The information system is the collection of technical elements and human resources. The Rocky Sports Club wants to implement an information system. The organization believes that IS can store and process their operational data.
The organization is currently having issues with monitoring the activities of the members such as how much and which articles they have submitted. The organization is having problem with tracking which member will edit next newsletter.
Waterfall Methodology: The waterfall model is the conventional way of exciting a software project. The waterfall model is executed stage by stage. The method states that a stage can be imitated only if the previous stage is completed.
Agile Methodology: The agile methodology is considered as the iterative approach for software development. The methodology concentrates on developing the software in various iterations, based on requirements of the system. The agile methodology allows the project manager to include requirements in any stage of the project.
Comparison: The Rocky Sports Club needs a SDLC method that can support its simple and short project. The differences between the waterfall and agile methodology are as following.
WBS |
Task Name |
Duration |
Predecessors |
0 |
ICF System Deveopment |
53 days |
|
1 |
Project Initiation |
14 days |
|
1.1 |
Identify Project Activities |
4 days |
|
1.2 |
Employ Project Team Members |
6 days |
2 |
1.3 |
Meeting with Stakeholders |
2 days |
3 |
1.4 |
Approve Project Activities |
1 day |
2,3 |
1.5 |
Generate Approximate Budget |
3 days |
4,5 |
1.6 |
Project Initiation Phase Complete |
0 days |
6 |
2 |
Planning |
10 days |
|
2.1 |
Define Project Scope |
2 days |
6 |
2.2 |
Create Project Execution Plan |
2 days |
9 |
2.3 |
Create Project Schedule |
1 day |
9,10 |
2.4 |
Identify Resources |
4 days |
11 |
2.5 |
Divide Resources among Team Members |
1 day |
12 |
2.6 |
Planning Phase Complete |
0 days |
13 |
3 |
Analysis |
13 days |
|
3.1 |
Identify Business Requirements |
3 days |
14 |
3.2 |
Identify User Requirements |
3 days |
14,16 |
3.3 |
Analyse the Gathered Requirments |
1 day |
16,17 |
3.4 |
Generate System Requirements |
4 days |
18 |
3.5 |
Evaluate the System Requirements |
1 day |
19 |
3.6 |
Prioritize System Requirements |
1 day |
20 |
3.7 |
Analysis Phase Complete |
0 days |
21 |
4 |
Design |
8 days |
|
4.1 |
System Architecture Design |
2 days |
22 |
4.2 |
UML Design |
1 day |
24 |
4.3 |
Database Entity and Attribute Identification |
1 day |
22,24 |
4.4 |
ERD Design |
1 day |
26 |
4.5 |
ERD to Physical Schema Diagram |
1 day |
27 |
4.6 |
Network Design using Cisco Packet Tracer |
2 days |
22 |
4.7 |
Webiste UX Design |
2 days |
25 |
4.8 |
Webiste UI Design |
3 days |
25,30 |
4.9 |
Design Phase Complete |
0 days |
31 |
5 |
Implementation |
7 days |
|
5.1 |
Webiste Interface Development |
3 days |
32 |
5.2 |
Website Backend Coding |
7 days |
32,24 |
5.3 |
Database Development |
3 days |
32 |
5.4 |
ICF Intranet Implementation |
4 days |
32 |
5.5 |
Implementation Phase Complete |
0 days |
37 |
6 |
Deployment |
1 day |
|
6.1 |
Go Live |
1 day |
35,36,37,38 |
6.2 |
Deployment Phase Complete |
0 days |
40 |
Figure 1: Gantt Chart
(Source: Created by Author)
Cost benefit analysis for Global Business System |
||||||
Year 0 |
Year 1 |
Year 2 |
Year 3 |
Year 4 |
Year 5 |
|
Overall savings |
$0 |
$50,000 |
$30,000 |
$35,000 |
$40,000 |
$30,000 |
Developmnet cost |
($67,412) |
$0 |
$0 |
$0 |
$0 |
$0 |
Maintainance Cost |
($12,000) |
($6,000) |
($3,900) |
($5,000) |
($3,500) |
($3,500) |
Net benefit/costs |
$21,000 |
$21,000 |
$21,000 |
$21,000 |
$21,000 |
$21,000 |
Net cash flow |
($58,412) |
$ 44,000.00 |
$26,100 |
$30,000 |
$36,500 |
$26,500 |
Discount factors |
||||||
Discount rate |
10% |
|||||
Year Index |
0 |
1 |
2 |
3 |
4 |
5 |
Discount factor |
1 |
0.91 |
0.83 |
0.75 |
0.68 |
0.62 |
Discounted flows |
||||||
Cost |
($67,412) |
($5,455) |
($3,223) |
($3,757) |
($2,391) |
($2,173) |
Benefit |
$21,000 |
$22,000 |
$23,000 |
$20,000 |
$22,000 |
$27,000 |
Net |
($46,412) |
$16,545 |
$19,777 |
$16,243 |
$19,609 |
$24,827 |
Cummulative |
($46,412) |
($29,867) |
($10,090) |
$6,154 |
$25,763 |
$50,590 |
Net present value |
$50,590 |
|||||
ROI |
36% |
|||||
Payback Analysis |
||||||
Years |
Months |
|||||
1 |
18 |
|||||
Payback Period in Years |
2.51 |
Conclusion:
The report includes the description of the project for implementing information system in Rocky Sports Club. Selection of the waterfall method for the project implementation is perfect. The system can be extremely beneficial for the organization. The automation of the back processes can improve the operation of the organization.
Baptista, A., Santos, F., Páscoa, J. and Sändig, N., 2016. Project management methodologies as main tool for current challenges in global economy driving historical changes. Journal of Advanced Management Science, 4(2).
Binder, J., 2016. Global project management: communication, collaboration and management across borders. Routledge.
Hornstein, H.A., 2015. The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), pp.291-298.
Misopoulos, F., Michaelides, R., Salehuddin, M.A., Manthou, V. and Michaelides, Z., 2018. Addressing Organisational Pressures as Drivers towards Sustainability in Manufacturing Projects and Project Management Methodologies. Sustainability, 10(6), p.2098.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download