Figure 1: Expected timeline of the project planning
(Source: Created by Author)
The above Gantt chart demonstrates the list of the activities necessary for the project planning and assuring that the planning being managed will be efficient and capable of managing the entire project activities. Construction projects are always sensitive projects and due to lack in proper planning it might influence the entire project and hence, the project planning is very vital. The above Gantt chart lists the activities those are necessary for the project planning and assuring that the project being delivered will be effectively and efficiently delivered. This includes all the phases within the planning including the scope, objective, and many others. Much emphasis has been provided on the better communication activities and risk management in manner to make sure that the quality of the project delivery is capable of meeting the expectations of the consumers.
The revised activities and timeline has been demonstrated in the below Gantt chart and every activity ad predecessor has been kept same as it was however, timeline has been altered in manner to meet the new deadline. Since, the project being delivered needs to be compressed from four months to three months and hence, the long deadline activities have been compressed, and hence, the overall delivery has been restricted to three months. Restriction in time will need to be done precisely in manner to manage the activities and assure that the restriction does not impact the quality of the project. The quality assurance will be managed through enhancing the work percentage in manner to complete the project one month early than the planning. The project planning will include all the activities listed previously however, compression will be made to the number of days and work percentage of the stakeholders and assure that the activities being delivered is up to the mark or above the expectations.
Figure 2: After restricting the timeline for one month
(Source: Created by Author)
Task Name |
Duration |
Resource Names |
Cost |
Project Planning |
120 days |
$464,600.00 |
|
Identification of the best practices of the quality assurance |
15 days |
Consultants 1, Consultants 2, Project Transformation officer, Secretory 1, Writer |
$63,000.00 |
Detailed analysis of the practices |
10 days |
Consultants 1, Consultants 2, Project Transformation officer |
$28,400.00 |
Outlining the improvement initiatives |
10 days |
Consultants 1, Consultants 2, Project Transformation officer |
$28,400.00 |
New project Detailed Description |
9 days |
Consultants 1, Consultants 2, Project Transformation officer |
$25,560.00 |
Designing training plan |
7 days |
Consultants 1, Consultants 2 |
$14,560.00 |
Project changes proposal |
10 days |
Consultants 1, Consultants 2 |
$20,800.00 |
Staff safety training |
10 days |
Project Transformation officer, Secretory 1, Writer |
$21,200.00 |
Cost estimation |
10 days |
Project Transformation officer, Secretory 1, Writer |
$21,200.00 |
Roadmap of the implementation |
7 days |
Project Transformation officer, Secretory 1, Writer |
$14,840.00 |
Developing implementation plan |
7 days |
Consultants 1, Consultants 2 |
$14,560.00 |
Engineers meeting |
9 days |
Consultants 1, Consultants 2 |
$18,720.00 |
Interior designer meeting |
8 days |
Consultants 1, Consultants 2 |
$16,640.00 |
Development of risk management plan |
7 days |
Consultants 1, Consultants 2 |
$14,560.00 |
Manage planning scope |
12 days |
Consultants 1, Consultants 2, Project Transformation officer, Secretory 1, Writer |
$50,400.00 |
Communication with the workers |
7 days |
Consultants 1, Consultants 2, Project Transformation officer, Secretory 1, Secretory 2 |
$31,360.00 |
Training mechanism |
10 days |
Project Transformation officer |
$7,600.00 |
Communication with the MD |
15 days |
Consultants 1, Consultants 2 |
$31,200.00 |
Final report preparation |
10 days |
Consultants 1, Consultants 2 |
$20,800.00 |
Demonstration of the final report |
10 days |
Consultants 1, Consultants 2 |
$20,800.00 |
The above table provides detail of the resources and the cost necessary for each activity and hence, the total budget will be prepared for every activities listed during the planning. The cost has been kept feasible considering accomplishment of every activities necessary for the deployment of the construction project. The cost for every resource has been kept in hours and thus, the consumption will be calculated as per the percentage of work delivered and time spent for the delivery of the activities. The resources necessary for the deployment of the construction project have been listed accordingly however the critical path analysis will be helpful in delivering the objectives and scope of the construction project. The expected budget for the planning has been stated in the above table and hence, every activity is necessary for the deployment of the construction projects.
Task Name |
Duration |
Resource Names |
Cost |
Project Planning |
90 days |
$312,400.00 |
|
Identification of the best practices of the quality assurance |
7 days |
Consultants 1, Consultants 2, Project Transformation officer, Secretory 1, Writer |
$29,400.00 |
Detailed analysis of the practices |
8 days |
Consultants 1, Consultants 2, Project Transformation officer |
$22,720.00 |
Outlining the improvement initiatives |
5 days |
Consultants 1, Consultants 2, Project Transformation officer |
$14,200.00 |
New project Detailed Description |
7 days |
Consultants 1, Consultants 2, Project Transformation officer |
$19,880.00 |
Designing training plan |
6 days |
Consultants 1, Consultants 2 |
$12,480.00 |
Project changes proposal |
10 days |
Consultants 1, Consultants 2 |
$20,800.00 |
Staff safety training |
5 days |
Project Transformation officer, Secretory 1, Writer |
$10,600.00 |
Cost estimation |
10 days |
Project Transformation officer, Secretory 1, Writer |
$21,200.00 |
Roadmap of the implementation |
4 days |
Project Transformation officer, Secretory 1, Writer |
$8,480.00 |
Developing implementation plan |
7 days |
Consultants 1, Consultants 2 |
$14,560.00 |
Engineers meeting |
4 days |
Consultants 1, Consultants 2 |
$8,320.00 |
Interior designer meeting |
10 days |
Consultants 1, Consultants 2 |
$20,800.00 |
Development of risk management plan |
7 days |
Consultants 1, Consultants 2 |
$14,560.00 |
Manage planning scope |
6 days |
Consultants 1, Consultants 2, Project Transformation officer, Secretory 1, Writer |
$25,200.00 |
Communication with the workers |
7 days |
Consultants 1, Consultants 2, Project Transformation officer, Secretory 1, Secretory 2 |
$31,360.00 |
Training mechanism |
6 days |
Project Transformation officer |
$4,560.00 |
Communication with the MD |
5 days |
Consultants 1, Consultants 2 |
$10,400.00 |
Final report preparation |
5 days |
Consultants 1, Consultants 2 |
$10,400.00 |
Demonstration of the final report |
6 days |
Consultants 1, Consultants 2 |
$12,480.00 |
The above table describes the new budget for the entire project considering the activities those have been compressed and the cost of the project will be decreased. The revised budget will be less than the previous activities as the above table presents the new revised cost considering the previous changes. The above table describes the newly estimated budget that will ensure that the project planning will be accomplished in an efficient and effective manner.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Papke-Shields, K.E. and Boyer-Wright, K.M., 2017. Strategic planning characteristics applied to project management. International Journal of Project Management, 35(2), pp.169-179.
Sligo, J., Gauld, R., Roberts, V. and Villa, L., 2017. A literature review for large-scale health information system project planning, implementation and evaluation. International journal of medical informatics, 97, pp.86-97.
Zeyauddin, M., Reza, M. and Danish, S.M., 2017. Project Planning and Delay Analysis For 2×300 Mw EMCO Thermal Power Plant.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download