On evaluation of the case study and on analysis of the procurement and the financial risks associated with the project, it is observed that the project lacked proper governance. In complex project like that of new Royal Adelaide Hospital project, it is essential to understand the concepts and process of public private partnership arrangements (Müller, Pemsel & Shao, 2014). The new Royal Adelaide project was implemented by the subcontracted builder. The project was mainly at risk from the delays and improper governance. Project governance is an important consideration of PPP project. From the case study of new Royal Adelaide Hospital project, major procurement and financial risks can be identified (New Royal Adelaide Hospital report, 2015). The procurement and the financial risks associated with this project resulted in project delays.
Findings from the discussion board unveil the major issues that were faced by the project team for implementation of new Royal Adelaide Hospital project. Findings from the audit report state that although SA health has tried to implement a governance structure, the project governance framework that was considered for this project was quite weak (Krohwinkel, 2015). Review of the project governance framework proves that there were a number of issues associated with the project that needed attention. It has been identified that there was an issue with the process of risk management associated with the implementation of the project. From the findings of the discussion board, it has been observed that the risk information that is provided to the committee required improvement for approving the key changes associated with the risk management process. It has been observed that an absence of a proper contract management framework and appropriate contract management plan was one of the most significant reasons behind the delays in the project. Along with that, there were a number of issues associated with the procurement management. Apart from that, it was observed that a number of procurement bundles. The timing, the scope, and cost of the project was not agreed with the Project Co.
The use of innovative approaches was necessary for delivery of new Royal Adelaide Hospital project. Inappropriate project planning and lack of collaboration among the project and procurement team added to the complexities of the project (Larsen et al., 2015). Findings from the discussion board states that it was essential to identify the possible risk mitigation strategies that could have eliminated some major risks associated with the project. As a possible mitigation strategy, it was essential to follow a planned approach of project implementation. It was the responsibility of the project manager to plan and implement the project with appropriate project governance. The issue with the project and program manager has resulted in further delays in the project which could have been eliminated. However, certain strategic drivers of the project was addressed which includes, safe patient care and enhanced access. The key concepts of the hospital in a part were considered for developing the design themes of the project. The new RAH project was inherently at risk mainly because of its scale and complexities.
While discussing about the major risks associated with the project, it has been observed that the new RAH project was inherently at high risk as the underlying contractual arrangements and PPP framework has transferred certain major risks related to this project. The risks related to the design and construction of the hospital building was multiplies with the unforeseen delays and cost overruns (New Royal Adelaide Hospital report, 2015). Contractual obligations associated with the PPP contract however, required the state to complete a number of tasks and contractual undertakings within a specified timeframe, which could not be followed. The SA health and the program team of new RAH was assigned a responsibility of delivering the project within a specified time the deadline of which could not be met.
Appropriate review of the risk management process associated with this project could observe a number of areas that required improvement (Demirel et al., 2017). The project needed improvements in terms of cost pressures, project delays, failure of meeting the PPP contractual requirements and inadequate management claim that is made against the state (Marchewka, 2014). Furthermore, the uncoordinated relocations to the RAH site had adversely affected the safe transfer of patients and the related services. The improper training of the staffs further added to the delays in the project.
However, with the involvement of the state, the new RAH project could be deliver with the implementation of a PPP arrangement. Under the project agreement, the Project co has a responsibility of offering a number of facilities and management services during during the operating term of the project that is associated with maintaining the hospital that is developed. Therefore, an innovative approach of project implementation was necessary. It can be concluded that the issues associated with the project could have been eliminated by designing, and enforcing and appropriate project governance plan (Cruz & Marques, 2013). There was certain payment issues associated with the project as well. In return for receiving the services provided by Project Co, the State needed to pay for the services in the operating phase which was delayed. In appropriate project governance and planning can be termed as common theme of the project.
From the audit report of new Royal Adelaide Hospital project, the major issues associated with the implementation of the project could be identified. The major risks associated with the project are as follows –
The above discussed points represent some of the major risks associated with a project. Inadequate delivery of the intended benefits of the project multiplied the already existing project issues.
Apart from those major risks, the project faced contractual risks as well. The project was implemented with a PPP agreement. The risk in the PPP contractual agreement is one of the major issues that is needed to be considered for in depth review of the project. The review of the new Royal Adelaide Hospital AG report addresses a number of issues with the project that relates to assurance management, program governance and reporting systems. These findings were later reported to the SA Health in September 2015.
The project faced several strategic risks that were needed to be considered for in-depth review (Larson et al., 2014). One of the strategic risks that are related to the project includes the need for process improvements in management of the project. Another major issue associated with the project was absence of proper contract management framework and contract management plan for the project for procurement program (Heagney, 2016). It has been observed that there was a scope of enhanced contract management practises of the project, which could have eliminated or reduced the negative impact of the identified risks in the project (Harvey & Kitson, 2015). Thus, it can be said that there was a scope of enhancing the contract management practices which could have eliminated the risk.
Thus, it can be said that the new Royal Adelaide Hospital project has a number of issues that were needed to be addressed. The delays in the project were the primary concern associated with the project and therefore in depth review of this issue is needed to be undertaken. The new Royal Adelaide Hospital project was quite complex and increase in the complexity added to the delays in the project. Further in-depth analysis to the issue can help in addressing such type of projects in future.
Another significant risk associated with the project includes cost overrun to a considerable margin. The original cost of the project was although $2 billion, another $245 million more was need for the medical equipments that were needed for completion of the project. In order to address the unforeseen cost increase, the state government agreed to pay an extra $34.3 million in the project. This issues or risk that is associated with the project needs further analysis.
Apart from these issues, the new Royal Adelaide Hospital project faced certain other risks such as risk in project leadership and governance (Guo et al., 2014). It is the responsibility of a leader to ensure accurate project implementation. The key areas of accountability in this project include the responsibility of project and the procurement manager in facilitating a successful project outcome.
As a solution to the problem, it was essential for the project team to follow a planned approach of implementation of the project.
References
Cruz, C. O., & Marques, R. C. (2013). Flexible contracts to cope with uncertainty in public–private partnerships. International Journal of Project Management, 31(3), 473-483.
Demirel, H. Ç., Leendertse, W., Volker, L., & Hertogh, M. (2017). Flexibility in PPP contracts–Dealing with potential change in the pre-contract phase of a construction project. Construction Management and Economics, 35(4), 196-206.
Domingues, S., Zlatkovic, D., & Roumboutsos, A. (2014, September). Contractual flexibility in transport infrastructure PPP. In European transport conference (Vol. 29).
Guo, F., Chang-Richards, Y., Wilkinson, S., & Li, T. C. (2014). Effects of project governance structures on the management of risks in major infrastructure projects: A comparative analysis. International Journal of Project Management, 32(5), 815-826.
Harvey, G., & Kitson, A. (2015). Implementing evidence-based practice in healthcare: a facilitation guide. Routledge
Heagney, J. (2016). Fundamentals of project management. Amacom.
Krohwinkel, A. (2015). A configurational approach to project delays: Evidence from a sequential mixed methods study. Journal of Mixed Methods Research, 9(4), 335-361.
Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2015). Factors affecting schedule delay, cost overrun, and quality level in public construction projects. Journal of Management in Engineering, 32(1), 04015032.
Larson, E. W., Gray, C. F., Danlin, U., Honig, B., & Bacarini, D. (2014). Project management: The managerial process (Vol. 6). Grandview Heights, OH: McGraw-Hill Education.
Marchewka, J. T. (2014). Information technology project management. John Wiley & Sons.
Müller, R., Pemsel, S., & Shao, J. (2014). Organizational enablers for governance and governmentality of projects: A literature review. International Journal of Project Management, 32(8), 1309-1320.
New Royal Adelaide Hospital report: November 2015. [pdf] Available at: https://www.audit.sa.gov.au/LinkClick.aspx?fileticket=lKSniN7sYQk%3D&tabid=283&portalid=0&mid=959&forcedownload=true [Accessed 25 Nov. 2018].
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download