According to Kubba (2010), the project planning and development had been largely helpful for the implication of the innovative and effective work completion. The project plan would be effectively implied with the formation of the project case study of ‘Construction of Regency Plaza Hotels and Condominiums’. The project management for construction projects would be required for the integration of the smart work alignment and development (Gorse & Emmitt, 2009). The following assignment would include the listing of the project contract management, project planning, controlling communication, and closure for the mentioned project. The document would support the successful transfer of the information to the required stakeholders.
Part A: Project Contracts
Legal benefits and Challenges of different types of contracts
The project contracts are helpful for developing the bond of work-fee between two or more parties (Forgues & Koskela, 2009). The participating parties would agree to deliver product/service to the other party in exchange of monetary benefits. The contract would also enable the stabilization of the advanced work alignment for the project of Construction of Regency Plaza Hotels and Condominiums. The contract management for the organization had been supported by the utilization of the contracts like Stipulated or lump-sum contract, Cost of work plus fee contract, Cost of work plus fee with guaranteed maximum price (GMP) contract, Construction management (CM) contract, and Design-build or design-and-construct (D&C) contract (Chen & Jin, 2012). These contracts have helped in gaining legal benefits along with some challenges as explained below.
Contract Type |
Legal benefits |
Challenges |
Stipulated or lump-sum contract |
Single fixed price bid for all activities of project scope Contractor would bear the risk associated with the project Reducing the construction cost expense |
Proposition of Unbalanced bids Changes required for the scope and design deployment Compensation requirement for early completion |
Cost of work plus fee contract |
It is budget friendly for the contractor Cost can be reimbursed as the work is aligned Limitation on the money expended by the contractor |
Requirement of justification for each of the costs No track of the indirect costs is another issue Pre-decided profit would limit the scope for gaining more profit from the project |
Cost of work plus fee with guaranteed maximum price (GMP) contract |
Ease is procuring the contracts for the project Easy accumulation of the funds for the project Incentive option available for work completion |
No mechanism for calculating the losses to the contractor Losing the contract due to high pricing |
Construction management (CM) contract |
Inclusion of the responsibility for the expertise of entire management The contract is continuous irrespective of the project manger |
Confidentiality Disputes are common in this contract Difficulty in management of the conflicts in the project |
Design-build or design-and-construct (D&C) contract |
Single Point Responsibility Improved efficiency due to design and construction expertise Few Changes are required as the implementation is simplified Increased Flexibility |
Owner Involvement is reduced Extra cost of risk and contingencies plan Limited qualified designer and builders Larger and complex in nature |
Mitigation of Challenges
Contract Type |
Challenges |
Mitigation of the Challenges |
Stipulated or lump-sum contract |
Proposition of Unbalanced bids Changes required for the scope and design deployment Compensation requirement for early completion |
Implication of the fair bid recognition should be implied Negotiable Compensation method should be followed |
Cost of work plus fee contract |
Requirement of justification for each of the costs No track of the indirect costs is another issue Pre-decided profit would limit the scope for gaining more profit from the project |
Cost management plan should be developed Detail cost (both direct and indirect) should be used Limited profit acquisition should be used |
Cost of work plus fee with guaranteed maximum price (GMP) contract |
No mechanism for calculating the losses to the contractor Losing the contract due to high pricing |
Contingency planning for the monetary losses Optimized costing should be used |
Construction management (CM) contract |
Confidentiality Disputes are common in this contract Difficulty in management of the conflicts in the project |
Negotiation should be followed for contract development |
Design-build or design-and-construct (D&C) contract |
Owner Involvement is reduced Extra cost of risk and contingencies plan Limited qualified designer and builders Larger and complex in nature |
Effective communication strategies should be used Training should be provided to the people Complex project management should be used |
Selection and Justification of the Design-Build-Contract
The contract of Design-Build-Contract should be used for the completion of the activities of the Construction of Regency Plaza Hotels and Condominiums project. The design bid build contract would allow the flexibility of the works for managing the change requirements, and implication of the smart work development and implication management (Carden & Boyd, 2012). The construction of the hotel rooms and condominiums would require inclusion of the design principles and construction of the facility.
Since, the project comprise of designing and constructing the building, floor, condominiums, and parking, the utilization of the design and build contract would be helpful for compiling work development. The single point responsibility in the design bid build contract would allow the manager/contractor to get the complete authorization over the project activities (Lester, 2014). The contract would help in improving the efficiency due to design and construction expertise for the construction project. Moreover, only few changes are required as the implementation is simplified using the contract which can be implemented due to the fact of increased flexibility.
Project Pre-Planning
Identified Challenges and Mitigation Strategies of Project
The identified challenges for the Construction of Regency Plaza Hotels and Condominiums project and their mitigation strategies are given below,
Project Phase |
Challenges |
Type |
Mitigation Strategy |
Planning |
Delay in building permit approval is a major issue that result in forming the major problems in completion of the project |
Operational |
Time Management Plan aligned with Project Baseline |
Construction |
Many minute changes in conceptual design had been resulting in forming change requirements for the project |
Design |
Change management plan should be used for effective change implication |
Construction |
Delay in construction of condominiums would result in causing loss to the organization |
Operational |
Time Management Plan aligned with Project Baseline |
Construction |
Rift between contractors (of hotel and condominiums) for worker distribution as the number of workers have reduced to 250 and the amount of work required for construction of hotel and condominiums is huge |
Human |
Effective Communication plan should be used for analyzing the requirements of both the contractor and hiring more workers for completion of the project on time |
Finish |
Unable to meet the punch list as the smaller items of the hotel and condominiums are not being equipped |
Procurement |
Continuous improvement plan steps should be followed for defining the works of the punch list |
Approach for on-time delivery of project
As per the study of Levy (2010), the development of the project schedule and cost baseline report would be helpful for defining the estimated cost and time requirements for the Construction of Regency Plaza Hotels and Condominiums project. The on-time delivery of the project would include the formation of the task checklist so that the implication of the effective work alignment would be implied. The checklist development would enable the utilization of the monitoring of the project completion. The following approach should be used,
Step 1- Using MS-Project for making schedule for the project (for example: it would help in defining all activities of the project)
Step 2- Developing Task Checklist with expected durations (for example: it would help in keeping track of the project progress)
Step 3- Development of resource management and risk management plan
Step 4- Consider all contingency plan for the project
Step 5- Monitoring the project performance
Step 6- Change Management should be included
Step 7- Evaluation of the progress
Organization of Project cost
The project of Construction of Regency Plaza Hotels and Condominiums was set for the budget of $157m. The construction of the condominiums would be effectively implied with the implication of the resource usage. The project cost would be divided into human resource usage, Cost of material usage, contingency cost, and fixed cost (Olawale & Sun, 2010). The following is the budget management plan for the project,
Particulars |
Standard rate |
Duration/Units |
Cost |
Total |
Human Resources |
||||
Project Manager |
$450.00 |
250 |
$112,500.00 |
|
Designer for Hotel |
$300.00 |
130 |
$39,000.00 |
|
Designer for Condominiums |
$300.00 |
150 |
$45,000.00 |
|
Contractor for Hotel |
$350.00 |
300 |
$105,000.00 |
|
Contractor for Condominiums |
$350.00 |
350 |
$122,500.00 |
|
Workers (250 workers) |
$110.00 |
1300 |
$35,750,000.00 |
|
Painter |
$250.00 |
200 |
$50,000.00 |
|
Carpenter |
$250.00 |
280 |
$70,000.00 |
|
Sub Total |
$36,294,000.00 |
|||
Material Resources |
$0.00 |
|||
Construction Materials |
$150,000.00 |
250 |
$37,500,000.00 |
|
Equipment and Appliances |
$130,000.00 |
400 |
$52,000,000.00 |
|
Others |
$15,000.00 |
200 |
$3,000,000.00 |
|
Sub Total |
$92,500,000.00 |
|||
Fixed Cost |
||||
Electricity |
$250,000.00 |
1 |
$250,000.00 |
|
Water utility |
$200,000.00 |
1 |
$200,000.00 |
|
Transportation |
$75,000.00 |
4 |
$300,000.00 |
|
Health and Safety |
$100,000.00 |
5 |
$500,000.00 |
|
Sub Total |
$1,250,000.00 |
|||
Contingency |
$20,807,040.00 |
|||
Total Budget |
$150,851,040.00 |
The project schedule has been developed using the MS-Project as a scheduling tool and the work breakdown structure identification can be done from the schedule developed below,
WBS |
Task Name |
Duration |
Start |
Finish |
0 |
Construction of Regency Plaza Hotels and Condominiums |
370 days |
Mon 12/5/05 |
Fri 5/4/07 |
1 |
Planning |
61 days |
Mon 12/5/05 |
Mon 2/27/06 |
1.1 |
Requirement Analysis |
10 days |
Mon 12/5/05 |
Fri 12/16/05 |
1.2 |
Bidding Process |
15 days |
Mon 12/19/05 |
Fri 1/6/06 |
1.3 |
Hiring of Team Members |
10 days |
Mon 1/9/06 |
Fri 1/20/06 |
1.4 |
Proposal |
10 days |
Mon 1/23/06 |
Fri 2/3/06 |
1.5 |
15 days |
Mon 2/6/06 |
Fri 2/24/06 |
|
1.6 |
Initial Meeting |
1 day |
Mon 2/27/06 |
Mon 2/27/06 |
1.7 |
Kick off |
0 days |
Mon 2/27/06 |
Mon 2/27/06 |
2 |
Construction |
247 days |
Tue 2/28/06 |
Wed 2/7/07 |
2.1 |
Conceptual Design |
17 days |
Tue 2/28/06 |
Wed 3/22/06 |
2.2 |
Detailed Design |
24 days |
Thu 3/23/06 |
Tue 4/25/06 |
2.3 |
Floor Works |
35 days |
Wed 4/26/06 |
Tue 6/13/06 |
2.4 |
Steel and Concrete Works |
40 days |
Wed 6/14/06 |
Tue 8/8/06 |
2.5 |
22 storey construction |
50 days |
Wed 8/9/06 |
Tue 10/17/06 |
2.6 |
96 Condominiums were built |
60 days |
Wed 8/9/06 |
Tue 10/31/06 |
2.7 |
Underground Parking were built |
30 days |
Wed 11/1/06 |
Tue 12/12/06 |
2.8 |
Hotel Room Division was built |
16 days |
Wed 12/13/06 |
Wed 1/3/07 |
2.9 |
Installation of equipment and devices at rooms and condominiums |
20 days |
Thu 1/4/07 |
Wed 1/31/07 |
2.10 |
Monitoring the facilities |
5 days |
Thu 2/1/07 |
Wed 2/7/07 |
2.11 |
Completed |
0 days |
Wed 2/7/07 |
Wed 2/7/07 |
3 |
Finish |
62 days |
Thu 2/8/07 |
Fri 5/4/07 |
3.1 |
Interior and External Paints |
20 days |
Thu 2/8/07 |
Wed 3/7/07 |
3.2 |
Finalize the works |
8 days |
Thu 3/8/07 |
Mon 3/19/07 |
3.3 |
Drapes and Pillow works |
10 days |
Tue 3/20/07 |
Mon 4/2/07 |
3.4 |
Counter Tops |
5 days |
Tue 4/3/07 |
Mon 4/9/07 |
3.5 |
Finish Plumbing and Electric |
12 days |
Tue 4/10/07 |
Wed 4/25/07 |
3.6 |
Complete Punch List |
7 days |
Thu 4/26/07 |
Fri 5/4/07 |
3.7 |
Closed |
0 days |
Fri 5/4/07 |
Fri 5/4/07 |
The first column has shown the WBS id for each of the activity which can be used for the development of the WBD diagram as below The specific work packages has been explained below,
Work Package |
Description |
Activities Involved |
Milestone |
Planning |
Initial analysis, documentation, and planning would be done in this phase |
Requirement Analysis, Bidding Process, Hiring of Team Members, Proposal, Building Permit Approval, and Initial Meeting |
Kick off |
Construction |
Constructing the hotel, Condominiums, and parking lot |
Conceptual Design, Detailed Design, Floor Works, Steel and Concrete Works, 22 storeys construction, 96 Condominiums were built, Underground Parking were built, Hotel Room Division was built, Installation of equipment and devices at rooms and condominiums, and Monitoring the facilities |
Completed |
Finish |
Final Closure of the project with last activities |
Interior and External Paints, Finalize the works, Drapes and Pillow works, Counter Tops, Finish Plumbing and Electric, and Complete Punch List |
Closed |
Controlling Communication
Communication Management Plan
The communication management plan would include the following steps for the project of Construction of Regency Plaza Hotels and Condominium,
Method of Communication |
Sender |
Receiver |
Frequency |
Information |
Emails |
Project client/manager |
Project manager/team |
Once |
Change Request, Progress |
Documents/Reports |
Project team/manager |
Project manager/client |
Weekly |
Project Issues, Progress, and Completion |
Meetings |
Project client/manager |
Project manager/team |
Once |
Project Requirements |
Addressing Project Stakeholder Expectations
The project stakeholder expectations would be addresses by the help of stakeholder engagement matrix,
Stakeholder |
Interest |
Power |
Impact |
Client (owner of regency plaza) |
Project output meeting all scope items and quality |
High |
High |
End User (renter/buyers of hotel rooms/condominium) |
Use of the end product of project |
Low |
Low |
Investors |
Returns of the project investment |
High |
High |
Project manager |
Completion of the works |
Low |
High |
The details of the project completion would be effectively implied with the formation of the development strategies (Levy, 2010). The analysis would be developed effectively for developing successful work alignment.
Role of Project Elements
Elements |
Role |
Schedule |
Project Timeline for execution of the activities |
Cost |
Ensuring the usage of the resources |
Quality |
Ensuring the construction quality is met |
Risk |
Management of the risk factors |
Lesson Learnt
The study had helped in understanding the importance of contract management, documentation, project planning, communication processes, and project closure. The use of MS-Project software for developing the project schedule, Gantt chart, and Network diagram had been effectively implied for taking care of the project completion. The study of the contracts for identifying the benefits of Stipulated or lump-sum contract, Cost of work plus fee contract, Cost of work plus fee with guaranteed maximum price (GMP) contract, Construction management (CM) contract, and Design-build or design-and-construct (D&C) contract.
Conclusion
The study had helped in understanding the importance of contract management, documentation, project planning, communication processes, and project closure. The project of ‘Construction of Regency Plaza Hotels and Condominiums’ had been used for the analysis of the importance of the project management principles and techniques for effective construction management. The use of MS-Project software for developing the project schedule, Gantt chart, and Network diagram had been effectively implied for taking care of the project completion.
It had allowed the significant management of processes and defining the explicit management of the works. The study of the contracts for identifying the benefits of Stipulated or lump-sum contract, Cost of work plus fee contract, Cost of work plus fee with guaranteed maximum price (GMP) contract, Construction management (CM) contract, and Design-build or design-and-construct (D&C) contract. The pre-planning phase had evaluated the various possible issues and the challenges needed to address using the project management tools.
Carden, L. L. & Boyd, R. O. (2012). Ethical and legal considerations for project managers. Mustang Journal of Business & Ethics 3, 10-23. Retrieved from the Torrens University Australia Library database.
Chen, Q., & Jin, R. (2012). Safety4Site commitment to enhance jobsite safety management and performance. Journal of Construction Engineering & Management, 138(4), 509-519.
Forgues, D. & Koskela, L. (2009). The influence of a collaborative procurement approach using integrated design in construction on project team performance. International Journal of Managing Projects in Business, 2(3), 370-385.
Gorse, C. A. & Emmitt, S. (2009). Informal interaction in construction progress meetings. Construction Management and Economics, (27)10, 983-993.
Kubba, S. (2010). Green construction project management and cost oversight. Oxford: Architectural Press.
Lester, A. (2014). Project management, planning and control: managing engineering, construction and manufacturing projects to PMI, APM and BSI standards (6th ed.). Oxford: Butterworth-Heinemann.
Levy, S. M. (2010). Construction process planning and management. Oxford: Butterworth-Heinemann [D1, D2, A].
Olawale, Y. A. & Sun, M. (2010). Cost and time control of construction projects: inhibiting factors and mitigating measures in practice. Construction Management and Economics, 28(5), 509-526
Project Management Institute, Inc. (2007). Construction extension to the PMBOK Guide (3rd edition).
Sacks, R., Koskela, L., Dave, B. A. & Owen, Information modeling in construction. Journal of Construction Engineering and Management, 136(9), 968-980.
Sundaram, V. (2008). Essentials of design phase cost management and budget control. Cost Engineering 50(2), 24-28.
Tuuli, M. M., Rowlinson, S. & Koh, T. Y. (2010). Control modes and mechanisms in construction project teams: drivers and consequences. Construction Management and Economics, 28(5), 451-465.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download