Dsicuss about the Multi-Mode Resource And Constrained Multi-Project.
The project is undertaken in order to repair the fuel tanks of the storage capacity in Western Australia. This is essential as 30% of the company’s unleaded petrol is bordering on collapse due to the age and condition of the tanks. The Condition of the tanks is over 50 years old with a complex and outdated design. Therefore renovation of the tanks is essential and the, budget has been proposed for implementation of the project (Maravas & Pantouvakis, 2012). The project budget is represented in the following table.
Task Name |
Cost |
Renovation of the oil tanker storage |
$867,800.00 |
Project Starts |
$0.00 |
Requirement Analysis |
$1,920.00 |
Meeting with Client for discussion on repairing start date |
$640.00 |
Knowing basic Requirements of the client in repairing the tanks |
$1,280.00 |
Planning |
$4,800.00 |
Understanding the Technical Requirements and the resource requirements |
$1,280.00 |
Budget calculation for the resources |
$2,240.00 |
Documenting the Requirements |
$640.00 |
Drafting the documents for Client’s Approval |
$640.00 |
Implementation/ Renovation of the Tanks |
$858,680.00 |
Repairing works on Tank 1 |
$267,640.00 |
Working on 4 Steel Patch |
$30,000.00 |
Working 4 Steel anchor on top of the tank |
$35,000.00 |
Cleaning the tank |
$600.00 |
Repainting the Tank |
$202,040.00 |
Repairing Tank 2 |
$274,240.00 |
working on 7 Steel Patch |
$35,800.00 |
Working on 4 Steel anchor |
$35,800.00 |
Cleaning the tank |
$600.00 |
Repainting the Tank |
$202,040.00 |
Repairing Tank 3 |
$316,800.00 |
Working on 6 steel patch |
$22,000.00 |
Working on 4 Steel anchor on top of the tank |
$37,000.00 |
Replacing the main water supply valve of the tank |
$52,000.00 |
Cleaning the tank |
$2,400.00 |
Repainting the Tank |
$203,400.00 |
Project Handover |
$2,400.00 |
Documents Handover |
$800.00 |
Documents Archive |
$0.00 |
Payment completion |
$960.00 |
Resource Release |
$640.00 |
Client Feedback |
$0.00 |
Client Sign off |
$0.00 |
Project Ends |
$0.00 |
Table 1: The Project Budget
(Source: Created by author using MS Project)
The budget is prepared with the help of activity based budgeting. This budgeting uses the volume of a particular activity in developing a project budget. Apart from this, the difficulty in accessing the tanks is considered while estimating this budget.
The assumptions made while preparing this budget are as follows-
It is estimated that it will take at least 4 months to complete the repairing works of three tanks. The project is taking more time than expected as the accessing the tanks simultaneously will be difficult. In addition to that, the tanks cannot be accessed during its filling time. The schedule and the major milestone of the project is represented in the table below (Be?ikci, Bilge & Ulusoy, 2015)-
Task Name |
Duration |
Start |
Finish |
Renovation of the oil tanker storage |
110.38 days |
Mon 02-04-18 |
Mon 03-09-18 |
Project Starts |
0 days |
Mon 02-04-18 |
Mon 02-04-18 |
Requirement Analysis |
3 days |
Mon 02-04-18 |
Wed 04-04-18 |
Meeting with Client for discussion on repairing start date |
1 day |
Mon 02-04-18 |
Mon 02-04-18 |
Knowing basic Requirements of the client in repairing the tanks |
2 days |
Tue 03-04-18 |
Wed 04-04-18 |
M1: Completion of Requirements Gathering |
0 days |
Wed 04-04-18 |
Wed 04-04-18 |
Planning |
6 days |
Thu 05-04-18 |
Thu 12-04-18 |
Understanding the Technical Requirements and the resource requirements |
2 days |
Thu 05-04-18 |
Fri 06-04-18 |
Budget calculation for the resources |
2 days |
Mon 09-04-18 |
Tue 10-04-18 |
Documenting the Requirements |
1 day |
Wed 11-04-18 |
Wed 11-04-18 |
Drafting the documents for Client’s Approval |
1 day |
Thu 12-04-18 |
Thu 12-04-18 |
M2: End of Project Planning |
0 days |
Thu 12-04-18 |
Thu 12-04-18 |
Implementation/ Renovation of the Tanks |
91 days |
Fri 13-04-18 |
Fri 17-08-18 |
Repairing works on Tank 1 |
28 days |
Fri 13-04-18 |
Tue 22-05-18 |
Working on 4 Steel Patch |
2 days |
Fri 13-04-18 |
Mon 16-04-18 |
Working 4 Steel anchor on top of the tank |
2 days |
Tue 17-04-18 |
Wed 18-04-18 |
Cleaning the tank |
1 day |
Thu 19-04-18 |
Fri 04-05-18 |
Repainting the Tank |
3 days |
Mon 07-05-18 |
Tue 22-05-18 |
M3: Tank 1 Repaired |
0 days |
Tue 22-05-18 |
Tue 22-05-18 |
Repairing Tank 2 |
28 days |
Wed 23-05-18 |
Fri 29-06-18 |
working on 7 Steel Patch |
2 days |
Wed 23-05-18 |
Thu 24-05-18 |
Working on 4 Steel anchor |
2 days |
Fri 25-05-18 |
Mon 28-05-18 |
Cleaning the tank |
1 day |
Tue 29-05-18 |
Wed 13-06-18 |
Repainting the Tank |
3 days |
Thu 14-06-18 |
Fri 29-06-18 |
M4: Tank 2 Repaired |
0 days |
Fri 29-06-18 |
Fri 29-06-18 |
Repairing Tank 3 |
35 days |
Mon 02-07-18 |
Fri 17-08-18 |
Working on 6 steel patch |
5 days |
Mon 02-07-18 |
Fri 06-07-18 |
Working on 4 Steel anchor on top of the tank |
5 days |
Mon 09-07-18 |
Fri 13-07-18 |
Replacing the main water supply valve of the tank |
5 days |
Mon 16-07-18 |
Fri 20-07-18 |
Cleaning the tank |
4 days |
Mon 23-07-18 |
Fri 03-08-18 |
Repainting the Tank |
5 days |
Mon 06-08-18 |
Fri 17-08-18 |
M5:Tank 3 Repaired |
0 days |
Fri 17-08-18 |
Fri 17-08-18 |
Project Handover |
10.38 days |
Mon 20-08-18 |
Mon 03-09-18 |
Documents Handover |
10 hrs |
Mon 20-08-18 |
Tue 21-08-18 |
Documents Archive |
5 hrs |
Tue 21-08-18 |
Tue 21-08-18 |
Payment completion |
12 hrs |
Tue 21-08-18 |
Thu 23-08-18 |
Resource Release |
1 day |
Thu 23-08-18 |
Fri 24-08-18 |
Client Feedback |
5 days |
Fri 24-08-18 |
Fri 31-08-18 |
Client Sign off |
1 day |
Fri 31-08-18 |
Mon 03-09-18 |
M6: Project Handover Successful |
0 days |
Mon 03-09-18 |
Mon 03-09-18 |
Project Ends |
0 days |
Mon 03-09-18 |
Mon 03-09-18 |
Table 2: The Project schedule
(Source: Generated by author using MS Project)
The Gant Chart and work breakdown structure of the project schedule is represented below –
Figure 1: Representing the Gantt Chart of the project
(Source: Generated by author using MS Project)
Figure 2: the work breakdown Structure of the Project
(Source: Created by author using MS schedule Pro)
The different tools and techniques used in developing the project structure include Gantt chart and work break down structure. The project will be following a waterfall approach since simultaneous working on all the three tanks will be practically impossible (Brioso, 2015). The merit of choosing waterfall approach is that there will be no scope creep and the project will be following a sequential approach (Balaji & Murugaiyan, 2012). This is one of the main merits of waterfall project management techniques over the other similar approaches (Burke, 2013). The organization is paying a heavy fine due to the oil leakage that is causing a considerable amount of environmental damage. Therefore, it is essential for the project team to complete the project within the set schedule (Kim, Kang & Hwang 2012). The schedule prepared for this project is expected to remain unchanged subjected to the fact that no new requirements are identified in the later stages of project implementation.
The resources involved in the project are listed below (Artigues, Leus & Nobibon, 2013)-
The resources required for implementing the different tasks associated with the project is represented in the table below (Tavana, Abtahi & Khalili-Damghani, 2014)-
Task Name |
Resource Names |
Renovation of the oil tanker storage |
|
Project Starts |
Project Manager |
Requirement Analysis |
|
Meeting with Client for discussion on repairing start date |
Project Manager |
Knowing basic Requirements of the client in repairing the tanks |
Project Manager |
Planning |
|
Understanding the Technical Requirements and the resource requirements |
Project Manager |
Budget calculation for the resources |
Business Analyst, Project Manager |
Documenting the Requirements |
Project Manager |
Drafting the documents for Client’s Approval |
Project Manager |
M2: End of Project Planning |
|
Implementation/ Renovation of the Tanks |
|
Repairing works on Tank 1 |
|
Working on 4 Steel Patch |
Steel Patch 2m2[1],Rented large crane, Rented small crane |
Working 4 Steel anchor on top of the tank |
Steel anchors T1[1] |
Cleaning the tank |
Cleaning Staff, Rented large crane, Rented small crane, Workers |
Repainting the Tank |
Rented large crane, Paint[1], Painter, Rented small crane, Workers |
Repairing Tank 2 |
|
working on 7 Steel Patch |
Steel Patch 3m2[1],Workers, Rented large crane, Rented small crane |
Working on 4 Steel anchor |
Steel anchors T2[1],Workers |
Cleaning the tank |
Cleaning Staff, Rented large crane, Rented small crane, Workers |
Repainting the Tank |
Paint[1],Painter, Rented large crane, Rented small crane, Workers |
Repairing Tank 3 |
|
Working on 6 steel patch |
Steel Patch1.5m2[1],Workers, Rented large crane, Rented small crane |
Working on 4 Steel anchor on top of the tank |
Steel anchors T3[1],Workers, Rented large crane, Rented small crane |
Replacing the main water supply valve of the tank |
Supply Valve[1],Workers |
Cleaning the tank |
Cleaning Staff, Rented large crane, Rented small crane, Workers |
Repainting the Tank |
Paint[1],Painter, Rented large crane, Rented small crane, Workers |
M5:Tank 3 Repaired |
|
Project Handover |
|
Documents Handover |
Project Manager |
Documents Archive |
Archieve |
Payment completion |
Project Manager |
Resource Release |
Project Manager |
Client Feedback |
|
Client Sign off |
|
Project Ends |
Table 3: The resources used for each task
The details of the resources along with their standard rate of payment is represented in the following table-
Resource Name |
Type |
Max. Units |
Std. Rate |
Project Manager |
Work |
100% |
$80.00/hr |
Steel Patch 2m2 |
Material |
$30,000.00 |
|
Steel Patch 3m2 |
Material |
$35,000.00 |
|
Steel Patch1.5m2 |
Material |
$20,000.00 |
|
Steel anchors T1 |
Material |
$35,000.00 |
|
Steel anchors T2 |
Material |
$35,000.00 |
|
Steel anchors T3 |
Material |
$35,000.00 |
|
Supply Valve |
Material |
$50,000.00 |
|
Workers |
Work |
50,000% |
$50.00/hr |
Paint |
Material |
$200,000.00 |
|
Cleaning Staff |
Work |
30,000% |
$25.00/hr |
Painter |
Work |
25,000% |
$35.00/hr |
Archieve |
Cost |
||
Business Analyst |
Work |
100% |
$60.00/hr |
Rented large crane |
Cost |
||
Rented small crane |
Cost |
Table 4: Representing the Resources details
The major resources stress points include availability of the materials and the presence of the workers during the project implementation stage. Since the tanks will remain accessible only for a limited time, availability of the workers in that time is a major stress point associated with the project. This project is particularly complex and it is the responsibility of the project manager to identify and manage the critical stress points of the resources, in this case it is the availability of the materials and the workers (Martinelli & Milosevic, 2016). Another major resourcing stress point is choice of workers. Since the geographical location and shape of the site makes it difficult to work on it (Kogan et al., 2017). Therefore, properly skilled workers are needed to be chosen for the project so that they can work on the tank in any condition.
A contingency approach technique is chosen for resource estimation in the project (Kerzner & Kerzner, 2017). The use of contingency approach is valid in this case as it deals with the funding of the resources based on the business objectives. In this approach, the less important resources can be sacrificed as well if it does not fit the budget (Wang et al., 2014).
One of the major tools of developing a proper budget is developing a proper project schedule and the project plan. If the project plan is accurate, the budget will be accurate as well. In this project, a resource manager is appointed who is responsible for identifying the resource requirements of the project (Navaz et al., 2013). However, the project budget and the resource estimation is done according to the project deliverable, it is expected that no changes in the resources will be required for successful project implementation.
References
Artigues, C., Leus, R., & Nobibon, F. T. 2013. Robust optimization for resource-constrained project scheduling with uncertain activity durations. Flexible Services and Manufacturing Journal, 25(1-2), 175-205.
Balaji, S., & Murugaiyan, M. S. 2012. Waterfall vs. V-Model vs. Agile: A comparative study on SDLC. International Journal of Information Technology and Business Management, 2(1), 26-30.
Be?ikci, U., Bilge, Ü., & Ulusoy, G. 2015. Multi-mode resource constrained multi-project scheduling and resource portfolio problem. European Journal of Operational Research, 240(1), 22-31.
Brioso, X. 2015. Integrating ISO 21500 guidance on project management, lean construction and PMBOK. Procedia Engineering, 123, 76-84.
Burke, R., 2013. Project management: planning and control techniques. New Jersey, USA.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Khodakarami, V., & Abdi, A. 2014. Project cost risk analysis: A Bayesian networks approach for modeling dependencies between cost items. International Journal of Project Management, 32(7), 1233-1245.
Kim, J., Kang, C., & Hwang, I. 2012. A practical approach to project scheduling: considering the potential quality loss cost in the time–cost tradeoff problem. International Journal of Project Management, 30(2), 264-272.
Kogan, L., Papanikolaou, D., Seru, A. and Stoffman, N., 2017. Technological innovation, resource allocation, and growth. The Quarterly Journal of Economics, 132(2), pp.665-712.
Maravas, A., & Pantouvakis, J. P. 2012. Project cash flow analysis in the presence of uncertainty in activity duration and cost. International journal of project management, 30(3), 374-384.
Martinelli, R. J., & Milosevic, D. Z. 2016. Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.
Navaz, A. S., Fiaz, A. S., Prabhadevi, C., Sangeetha, V., & Gopalakrishnan, S. 2013. Human Resource Management System. arXiv preprint arXiv:1309.5351.
Tavana, M., Abtahi, A. R., & Khalili-Damghani, K. 2014. A new multi-objective multi-mode model for solving preemptive time–cost–quality trade-off project scheduling problems. Expert Systems with Applications, 41(4), 1830-1846.
Wang, W. C., Weng, S. W., Wang, S. H., & Chen, C. Y. 2014. Integrating building information models with construction process simulations for project scheduling support. Automation in construction, 37, 68-80.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download