The project report is based on Swaggies Australian Gifts which is a franchised gift stores retailing authentic Australian products. Due to success of the franchised gift stores into NSW, the gift store is decided to expand their business into Victoria, South Australia and Tasmania. The Wagga Wagga franchise of Swaggies needed to relocate the Administration Department and Sales Department for their premises. It involves of repainting and recarpeting of the office area. The total budget of the research plan is $30,000 and its timeframe is six weeks.
The report summarizes the project plan which includes of research project and identification of the information sources. The plan documents methodology for gathering as well as storing of information with estimation of timeline as well as budget.
The project is based on relocation of the administration department of Wagga Wagga premises which is conducted by the project manager. The premises are renovated and managed refurbishment of the Administration area which involves of repainting and recarpeting of the office area. There are lot of issues into the relocation of Administration and Sales Departments to the Baylis Street site. The project manager coordinates the decoration of the office, outfit the administration department includes of fitting of furniture and installation of the office equipments. The dimensions for the administration department are considered as 10m width as well as 10m length.
The sources of information are collected from the secondary sources such as from the company’s reports. The secondary sources describe, evaluate and discuss the evidence which is provided by means of primary sources. The data are collected by the individuals and agencies for the purpose to do this particular research study. The sources are published recently and it provides of in-depth analysis.
WBS |
Task Name |
Duration |
Start |
Finish |
Resource Names |
Cost |
0 |
Relocation of administrative department of the Wagga Wagga premises |
33 days |
Tue 2/6/18 |
Thu 3/22/18 |
$30,000.00 |
|
1 |
Initiation phase |
14 days |
Tue 2/6/18 |
Fri 2/23/18 |
$14,280.00 |
|
1.1 |
Design of the administrative department |
2 days |
Tue 2/6/18 |
Wed 2/7/18 |
Administrative Officer, Project Manager |
$1,840.00 |
1.2 |
Assign of the administrative space |
2 days |
Thu 2/8/18 |
Fri 2/9/18 |
Administrative Officer, Project Manager |
$1,840.00 |
1.3 |
Order of the chairs |
1 day |
Mon 2/12/18 |
Wed 2/14/18 |
Business Consultant, Contractor, Project Manager, Supplier |
$620.00 |
1.4 |
Order of the desks |
1 day |
Wed 2/14/18 |
Fri 2/16/18 |
Business Consultant, Project Manager |
$380.00 |
1.5 |
Ordering of new office equipment |
4 days |
Thu 2/8/18 |
Tue 2/13/18 |
Project Manager, Resource Manager, Business Consultant, Supplier |
$3,600.00 |
1.6 |
Hiring of movers |
1 day |
Mon 2/19/18 |
Mon 2/19/18 |
Project Manager, Resource Manager |
$920.00 |
1.7 |
Identification of potential office sites |
2 days |
Wed 2/14/18 |
Fri 2/16/18 |
Administrative Officer, Project Manager |
$1,840.00 |
1.8 |
Evaluation of server room requirements |
1 day |
Fri 2/16/18 |
Mon 2/19/18 |
Developer, System Vendor |
$440.00 |
1.9 |
Evaluation of computer networking requirements |
2 days |
Mon 2/19/18 |
Wed 2/21/18 |
Business Consultant, Developer |
$800.00 |
1.10 |
Order the signage for the new location |
1 day |
Wed 2/21/18 |
Thu 2/22/18 |
Project Manager, Resource Manager |
$920.00 |
1.11 |
Arrange internal maintenance services |
1 day |
Thu 2/22/18 |
Fri 2/23/18 |
Internal Customers, Project Manager |
$800.00 |
1.12 |
Authorization of the project manager |
0.5 days |
Fri 2/23/18 |
Fri 2/23/18 |
Project Manager |
$280.00 |
1.13 |
Milestone 1: Completion of initiation phase |
0 days |
Fri 2/23/18 |
Fri 2/23/18 |
$0.00 |
|
2 |
Relocation planning |
13 days |
Mon 2/26/18 |
Wed 3/14/18 |
$11,220.00 |
|
2.1 |
Appraise the assets transferred to new location |
2 days |
Mon 2/26/18 |
Tue 2/27/18 |
Internal Customers, Project Manager |
$1,600.00 |
2.2 |
Business quotes for the new space |
1 day |
Wed 2/28/18 |
Wed 2/28/18 |
Project Manager, Resource Manager, Supplier, System Vendor |
$1,400.00 |
2.3 |
Order the security system |
0.5 days |
Thu 3/1/18 |
Thu 3/1/18 |
Business Consultant, Project Manager |
$380.00 |
2.4 |
Identification of move project team |
2 days |
Thu 3/1/18 |
Mon 3/5/18 |
Internal Customers, Project Manager, Resource Manager |
$2,320.00 |
2.5 |
Making final decision on the office spaces |
4 days |
Mon 3/5/18 |
Fri 3/9/18 |
Internal Customers, Project Manager |
$2,520.00 |
2.6 |
Review of the space plans |
0.5 days |
Fri 3/9/18 |
Fri 3/9/18 |
Administrative Officer, Business Consultant, Project Manager |
$560.00 |
2.7 |
Plan procurements and risk management |
2 days |
Mon 3/12/18 |
Tue 3/13/18 |
Business Consultant, Project Manager |
$1,520.00 |
2.8 |
Defining the organizational requirements |
1 day |
Wed 3/14/18 |
Wed 3/14/18 |
Project Manager, Resource Manager |
$920.00 |
2.9 |
Milestone 2: Completion of planning phase |
0 days |
Wed 3/14/18 |
Wed 3/14/18 |
$0.00 |
|
3 |
Execution phase |
3 days |
Thu 3/15/18 |
Mon 3/19/18 |
$2,260.00 |
|
3.1 |
Direct and manage of the project work |
0.5 days |
Thu 3/15/18 |
Thu 3/15/18 |
Project Manager, Resource Manager |
$460.00 |
3.2 |
Monitor and control the project progress |
0.5 days |
Thu 3/15/18 |
Thu 3/15/18 |
Project Manager |
$280.00 |
3.3 |
Manage the risks |
1 day |
Fri 3/16/18 |
Fri 3/16/18 |
Risk Manager, Business Consultant, Project Manager |
$960.00 |
3.4 |
Manage the stakeholders |
1 day |
Mon 3/19/18 |
Mon 3/19/18 |
Project Manager |
$560.00 |
3.5 |
Milestone 3: Completion of execution phase |
0 days |
Mon 3/19/18 |
Mon 3/19/18 |
$0.00 |
|
4 |
Closure phase |
3 days |
Tue 3/20/18 |
Thu 3/22/18 |
$2,240.00 |
|
4.1 |
Close the procurements |
1 day |
Tue 3/20/18 |
Tue 3/20/18 |
Project Manager, Resource Manager |
$920.00 |
4.2 |
Delivering the project scope to the customer |
1 day |
Wed 3/21/18 |
Wed 3/21/18 |
Business Consultant, Project Manager |
$760.00 |
4.3 |
Release the project staffs |
1 day |
Thu 3/22/18 |
Thu 3/22/18 |
Project Manager |
$560.00 |
4.4 |
Milestone 4: Completion of closure phase |
0 days |
Thu 3/22/18 |
Thu 3/22/18 |
$0.00 |
Report
Swaggies is known to be a growing chain in the domain of the franchised gift which mainly in various kinds of Australian based products. This particular organization claims that the product supplied to customers are purely authentic in nature. Swaggies management team has considered some kinds of issues in this project that is relocation of administrative and sales department to new place that is Baylis Street site. Manager has presented a certain number of guidelines for making certain number of renovation and movements. This project mainly focusses on the administrative area which is present in the Baylis street and is generally involved in purchasing of new equipment’s and furniture. The following project addresses a certain number of tasks like repaint of office premises, recarpet of office premises, purchase of necessary furniture, lastly purchasing of necessary equipment’s.
Swaggies is involved in selling of wide range of products which made in Australia. There are range of products which are sold in Swaggies stores that are gift boxes, jewelery, CD’s, videos, clothing, homewares. The store also sells other kinds of products like Novelty gift, book and maps, Toys and games.
The following project addresses the important points like aims and objectives of well-known retailer that is Swaggies. The main scope of Swaggies that is customer satisfaction, making use of useful products, presentation of products has been discussed in details. After that a risk management plan has been provided with respect to Swaggies store. Two important plan that is quality management plan and change management plan has been discussed.
Swaggies is focused to become the leading retailer in the world of Australian gift products. This aim can be achieved by providing the customers with idea or logic of unique type of selection of products at much competitive prices. Swaggies store understand the fact that satisfied customers are loyal customers. So Swaggies have developed a certain number of strategies which mainly focuses in building of relationship.
This objective will help this store in returning customers to make maximum number of purchase. After that a communication plan with respect to project has been provide.Swaggies store take into the fact that a customer will be satisfied if and only if he or she has purchase the products for meeting the needs. So choosing of right products will help in understanding the needs of the various customers. After the obtaining of products, it must be presented in such a way that it can easily draw the attention of various customers. Retail merchandising generally require certain number of creative people who can easily understand and relate the products to the needs of the market.
The main objectives of Swaggie store are:
There are certain numbers of deliverables of project that are communication plan, risk management plan, Quality management plan and lastly change management plan. All these plans will ultimately help in improvisation of project.
Task Name |
Duration |
Start |
Milestone 1: Completion of initiation phase |
0 days |
Fri 2/23/18 |
Milestone 2: Completion of planning phase |
0 days |
Wed 3/14/18 |
Milestone 3: Completion of execution phase |
0 days |
Mon 3/19/18 |
Milestone 4: Completion of closure phase |
0 days |
Thu 3/22/18 |
Risk management plan
There are mainly five stages of risk management plan that are risk analysis, risk evaluation, risk acceptance, mitigation or control of risk, On-going evaluation.
Risk identifier |
Risk identification |
Risk owner |
Likelihood |
Consequences |
Risk Status |
Risk response |
R1 |
Loss of customer: It is loss of customer for an organization. Even certain number of techniques are used for retention of clients like advertisement do not work as customer do not visit new location. |
Organization (Project manager) |
Possible |
Severe on organization |
Open |
Follow up and follow through: Excellent post customer service is considered to an effective way for prevention of loss of customers. |
R2 |
Cost to business interruption: Almost any kind of business will suffer a lot of issues in terms of productivity. |
Organization (project owner ) |
Likely |
Organization |
Open |
There is requirement of cost plan to estimate the budget for the project plan. |
R3 |
Staff recruitment difficulties: A business moving into urban location takes the advantage of cheaper commercial spaces. It might difficult for recruiting various kinds of quality workers. |
Organization |
Possible |
Organization |
Open |
Hiring on internal basis: various kinds of organization look for resources and time for having an internal look on organization. |
Communication plan
What information |
Target audience |
When |
Mode/Method of communication |
Provider |
Milestone report |
Senior management of Wagga Wagga franchise of Swaggies |
Bimonthly |
Through E-mail and hardcopy |
Project office of Wagga Wagga franchise of Swaggies |
Status of project |
Staff and customer of Wagga Wagga franchise of Swaggies stores |
Weekly |
Through E-mail and hardcopy |
Project of manager of Wagga Wagga franchise of Swaggies stores |
Team status report |
Project manager of Wagga Wagga |
Weekly |
|
Team recorder of Swaggies |
Issue reports |
Staff of Wagga Wagga franchise of Swaggies |
Weekly |
|
Team recorder of Swaggies |
Escalation reports |
Staff of Wagga Wagga franchise of Swaggies |
When required or needed |
At the time of meeting along with hardcopy |
Project manager of Wagga Wagga franchise of Swaggies |
Outsourcing of performance |
Staff and customer of Wagga Wagga |
Bimonthly |
During meeting |
Project manager of Wagga Wagga franchise of Swaggies |
Acceptance of request |
Project office and project manager |
Anytime or as required |
Through email and hardcopy |
Design department |
Gate decision |
Senior management |
As needed or required |
Providing report through email |
Project office of Wagga Wagga franchise of Swaggies. |
The Quality management plan generally helps in accepting the level of quality which is generally defines the customer. It mainly ensures the fact of level of quality which is present in the deliverables. The main objectives of quality management plan are
Quality management plans are generally applied to the deliverables of the project and various kinds of work processes which are associated with it. Activities related to project management generally monitors and check the deliverables of the project which ultimately checks the standard of quality. Quality assurance activities generally monitor and check the processes which are used for managing and creation of deliverables.
Components of Quality management plan are as follows:
A change management plan generally helps in management of change processes. It also ensures or checks the parameters like budget, scope, communication, schedule and lastly resources. There are mainly five stages of change management process that are requesting for change, analysis of impact or effect, Approving or denying, implementation of changes and lastly reviewing or reporting.
Request for the changes: Most of the changes generally occur for improvement of processes, outcomes and lastly identification of certain number of goals. After proper identification of parameters, a request for change is provided to the project manager.
Analysis of impact: The roadmap for identification generally begins at route which is taken to the destination. It also addresses scope, objective and cost which is involved in the plan.
Approving and Denying: Resistance is well known term in change management which can affect the success of a project.
Implementation of changes: Communication is considered to be key tool for implementation of changes in change management. Identification, planning and execution is considered to be good change for management plan. The whole thing depends on good type of communication which is provided.
Reviewing: Change is considered to be painful in various ongoing processes. Change management strategies are generally adjusted as per the need of the project.
The project manager estimated the timeline and budget as 6 weeks and $30,000, but as per the tender and suppliers, the total estimated timeline is 50 days with a budget of $ 42,880.
WBS |
Task Name |
Duration |
Start |
Finish |
Resource Names |
Cost |
0 |
Relocation of administrative department of the Wagga Wagga premises |
50 days |
Tue 2/6/18 |
Mon 4/16/18 |
$42,880.00 |
|
1 |
Initiation phase |
24 days |
Tue 2/6/18 |
Fri 3/9/18 |
$21,240.00 |
|
1.1 |
Design of the administrative department |
2 days |
Tue 2/6/18 |
Wed 2/7/18 |
Administrative Officer, Project Manager |
$1,840.00 |
1.2 |
Assign of the administrative space |
2 days |
Thu 2/8/18 |
Fri 2/9/18 |
Administrative Officer, Project Manager |
$1,840.00 |
1.3 |
Order of the chairs |
1 day |
Mon 2/12/18 |
Fri 2/16/18 |
Business Consultant, Contractor, Project Manager, Supplier |
$620.00 |
1.4 |
Order of the desks |
1.5 days |
Fri 2/16/18 |
Mon 2/19/18 |
Business Consultant, Project Manager |
$940.00 |
1.5 |
Ordering of new office equipment |
4 days |
Thu 2/8/18 |
Tue 2/13/18 |
Project Manager, Resource Manager, Business Consultant, Supplier |
$3,600.00 |
1.6 |
Hiring of movers |
2 days |
Tue 2/20/18 |
Wed 2/21/18 |
Project Manager, Resource Manager |
$1,840.00 |
1.7 |
Identification of potential office sites |
2 days |
Fri 2/16/18 |
Tue 2/20/18 |
Administrative Officer, Project Manager |
$1,840.00 |
1.8 |
Evaluation of server room requirements |
2 days |
Tue 2/20/18 |
Thu 2/22/18 |
Developer, System Vendor |
$880.00 |
1.9 |
Evaluation of computer networking requirements |
4 days |
Thu 2/22/18 |
Wed 2/28/18 |
Business Consultant, Developer |
$1,600.00 |
1.10 |
Order the signage for the new location |
3 days |
Wed 2/28/18 |
Mon 3/5/18 |
Project Manager, Resource Manager |
$2,760.00 |
1.11 |
Arrange internal maintenance services |
4 days |
Mon 3/5/18 |
Fri 3/9/18 |
Internal Customers, Project Manager |
$3,200.00 |
1.12 |
Authorization of the project manager |
0.5 days |
Fri 3/9/18 |
Fri 3/9/18 |
Project Manager |
$280.00 |
1.13 |
Milestone 1: Completion of initiation phase |
0 days |
Fri 3/9/18 |
Fri 3/9/18 |
$0.00 |
|
2 |
Relocation planning |
15 days |
Mon 3/12/18 |
Fri 3/30/18 |
$13,140.00 |
|
2.1 |
Appraise the assets transferred to new location |
2 days |
Mon 3/12/18 |
Tue 3/13/18 |
Internal Customers, Project Manager |
$1,600.00 |
2.2 |
Business quotes for the new space |
1 day |
Wed 3/14/18 |
Wed 3/14/18 |
Project Manager, Resource Manager, Supplier, System Vendor |
$1,400.00 |
2.3 |
Order the security system |
0.5 days |
Thu 3/15/18 |
Thu 3/15/18 |
Business Consultant, Project Manager |
$380.00 |
2.4 |
Identification of move project team |
3 days |
Thu 3/15/18 |
Tue 3/20/18 |
Internal Customers, Project Manager, Resource Manager |
$3,480.00 |
2.5 |
Making final decision on the office spaces |
4 days |
Tue 3/20/18 |
Mon 3/26/18 |
Internal Customers, Project Manager |
$2,520.00 |
2.6 |
Review of the space plans |
0.5 days |
Mon 3/26/18 |
Mon 3/26/18 |
Administrative Officer, Business Consultant, Project Manager |
$560.00 |
2.7 |
Plan procurements and risk management |
3 days |
Tue 3/27/18 |
Thu 3/29/18 |
Business Consultant, Project Manager |
$2,280.00 |
2.8 |
Defining the organizational requirements |
1 day |
Fri 3/30/18 |
Fri 3/30/18 |
Project Manager, Resource Manager |
$920.00 |
2.9 |
Milestone 2: Completion of planning phase |
0 days |
Fri 3/30/18 |
Fri 3/30/18 |
$0.00 |
|
3 |
Execution phase |
8 days |
Mon 4/2/18 |
Wed 4/11/18 |
$6,260.00 |
|
3.1 |
Direct and manage of the project work |
0.5 days |
Mon 4/2/18 |
Mon 4/2/18 |
Project Manager, Resource Manager |
$460.00 |
3.2 |
Monitor and control the project progress |
0.5 days |
Mon 4/2/18 |
Mon 4/2/18 |
Project Manager |
$280.00 |
3.3 |
Manage the risks |
4 days |
Tue 4/3/18 |
Fri 4/6/18 |
Risk Manager, Business Consultant, Project Manager |
$3,840.00 |
3.4 |
Manage the stakeholders |
3 days |
Mon 4/9/18 |
Wed 4/11/18 |
Project Manager |
$1,680.00 |
3.5 |
Milestone 3: Completion of execution phase |
0 days |
Wed 4/11/18 |
Wed 4/11/18 |
$0.00 |
|
4 |
Closure phase |
3 days |
Thu 4/12/18 |
Mon 4/16/18 |
$2,240.00 |
|
4.1 |
Close the procurements |
1 day |
Thu 4/12/18 |
Thu 4/12/18 |
Project Manager, Resource Manager |
$920.00 |
4.2 |
Delivering the project scope to the customer |
1 day |
Fri 4/13/18 |
Fri 4/13/18 |
Business Consultant, Project Manager |
$760.00 |
4.3 |
Release the project staffs |
1 day |
Mon 4/16/18 |
Mon 4/16/18 |
Project Manager |
$560.00 |
4.4 |
Milestone 4: Completion of closure phase |
0 days |
Mon 4/16/18 |
Mon 4/16/18 |
$0.00 |
Moving into the new administrative department is a big challenge when planning as well as management is not being carried out. Following are the recommendations for the project plan which are suggested to the project manager as:
Requirement of architect: In order to relocate the administrative department, the business should require an architect who would design, train the entire plan and design of the office space. The architect should lead the process to create the functional spaces from design to realization of the designs. They can determine the layout and location of the files and office related equipments.
Supply employees with information: All the employees those are supplied with information regarding the new areas. As it is relocation of the administrative department, therefore the employees should provide details such as amenities, parking and internet access specific to the new location of the department.
Conclusion
It is concluded that the relocation of the administrative department builds a strong relationship among the clients and employees. The clients are satisfied with the new location. The new plan helps the store in attaching of more customers towards their purchase of gifts. A communication plan is implemented for the purpose of interaction among the stakeholders. Choosing of the right products help to understand the requirements of the customers.
1 |
A |
Identify one source of non-electronic information and provide an example of when you might use this research method to collect information |
Source: |
Letter |
|
Example: |
Project manager can make use of letter for sending information from one person to another. |
|
B |
List three methods of online research you might use for data collection |
|
1 |
Telephonic interviews: The biggest advantage of telephonic interview is that it saves both cost and time. At present accessing people can be done through telephone which is considered as the easiest method. Another advantage which can be done is fewer number of interviews in comparison to face to face interviews. |
|
2 |
Online survey: The present idea focuses on the development in field of technology and use of online survey has improvised to large extent. It is considered as the least expensive method for reaching to the views of large number of people. After the conduction of online survey, it data can be used as needed from time to time basis. The response time is so quick in online survey that it is preferred over the type of data collection method. |
|
3 |
Face to face interviews: This technique or method is considered to be most effective way for gathering of data and gaining of trust. It is very useful for detection of discomfort while discussing certain number of sensitive issues. There are certain advantages for interviewing a person like observation of non-verbal languages. |
|
C |
Briefly explain the term triangulation and its purpose in research. |
|
Triangulation can be defined as the using of more than one method for collection of data on same topic. This is considered as the most useful way for assuring the validity of a research. It generally puts emphasizes on the collection of data on same topic. It involves various kinds of samples or methods for collection of data. However, it is taken account that triangulation is not essential for cross-validation of data rather than it emphasizes on various dimension which can be used for same type of phenomenon. |
||
2 |
A |
List the three main Boolean operators. |
1 |
AND |
|
2 |
OR |
|
3 |
NOT |
|
B |
Provide one strategy you could use when you are gathering data for analysis online using a search engine, and targeting a word, phrase or string of words. |
|
Strategy used for gathering of data are: · Collection of all the information which is available. · Taking into account the information which is needed. · Proper identification of gaps in provided information. |
||
3 |
A |
You have completed lengthy online research and obtained some critical data from the internet. You have stored the data in a folder on your PC. Describe one method you could use to protect your valuable research information from being modified and from being accidentally deleted and lost forever(please suggest a separate strategy for each problem) |
Modified |
Modification of important data can be prevented by deny access to it that is it should be only present in read mode. |
|
Deleted and lost forever |
There are several methods or ways by which data can saved from deletion and losing ü Back up of important data. ü Making use of password protection. ü Making use of EFS encryption. ü Making use of disk encryption method ü Hiding of data by making use of steganography ü Protection of data in transit with various kinds of IP security ü Securing various kinds of wireless communication ü Use of right management for retention control. |
|
B |
When gathering and analysing information, it is essential that the documents/data is handled systematically and securely. Provide two examples of security strategies that could be applied to electronic and non-electronic data storage. |
|
Electronic Data Strategy |
There are four ways for prevention of data that are: ü Back up on a regular basis ü Email security ü Encryption of business data ü Mobile data and security related to it. |
|
There are several ways for prevention of non-electronic data ü Creation of document management plan ü Shoring up of on-site security ü Shredding of documents securely and regularly. |
||
4 |
A |
Organisational systems for recordkeeping include different types of filing systems. For example, records can be stored by subject and/or by geographical region. Identify two other filing systems organisations use to store their records. |
1 |
Numeric filling system: Each of the files is assigned with the numbers and arranged the numbers into sequential order. The files on people with same name are not able to duplicate the headings with other system. The system offers with better files with higher level of confidentiality since there are no names displayed on the files as well as work at the time of handling of large volume of files. |
|
2 |
Alphanumeric Filing System: Use both of the letters as well as numbers into the filing system. The letters are signified the state which are followed by number in order to denote the account number. It is a easier way to pull out larger quantity of the files from same location. |
|
B |
In Australia, how long are businesses required to keep transactional business records? |
|
In Australia, the transactional business records are retained for 7 years. The period for retention is longer when it is supporting documents for the tax purposes. The monthly statements are disposed after about a year. |
||
5 |
A |
Define the term ‘Validity’ as it relates to research and data collection. |
Validity refers to the conclusion which is drawn from the analysed survey data are acceptable to degree which are determined as valid. It is used for determining whether the research measures are intended to measure the reliability of the analysed results. |
||
B |
Define the term ‘Reliability’ as it relates to research and data collection. |
|
It is the degree to which the assessment tools are produced stable along with consistent results. It is also stated as the degree of consistency of the measures. The test is reliable when it provides same repeated result under the same conditions. |
||
6 |
A |
What is a social network analysis? |
It is the approach which allowed the researchers for documenting, representing and analysing the impacts of the relationships patterns. The researcher can rely on either secondary or primary data in order to conduct the data analysis. |
||
B |
List an instance when you would use a statistical analysis? |
|
I had used of statistical analysis when I carried out any research study of planning, designing and analysing the research findings. The results are precise when there is carry out of accurate statistical tests. |
||
7 |
Identify one electronic and one non-electronic source of Primary information and provide an example when each of the sources would be effectively and efficiently used. |
|
Electronic Source |
Online questionnaire is an electronic source of primary information. |
|
Use |
Throughout online survey, the researcher can take the feedback from the target audiences. It is an effective method as the time span required to complete the online survey are average. The margin of occurrence of error is reduced with online survey as the participants can enter their responses direct into the system. |
|
Non- Electronic Source |
Speeches are a non-electronic source of primary information. |
|
Use |
Speeches are vocalized form of the communication used by the humans to transfer the data from one human to another. It is done from face to face by the humans. |
Albertoni, F., Elia, S., Massini, S. and Piscitello, L., 2017. The reshoring of business services: Reaction to failure or persistent strategy?. Journal of World Business, 52(3), pp.417-430.
Arvidsson, V., Holmström, J. and Lyytinen, K., 2014. Information systems use as strategy practice: A multi-dimensional view of strategic information system implementation and use. The Journal of Strategic Information Systems, 23(1), pp.45-61.
Dawson, C.J., Rick, A.H.I., McGinley, R.C. and Pickover, C.A., International Business Machines Corp, 2016. Deferred teleportation or relocation in virtual worlds. U.S. Patent 9,526,994.
Duboz, M.L., Rodet-Kroichvili, N. and Slim, A., 2016. Are Central and Eastern European Countries a New Area for the Relocation of Business Services? An Analysis for 2000-2013. Revue d’études comparatives Est-Ouest, (1), pp.233-274.
Laudon, K.C. and Laudon, J.P., 2016. Management information system. Pearson Education India.
Lee, T., Ghapanchi, A.H., Talaei-Khoei, A. and Ray, P., 2015. Strategic information system planning in healthcare organizations. Journal of Organizational and End User Computing (JOEUC), 27(2), pp.1-31.
Leigh, N.G. and Blakely, E.J., 2016. Planning local economic development: Theory and practice. Sage Publications.
Lorenc, M.J., Moore, R.J. and Osisek, D.L., International Business Machines Corp, 2015. Dynamic virtual machine domain configuration and virtual machine relocation management. U.S. Patent 8,949,831.
Manoharan, A., Melitski, J. and Bromberg, D., 2015. State strategic information system plans: An assessment integrating strategy and operations through performance measurement. International Journal of Public Sector Management, 28(3), pp.240-253.
Osman, E., El Beltagi, I.M. and Hardaker, G., 2015. The impact of leadership orientation on strategic information system planning processes, with an application to Libyan organizations. Information Technology for Development, 21(4), pp.601-627.
Pearlson, K.E., Saunders, C.S. and Galletta, D.F., 2016. Managing and Using Information Systems, Binder Ready Version: A Strategic Approach. John Wiley & Sons.
Peppard, J. and Ward, J., 2016. The strategic management of information systems: Building a digital strategy. John Wiley & Sons.
Peppard, J., Galliers, R.D. and Thorogood, A., 2014. Information systems strategy as practice: Micro strategy and strategizing for IS. J. Strategic Inf. Sys., 23(1), pp.1-10.
Quinn, M. and Kristandl, G., 2014. Business information systems for accounting students. Pearson Education Ltd..
Tarhini, A., Ammar, H. and Tarhini, T., 2015. Analysis of the critical success factors for enterprise resource planning implementation from stakeholders’ perspective: A systematic review. International Business Research, 8(4), p.25.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download