The main requirements of the project are generally elaborated below:
The objectives of the entire project are listed below:
The critical success factors of the project are elaborated below:
The changes that are generally required within the entire project are elaborated below:
It is found that there are two options that are generally considered for the analysis and the two options are generally listed below:
The evaluation criteria of the options are generally elaborated in the table below:
The delivery of the entire project should be under $5 million |
25% |
The delivery of the entire project should be done within the timeline that is expected |
30% |
The construction of the rail extension should not extend the environment |
25% |
It is necessary to extend the rail of Mernda properly in order to access other facilities of the city of Mernda. |
30% |
The project must be successfully delivered within the subject site |
Mandatory |
The reasons of the selected options are generally evaluated below:
It is found that option 1 is mainly recommended as the integration of the station with the city of Mernda will generally allow the people of that area or city to access the restaurants, entertainment, hospitals as well as shopping malls quite easily without wasting much time. Moreover, they can also get the facility of parking for the bikes that are more than 1,000 cars.
The scope of the project is listed below:
The constraints of the project are generally elaborated below:
The steps that are generally required for managing the scope of the project are generally elaborated below:
Understanding the problem: It is very much necessary to understand the problem of the project quite effectively so that the reasons of the problems can be identified quite effectively.
Understanding the needs of the project: It is very much necessary to understand the needs of the project quite effectively so that the requirements of the project can be properly gathered.
Identifying the signs of the project creep: The signs of the project creep must be understood in the initial stage so that the problems or challenges that are mainly associated with the scope can be effectively avoided.
Account for the various changes that is done financially: The changes of the project should not incur cost that is above the ore-determined amount so that the manager of the project must be prepared for asking for increase the budget of the project. Moreover, if the resources of the project are unavailable then it is identified that the project managers cannot make this type of determination without taking the permission to increase the budget.
The deliverables of the entire project are generally elaborated below:
The KPI’s of the project are generally elaborated below:
Time spent: It is found that the time that is generally spent by the team members on each of the project tasks should be effectively tracked.
Budget variance: It is quite responsible to track the actual budget that generally varies from the projected budget in order to determine the KPI for measuring the baseline amount of expenses.
Training: Proper method of training facility should be provided to the team members so that they can be able to work effectively within the entire project.
Project sign off: This is generally required in order to track that whether each of the activities of the project can be completed successfully.
It is necessary to follow proper project management strategies in order to finish the entire project within the expected budget and time. The project management strategies are elaborated below:
Adopting proper project management methodologies: It is quite essential to use proper project methodology so that the rail extension can be effectively completed.
Setting clear expectation: It is quite necessary to set proper as well as clear expectation of the project so that the entire project can be completed within the expected budget and time.
Selecting the right team as well as system: It is quite important to use right team members within the entire project so that the entire work of the project can be finished quite successfully.
Defining milestones: It is quite necessary to define the project milestones properly throughout the lifecycle of the project in order to perform evaluation after each phase of the project.
Managing risks of the project: It is quite necessary to manage the risks as well as problems of the project quite effectively in order to finish the extension of the Mernda project within the expected time and budget.
The structure of the project is elaborated below:
Figure 1: Project Structure
(Source: Created by Author)
It is found that various managers are generally hired for the governance of the project:
Project manager: It is found that the project manager is mainly responsible for managing the team of the project including functional project team as well as civil and transport team of the project. In addition to this, it is found that the project manager generally governs as well as associates the advisors for finishing the project quite effectively.
Program director-Civil and transport: It is found that the program director of civil and transport is mainly responsible of managing the success of the project in association with the transport as well as civil delivery manager of the project.
The reporting structure of the project is generally provided below:
Tester |
Risk manager |
Supplier |
Business Consultant |
Team member |
Sub-contractor |
Contractor |
Project planner |
Project Manager |
|
Project Manager |
M |
M |
M |
M |
M |
M |
– |
||
Project planner |
– |
R |
|||||||
Contractor |
M |
M |
– |
R |
R |
||||
Sub-contractor |
– |
R |
|||||||
Team member |
– |
R |
|||||||
Business Consultant |
– |
R |
|||||||
Supplier |
– |
R |
|||||||
Risk manager |
– |
R |
|||||||
Tester |
– |
R |
The procurement strategy that are generally utilized within the entire project are mainly elaborated below:
The communication plan for the project are provided below:
Team members |
The project manager discusses about the objectives as well as goals of the project |
Once |
Email/face to face |
Project managers |
Financial planner |
Discuses about the budget that is needed for the project |
Once |
Email/face to face |
Project manager |
Team leader |
Discusses about the risks and challenges of the project |
Whenever required |
Email/face to face |
Team member |
The stakeholder’s management strategy is provided in the below table:
Project Manager |
High |
High |
Manage closely |
Project planner |
High |
High |
Manage closely |
Contractor |
High |
High |
Manage closely |
Sub-contractor |
High |
High |
Manage closely |
Team member |
Medium |
High |
Manage closely |
Business Consultant |
Medium |
High |
Manage closely |
Supplier |
Medium |
Medium |
Manage closely |
Risk manager |
High |
High |
Manage closely |
Tester |
High |
High |
Manage closely |
The expected timing of the project is provided in the table below:
1.1 |
Feasibility study of project plan |
10 days |
Wed 19-04-17 |
Tue 02-05-17 |
1.2 |
Prepare business case |
12 days |
Wed 03-05-17 |
Thu 18-05-17 |
1.3 |
Review of business case |
13 days |
Fri 19-05-17 |
Tue 06-06-17 |
1.4 |
Appointment of project government team |
10 days |
Wed 07-06-17 |
Tue 20-06-17 |
1.5 |
Acquisition of land |
12 days |
Wed 21-06-17 |
Thu 06-07-17 |
1.6 |
Milestone 1: Completion of project development phase |
0 days |
Thu 06-07-17 |
Thu 06-07-17 |
2.1 |
Prepare a design report |
30 days |
Fri 07-07-17 |
Thu 17-08-17 |
2.2 |
Designing the extension rail |
25 days |
Fri 18-08-17 |
Thu 21-09-17 |
2.3 |
Detailed engineering done |
28 days |
Fri 22-09-17 |
Tue 31-10-17 |
2.4 |
Infrastructure provision |
27 days |
Wed 01-11-17 |
Thu 07-12-17 |
2.5 |
Milestone 2: Completion of project design phase |
0 days |
Thu 07-12-17 |
Thu 07-12-17 |
3.1 |
Hire of project contractors |
30 days |
Fri 08-12-17 |
Thu 18-01-18 |
3.2 |
Preparing layout for 8km-long dual rail line |
24 days |
Fri 19-01-18 |
Wed 21-02-18 |
3.3 |
Developing Mernda Rail extension project |
30 days |
Thu 22-02-18 |
Wed 04-04-18 |
3.4 |
Integration of Mernda Rail extension project with the town of Mernda |
25 days |
Thu 05-04-18 |
Wed 09-05-18 |
3.5 |
Milestone 3: Completion of project construction phase |
0 days |
Wed 09-05-18 |
Wed 09-05-18 |
4.1 |
Identify risk |
20 days |
Thu 10-05-18 |
Wed 06-06-18 |
4.2 |
Mitigate risk |
18 days |
Thu 07-06-18 |
Mon 02-07-18 |
4.3 |
Testing |
18 days |
Tue 03-07-18 |
Thu 26-07-18 |
4.4 |
Audit report |
20 days |
Fri 27-07-18 |
Thu 23-08-18 |
4.5 |
Milestone 4: Completion of project testing phase |
0 days |
Thu 23-08-18 |
Thu 23-08-18 |
5 |
1 day |
Wed 19-07-17 |
Wed 19-07-17 |
Summary Information – Project Estimates |
Current Funding Current Cost Estimates |
Capital $352,000 Capital $1,004, 728 |
Expense Expense |
Ongoing Costs (life of asset) Ongoing Costs (life of asset) |
Subtotal Subtotal |
Revenue Revenue |
Net Total $352,000 Net Total $1,004, 728 |
Cost Escalation & Risk Cost Escalation & Risk $1,384,000 |
TOTAL $352,000 TOTAL $1,736,000 |
Cash Flow Estimates |
Financial Year 2016/17 2017/18 |
Budget $352,000 $0 |
Current Cost Estimate $352,000 $1,004, 728 |
Cumulative Cost Estimates $166,000 $1,736,000 |
Improper scheduling |
Due to improper analyzes, the time of the project is not estimated properly. |
High |
High |
It is necessary to estimate the time of the project properly. |
Increment in the project cost |
Due to improper management, the cost that is associated with the project generally increases. |
High |
High |
Proper management of the project is necessary for avoiding financial issues. |
Problems in project approval |
Due to problem, the project does not get approval. |
High |
High |
It is necessary to get approval at the right time in order to finish the project on time. |
Inexperienced workers |
As the workers are not experienced, then it can cause number of challenges in finishing the project properly. |
High |
Medium |
It is quite necessary to provide proper facility of training to the workers. |
The quality management strategy of the entire project is provided below:
The completion strategies of the project are generally provided below:
The benefits realization plan of the entire project is generally elaborated below:
Reference
Ahern, T., Leavy, B., & Byrne, P. J. (2014). Complex project management as complex problem solving: A distributed knowledge management perspective. International Journal of Project Management, 32(8), 1371-1381.
Badewi, A. (2016). The impact of project management (PM) and benefits management (BM) practices on project success: Towards developing a project benefits governance framework. International Journal of Project Management, 34(4), 761-778.
Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.
Cagliano, A. C., Grimaldi, S., & Rafele, C. (2015). Choosing project risk management techniques. A theoretical framework. Journal of Risk Research, 18(2), 232-248.
Conforto, E. C., Amaral, D. C., da Silva, S. L., Di Felippo, A., & Kamikawachi, D. S. L. (2016). The agility construct on project management theory. International Journal of Project Management, 34(4), 660-674.
Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., & de Almeida, L. F. M. (2014). Can agile project management be adopted by industries other than software development?. Project Management Journal, 45(3), 21-34.
Costantino, F., Di Gravio, G., & Nonino, F. (2015). Project selection in project portfolio management: An artificial neural network model based on critical success factors. International Journal of Project Management, 33(8), 1744-1754.
Drouin, N., Sankaran, S., & Muller, R. (2016). The nature of organizational project management and its role as an organizational capability. Manageable Cooperation?.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.
Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), 291-298.
Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), 1377-1392.
Kaiser, M. G., El Arbi, F., & Ahlemann, F. (2015). Successful project portfolio management beyond project selection techniques: Understanding the role of structural alignment. International Journal of Project Management, 33(1), 126-139.
Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.
Kucharska, W., & Kowalczyk, R. (2016). Trust, collaborative culture and tacit knowledge sharing in project management–A relationship model.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A. M. E., & Villanueva, P. (2014). Project risk management methodology for small firms. International journal of project management, 32(2), 327-340.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.
Sánchez, M. A. (2015). Integrating sustainability issues into project management. Journal of Cleaner Production, 96, 319-330.
Serra, C. E. M., & Kunc, M. (2015). Benefits realisation management and its influence on project success and on the execution of business strategies. International Journal of Project Management, 33(1), 53-66.
Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), 278-290.
Todorovi?, M. L., Petrovi?, D. ?., Mihi?, M. M., Obradovi?, V. L., & Bushuyev, S. D. (2015). Project success analysis framework: A knowledge-based approach in project management. International Journal of Project Management, 33(4), 772-783.
Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), 1382-1394.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download