According to Kerzner, & Kerzner, (2017) quality on a project is the process through which the project deliverables as well as outcomes are generated in accordance to the customer’s specifications, plans and needs. Therefore, quality management complement project management in the sense that they both emphasis on customer satisfaction. Quality results in customer satisfaction.
There are various tools and techniques used for planning a project’s quality management such as cost benefits analysis, cost of quality and quality control are the primary planning tools:
Cost benefit analysis: It is also referred to as Benefit-Cost Analysis. Accordingly, this tool is used to illustrate the value of conducting a project. Therefore, cost benefit analysis plays the role of calculating the expenses involved to generate a service, product or outcome for comparison with the benefits supposed to be achieved. Similarly, cost-benefit analysis provides the present value of upcoming earnings which aid for maters of comparison with other projects.
Cost of quality (COQ): This is a tool applied in the project for purposes of decision-making. On the other hand cost of quality is defined as the aggregate expenses needed to come up with poor quality product or service to the project management defined standards.
Quality control: It is the process of monitoring as well as recording the results of executing the quality of practices to evaluate performance and provide necessary recommendation for modification (Larson, & Gray, 2015). Thus, quality control is concerned with the project results where it works to ensure that the outcomes comply with the quality standards described for the project to eliminate any causes of unsatisfying performance.
In addition other planning tools include force filed analysis (FFA), brainstorming and nominal group technique (NGT). Force filed analysis is a technique used for analysis concepts by diving these concepts in terms of their characteristic advantages against their disadvantages. Brainstorming is a technique used for collecting information whereby different unfiltered inputs are solicited and collected for later analysis and decision-making (Martinelli, & Milosevic, 2016). On the other hand, Nominal group technique is a refinement of brainstorming which include ranking of ideas as an extra mechanism in accordance to the assumptions reached by a nominal groups. Certainly, the ranking of ideas is significant as it help to generate better results as compared to the traditional brainstorming. On the other hand, there are also additional tools used in both control quality and quality planning such as scatter diagrams, histograms, control charts, Pareto diagrams, check sheets, flowcharts, and cause-and-effect diagrams. These tools are commonly referred to as Ishikawa’s seven basics tools.
The Cost of poor Quality is the expense associated with giving poor quality service or product. A good example of cost of poor quality is when a business spends money a certain project with the intention to produce a product which particular specification but the money is lost due to the product delivered not beings in the position to meet the business requirements and specifications.
Cost management plan is a process that is majorly concerned with planning, budgeting and controlling of the project. Therefore, the cost management plan entails practices such as estimating, planning, manging, budgeting, control as well as funding of the expenses of the project within the specified and certified budget. The process of cost management runs throughout the entire project lifecycle starting from initial planning stage to evaluating the actual performance cost and project accomplishment (Larson, & Gray, 2015). Consequently, the main process of project costs management include resource planning, cist budgeting, cost control and cost estimation.
Resource planning: Resource planning is the process of identifying the project’s physical resources that is individuals, materials and equipment as well as the quantities that are supposed to be used to undertake project activities (Kerzner, & Kerzner, 2017). Therefore, resource planning involves a number of inputs, tools and techniques as well as outputs.
Tools and techniques of resource planning: In order to determine the tools and resource required for resource planning its calls for expert judgement. Indeed, an expert judgement comes from an expert’s professional experience. On the same note, resource planning demand for alternative identification since projects are likely to change over time thus, it is important to take a range of scenarios into account. In so doing, it is possible to come up with solutions for use as change happens (Heagney, 2016). Therefore, alternative identification involves two approaches pattern thinking and lateral thinking. Pattern thinking is an approach that entails pattern recognition which is relevant for improvement in accordance to the previous experiences. Lateral thinking is a method that calls for creative thinking as well as problem solving which concepts which could not be obvious initially.
Outputs from resource planning: The outputs of resource planning defines the type of resources as well as the quantities in which every component included in the work breakdown structure.
Cost estimation include establishing an approximation of the expenses of the resources required to ensure that it accomplishes the project events. Therefore, cost estimation involves coming up with an evaluation of the possible quantitative results that is the amount of money that incurred by the organisation to make available the service or product needed (Heldman, 2018). As a result, cost estimation include considering and identifying different costing alternatives. Accordingly, cost estimation involves inputs, tools and techniques as well as outputs.
The inputs to cost estimation include work breakdown structure, resource requirements, resource rates, event duration estimates, historical information and chart of accounts.
Work breakdown structure: The WBS is used to identify the projects aspects that will require resources hence it is key input to resource planning.
Resource requirements: Resource planning is the process of identifying the project’s physical resources that is individuals, materials and equipment as well as the quantities that are supposed to be used to undertake project activities (Martinelli, & Milosevic, 2016). Therefore, cost estimation involves a number of inputs, tools and techniques as well as outputs.
Resource rates: It is important that the groups or person preparing the estimates is well conversant with unit rates such as the cost of employee per hour for every resource so as to compute the project costs. Certainly, in case the real rates are unknown then the rates can be estimated.
Historical information: Historical information on cost comes in a range of source s such as project files, project team knowledge and commercial cost estimation.
Event duration estimates: It illustrates the act of quantifying the amount of time which is projected that the activity will last to completion.
Chart of accounts: A chart of accounts defines the coding structure utilised by the performing company to report monetary information through its general ledger.
Analogous estimating: It involves using the real cost of a previous similar project to project the cost of the present project.
Parametric modelling: It entails use of project features using a mathematical model to project the project’s cost (Gido, Clements, & Clements, 2014).
Bottom-up estimating: It the techniques of estimating the expense of each distinct work and then rolling-up the estimate to determine the total project cost.
Computerised tools: It involves the use of computerised tools such as project management software to aid in cost estimating.
The cost estimating outputs include cost estimates, supporting details, and cost management plan.
Cost budgeting entails the general allocation of cost estimates to specific work items so that to develop a cost baseline for evaluating the performance of the project (Newton, 2016). The project cost is estimated at $275,500 as shown in the table below.
No Units/hrs |
Cost/hrs/unit ($) |
Subtotals ($) |
WBS Level 1 Total ($) |
% Total |
|
1. Project Management |
101,000 |
37.1 |
|||
Project manager |
500 |
70 |
35,000 |
||
Project team members |
1200 |
55 |
66,000 |
||
Contractors (10 of total project management) |
10,100 |
10,100 |
3.7 |
||
2. Resource planning (20% of the project management) |
20,200 |
20,200 |
7.4 |
||
3. Tools and techniques (40% of the project management) |
40,400 |
40,400 |
14.8 |
||
Hardware |
20,200 |
20,200 |
7.4 |
||
Handheld devices |
20 |
800 |
16,000 |
||
Servers |
3 |
1400 |
4,200 |
||
Software |
20,200 |
20,200 |
7.4 |
||
Licensed software |
20 |
200 |
4,000 |
||
Software development |
16,000 |
||||
4. Testing (10% of the total cost for hardware and software) |
10,100 |
3.7 |
|||
Training and support |
30,000 |
11.1 |
|||
Reserve (20% of total estimate) |
20,200 |
7.4 |
|||
Total project cost estimate |
272,500 |
100 |
Table 1: Cost management plan
Quality Management Plan
Project quality management plan is a procedure that is needed to make sure that the project is a position to satisfy the needs and specifications for which it was intended. Therefore, quality management entails all the general management functionalities which determine the quality objectives, policy as well as responsibilities (Aaltonen, & Kujala, 2010). Therefore, quality management plan involves quality control, quality planning, quality improvement, and quality assurance. Particularly, the primary quality management process include quality planning, quality assurance and quality control.
The process of quality planning include the identification of the quality standards significant to the project as well as determining ways on how to realise them. Accordingly, this is one of the chief facilitating projects during planning which has to be undertaken consistently and parallel with other processes of project planning (Sahi, 2009). Therefore, quality planning involves certain inputs tools and techniques and outputs.
Quality planning has various inputs such as:
Quality policy: Quality policy is describes as the general directive and intent of the organisation in regard to quality.
Scope statement: The scope statement is a major input to quality planning as it documents key project deliverables together with the project objectives which work to describes relevant stakeholder necessities.
Some of the tools and techniques used for ensuring quality planning include cost analysis, benchmarking, design of experiments and flowcharting.
Quality assurance is the process used to ensure that all the planned project activities are systematically implemented within the borders of quality standards to deliver confidence that the project meets the appropriate standards of quality (Ainamo et al., 2010). Certainly, quality assurance involves various inputs, tools and techniques as well as outputs. The inputs to quality assurance include quality management plan and results quality control measures. The tools and techniques for quality assurance comprises quality audits, and quality planning tools and techniques.
Quality control encompasses monitoring certain project outcomes to determine whether they agree with the accepted quality standards by looking for ways to eliminate causes of unsatisfactory outcomes (Pensar, 2010). The inputs to quality control include checklists and work lists. The tools and techniques for quality control include control charts, flowcharting, and Pareto diagrams among others. Lastly, the outputs from quality control include completed checklists, acceptance decisions, quality improvement and rework.
References:
Aaltonen, K., & Kujala, J. (2010). A project lifecycle perspective on stakeholder influence strategies in global projects. Scandinavian Journal of Management, 26(4), 381–397.
AIMS (2015). What is Project Cost Management? Tools, Techniques and Processes for PMP & PMBOK | AIMS Lecture. Retrieved from https://www.youtube.com/watch?v=PflAkMayixM
Ainamo, A., Artto, K., Levitt, R. E., Orr, R. J., Scott, W. R., & Tainio, R. (2010). Global projects: Strategic perspectives. Scandinavian Journal of Management, 26(4), 343–351.
Gido, J., Clements, J., & Clements, J. (2014). Successful project management. Nelson Education.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.
Heagney, J. (2016). Fundamentals of project management. Amacom.
Heldman, K. (2018). PMP: project management professional exam study guide. John Wiley & Sons.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Larson, E. W., & Gray, C. F. (2015). A Guide to the Project Management Body of Knowledge: PMBOK (®) Guide. Project Management Institute.
Martinelli, R. J., & Milosevic, D. Z. (2016). Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.
Newton, R. (2016). Project management step by step: how to plan and manage a highly successful project. Pearson UK.
Pensar, S. (2010, August 17). Five challenges in global projects. Retrieved from https://www.itforbusiness.org/article/five-challenges-in-global-projects/
Sahi, R. (2009). Managing Projects across the Global Enterprise. Retrieved from https://www.pmi.org/learning/managing-projects-global-six-challenges-6823
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download