, Systems Manager, Testing Team |
Contact Vendor for Resources |
1 day |
Wed 26-09-18 |
Wed 26-09-18 |
Procurement Manager |
Procurement of the Resources |
5 days |
Thu 27-09-18 |
Wed 03-10-18 |
Procurement Manager |
Allocation of Resources |
1 day |
Thu 04-10-18 |
Thu 04-10-18 |
Project Team Leader |
Teams Ready to Go Ahead |
0 days |
Thu 04-10-18 |
Thu 04-10-18 |
|
Project Execution |
156 days |
Fri 05-10-18 |
Fri 10-05-19 |
|
Analysis of Existing System by System Developer |
5 days |
Fri 05-10-18 |
Thu 11-10-18 |
System Development Team |
Subscription to AWS |
5 days |
Fri 12-10-18 |
Thu 18-10-18 |
System Development Team |
Connecting the Existing Business Server with AWS |
4 days |
Fri 19-10-18 |
Wed 24-10-18 |
System Development Team |
Test the System with AWS |
5 days |
Thu 25-10-18 |
Wed 31-10-18 |
System Development Team, Testing Team |
Upgrade Hardware |
4 days |
Thu 01-11-18 |
Tue 06-11-18 |
System Development Team, Updated Hardware[1] |
Upgrade Software |
5 days |
Wed 07-11-18 |
Tue 13-11-18 |
System Development Team, Software[1] |
Develop Business ERP Solution |
30 days |
Wed 14-11-18 |
Tue 25-12-18 |
System Development Team |
Create UI for the ERP software |
10 days |
Wed 26-12-18 |
Tue 08-01-19 |
System Development Team |
Add Features to the Software |
15 days |
Wed 09-01-19 |
Tue 29-01-19 |
System Development Team |
Test the Software Demo Version |
10 days |
Wed 30-01-19 |
Tue 12-02-19 |
System Development Team, Testing Team |
Make Internal Changes and Upgrades |
15 days |
Wed 13-02-19 |
Tue 05-03-19 |
System Development Team |
Debugging |
7 days |
Wed 06-03-19 |
Thu 14-03-19 |
System Development Team |
Deploy Strong System Firewall |
6 days |
Fri 15-03-19 |
Fri 22-03-19 |
System Development Team |
Test the system |
10 days |
Mon 25-03-19 |
Fri 05-04-19 |
System Development Team, Testing Team |
Create New Exclusive Netflix Business Portal |
15 days |
Mon 08-04-19 |
Fri 26-04-19 |
System Development Team |
Final Testing and Changes |
10 days |
Mon 29-04-19 |
Fri 10-05-19 |
System Development Team, Testing Team |
Handover to Project Authority |
0 days |
Fri 10-05-19 |
Fri 10-05-19 |
|
Closing and Sign Off |
10 days |
Mon 13-05-19 |
Fri 24-05-19 |
|
Post Project Appraisal and Review |
4 days |
Mon 13-05-19 |
Thu 16-05-19 |
Project Manager |
Prepare Project Report |
5 days |
Fri 17-05-19 |
Thu 23-05-19 |
Project Team Leader |
Signoff from Stakeholders and Project Manager |
1 day |
Fri 24-05-19 |
Fri 24-05-19 |
Business Strategies Manager, Consultancy Manager, Finance Manager, Procurement Manager, Project Manager, Project Team Leader, System Development Team, Systems Manager, Testing Team |
Closing of the Project |
0 days |
Fri 24-05-19 |
Fri 24-05-19 |
The resources required for the project including their standard costs and charges are shown in the following table.
Resource Name |
Type |
Max. Units |
Std. Rate |
Ovt. Rate |
Project Manager |
Work |
100% |
$400.00/hr |
$0.00/hr |
Finance Manager |
Work |
100% |
$250.00/hr |
$0.00/hr |
Business Strategies Manager |
Work |
100% |
$325.00/hr |
$0.00/hr |
Systems Manager |
Work |
100% |
$325.00/hr |
$0.00/hr |
Procurement Manager |
Work |
100% |
$225.00/hr |
$0.00/hr |
Consultancy Manager |
Work |
100% |
$250.00/hr |
$0.00/hr |
Project Team Leader |
Work |
100% |
$175.00/hr |
$0.00/hr |
System Development Team |
Work |
100% |
$350.00/hr |
$0.00/hr |
Testing Team |
Work |
100% |
$275.00/hr |
$0.00/hr |
Updated Hardware |
Material |
$150,000.00 |
||
Software |
Material |
$125,000.00 |
The Gantt chart of the project is shown in the following diagram.
Figure 2: Gantt Chart of the Project
(Source: Created by Author)
The critical path analysis is shown in the following diagram.
Figure 3: Critical Path Analysis of the Project
(Source: Created by Author)
The overall estimated budget for the project is shown in the following table.
Resource |
Estimated Budget |
Human Resource (From Gantt Chart) |
$ 1,587,400 |
Hardware Costs |
$ 150,000 |
Software Costs |
$ 125,000 |
Development Costs |
$ 200,000 |
Testing Costs |
$ 125,000 |
Business Implementation Costs |
$ 165,000 |
TOTAL |
$ 2,352,400 |
Quality assurance plan is required in every project in order to ensure the project meets the best quality standards. Furthermore, for this large scale and high budget project for Netflix, quality assurance plan must be prepared before the project is executed.
The list of policies and requirements to be following during quality assurance is as follows.
The possible risks associated with the project as well as suitable management plans are shown in the following table.
Risk Details |
Chance of Occurrence |
Impact on Project |
Management Plan |
Budget Overshoot, caused due to scope creep or excessive overspend during the project |
High |
Very High |
Prepare accurate budget plan during planning, try to remain within the limits of the allocated budget to complete the works in the project |
Failed Implementation, due to lack of quality resources, fraud consultancy and others |
Medium |
Extreme |
Check background details of the consultancy before hiring, conduct quality check on the resources before purchase |
Cyber Attack, due to lack of system firewall, external attackers, malwares and others may enter into and harm the company database |
Very High |
Extreme |
Use strong system firewalls, cyber security softwares, system cleaners and others to minimize chances of cyber attacks |
Conclusion
In this report, a detailed project plan has been provided for the new strategic development of Netflix. As per the analysis of the existing issues and problems faced by Netflix, deployment of an ERP system as well as migration of the entire database into cloud have been suggested as part of the recommendation for the project. Following the scope and objectives of the project, an estimated budget has been developed along with a rough schedule. Furthermore, stakeholder analysis, quality assurance and risk management plans have also been provided. However, it should be noted that this is only a rough initial plan that needs to be further developed with more accurate estimations before it can be used as the plan of the actual project.
References
Boud, D., Cohen, R. and Sampson, J. eds., 2014. Peer learning in higher education: Learning from and with each other. Routledge.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.
Fuller, M.A., Valacich, J.S., George, J.F. and Schneider, C., 2017. Information Systems Project Management: A Process and Team Approach, Edition 1.1. Prospect Press.
Heagney, J., 2016. Fundamentals of project management. AMACOM Div American Mgmt Assn.
Heldman, K., 2018. PMP: project management professional exam study guide. John Wiley & Sons.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Leach, L.P., 2014. Critical chain project management. Artech House.
Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and technology. Taylor & Francis.
Pinto, J.K., 2015. Project management: achieving competitive advantage. Prentice Hall.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Snyder, C.S., 2014. A guide to the project management body of knowledge: PMBOK (®) guide. Project Management Institute: Newtown Square, PA, USA.
Turner, R., 2016. Gower handbook of project management. Routledge.
Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.
Walker, A., 2015. Project management in construction. John Wiley & Sons.
The resources required for the project including their standard costs and charges are shown in the following table.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download