This project will help in implementing change management in order to complete project with deadline. There have been various cases in which projects are not completed within deadline. Therefore, several organizations have been losing their projects from clients due to late delivery. The brand value of organizations have been decreasing due to poor quality of project deliverable. This problem will be minimized by organizing this project. This project will help in focusing on different factors including external and internal factors that create problems in the project.
The scope of the project is to implement change management in the project management. A change management has been a process that helps in defining steps used for identifying and modifying changes in the project. The scope pf this project include deliverables, objectives, functions and several tasks to be done in the project. The project scope focuses on implementing change management process in the projects for completing them within deadline. The change include both external and internal factors in the project. It ensures that the project will be completed within deadline and budget allocated. All the efforts done will help in development of organization. The scope of this project will also encourage changes in policies for strategic management of the project.
The objectives of the project has been depended on the development of changes in the organizations for making efficient projects within deadline.
Following are the objectives of this project:
Risks |
Description |
Impact on project |
Probability |
Mitigation Actions |
Responsible person |
Cost related |
Low allocation of cost for the project |
Several resources for the project cannot be utilized. |
The probability of cost related risks is very high. |
More financial investors need to be included in the project |
Project Manager |
Scope |
Scope of the project has not been properly defined |
The procedure of project might change and create obstacles. |
The probability of scope has been medium. |
The scope of project needs to be improved and well-defined. |
Project Manager |
Stakeholder conflicts |
Change requests may be the source of stakeholder conflict. |
It create conflicts in project handling and might cause failure. |
The probability of stakeholder conflicts has been high. |
Proper communication among stakeholders for avoiding conflicts. |
Project Manager |
Lack of skills |
Lack in skilled and qualified employees in the project |
Lack in skilled team members causes missed deadline and poor quality of work in the project. |
The probability of lack of skill have been medium. |
Providing proper training and motivation to team members related to the project helps in gaining skills and knowledge. |
Project manager |
Design failure |
Poor design of the project might led to failure of project. |
Poor design led to improper direction for completing the project and takes long time for completing with no surety of success. |
The probability of design failures have been high. |
Proper designing during planning process of the project. |
Project manager |
The deliverables of the project will include all requirements of the organizations including analyzing businesses and need of modification. The planning phase will include scope of the project and planning done with the stakeholders of the organization. There will be a schedule prepared for proper breakdown of the tasks. After that risks assessment will be done by identifying risks involved in the project. The execution of proposal will be done with the help of the planning stage and design of the project.
There are various criteria for acceptance of the project mentioned below:
Efficient and prompt handling of changes: This refers to providing value and justifying change management process.
Change handling meet processes: There should be timely and successful change implementations without any unanticipated change related to incidents and customer satisfaction.
Various tools supporting and change management process: As the process is established, various tools might be supporting and not hinder the progress of process outcomes.
Management commitment to change management: Leadership has been playing a key role in setting attitude, culture and behavior of organizational behavior for achieving desired outcomes.
Exclusions are those things that are outside of the project boundaries. This project does not include the name of the organization as this project has been applicable to all type of organizations. The impact of changes in the organization after the project has not been included in the scope of the project. There has no development of decision model included in the project.
The constraints of the project include availability of funding for the project. The resource allocation system has been included in the project. A proper budget allocation for resources have been include. The time frame has been maintained in the project for completing to within deadline. The involvement of higher authority of management has been present in this project. The project has been following all ethical consideration in the process. The involvement of stakeholders have been included in the project. Change management activities required for the implementation of course scheduling policies and procedures.
There are various assumptions included in the project including the size of the organizations. It has been assumed that the size of the organization has been medium to large companies. Therefore, the change management in those companies can be done properly. The change in the organization operations have been assumed to be in a positive manner. It has been assumed that results of the changes are positive in the organization. The time frame for the project has been already assumed to be of 273 days. It has been assumed that the project will finished with this time period.
Task Name |
Duration |
Start |
Finish |
Change management in project |
273 days |
Mon 12/10/18 |
Wed 12/25/19 |
Phase 1: Initiation |
51 days |
Mon 12/10/18 |
Mon 2/18/19 |
Organizational Requirements |
30 days |
Mon 12/10/18 |
Fri 1/18/19 |
Analyzing Business |
10 days |
Mon 12/10/18 |
Fri 12/21/18 |
Analyze Modifications |
15 days |
Mon 12/24/18 |
Fri 1/11/19 |
Solution for the identified problems |
5 days |
Mon 1/14/19 |
Fri 1/18/19 |
Resources Identification |
5 days |
Wed 2/6/19 |
Tue 2/12/19 |
Stakeholders |
4 days |
Wed 2/13/19 |
Mon 2/18/19 |
Phase 2: Planning |
40 days |
Tue 2/19/19 |
Mon 4/15/19 |
Stakeholder Communication |
9 days |
Tue 2/19/19 |
Fri 3/1/19 |
Scope development |
5 days |
Mon 3/4/19 |
Fri 3/8/19 |
Scheduling project |
9 days |
Mon 3/11/19 |
Thu 3/21/19 |
Work breakdown |
5 days |
Mon 3/11/19 |
Fri 3/15/19 |
Assigning predecessors |
4 days |
Mon 3/18/19 |
Thu 3/21/19 |
Schedule prepared |
0 days |
Thu 3/21/19 |
Thu 3/21/19 |
Risk Management |
17 days |
Fri 3/22/19 |
Mon 4/15/19 |
Risks identification |
7 days |
Fri 3/22/19 |
Mon 4/1/19 |
Risks prioritization |
5 days |
Tue 4/2/19 |
Mon 4/8/19 |
Countermeasures |
5 days |
Tue 4/9/19 |
Mon 4/15/19 |
Phase 3: Execution |
122 days |
Tue 4/16/19 |
Wed 10/2/19 |
Design and approval |
77 days |
Tue 4/16/19 |
Wed 7/31/19 |
System implementation documentation |
25 days |
Tue 4/16/19 |
Mon 5/20/19 |
Approval on the project |
0 days |
Wed 7/31/19 |
Wed 7/31/19 |
Training |
24 days |
Thu 8/1/19 |
Tue 9/3/19 |
Training to employees |
5 days |
Thu 8/1/19 |
Wed 8/7/19 |
Training completed |
0 days |
Tue 9/3/19 |
Tue 9/3/19 |
Implementation |
21 days |
Wed 9/4/19 |
Wed 10/2/19 |
Introducing Modifications |
5 days |
Fri 9/13/19 |
Thu 9/19/19 |
Software implementation |
0 days |
Wed 10/2/19 |
Wed 10/2/19 |
Phase 3: Monitoring and controlling |
30 days |
Thu 10/3/19 |
Wed 11/13/19 |
User Test |
9 days |
Thu 10/3/19 |
Tue 10/15/19 |
Feedback collection |
5 days |
Wed 10/16/19 |
Tue 10/22/19 |
Phase 4: Termination |
30 days |
Thu 11/14/19 |
Wed 12/25/19 |
User Support |
9 days |
Thu 11/14/19 |
Tue 11/26/19 |
Project documentation |
8 days |
Wed 11/27/19 |
Fri 12/6/19 |
Resource Name |
Type |
Material Label |
Initials |
Group |
Max. Units |
Std. Rate |
Ovt. Rate |
Cost/Use |
Accrue At |
Base Calendar |
Project manager |
Work |
PM |
100% |
$30.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Software developer |
Work |
SD |
100% |
$20.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Business representative |
Work |
BR |
100% |
$20.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Project team |
Work |
PT |
100% |
$10.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Project sponsor |
Work |
PS |
100% |
$0.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Business technical team |
Work |
BT |
100% |
$15.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Business staff |
Work |
BS |
100% |
$10.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Business owner |
Work |
BO |
100% |
$0.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Business analyst |
Work |
BA |
100% |
$15.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
External users view |
Work |
EU |
100% |
$10.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
Resource Manager |
Work |
RM |
100% |
$15.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
IT staffs |
Work |
IS |
100% |
$15.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
||
System Analyst |
Work |
SI |
100% |
$15.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.
Heagney, J. (2016). Fundamentals of project management. Amacom.
Kerzner, H. (2018). Project management best practices: Achieving global excellence. John Wiley & Sons.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and technology. Routledge.
Turner, J. R. (2014). Handbook of project-based management(Vol. 92). New York, NY: McGraw-hill.
Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.
Walker, A. (2015). Project management in construction. John Wiley & Sons.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download