The activity list of Drive through Super market consists of four phases:
(a) Initiation Phase:
The initiation phase consists of the following activities:
(b) Planning phase:
The planning phase consists of the following activities:
(c) Execution phase:
The execution phase consists of a number of subtasks. The execution phase is initiated by land approvals followed by the following activities:
(d) Project closure phase:
It is the last phase of the project and consists of the following activities:
Activity |
Dependencies |
Sequence |
Initiation Phase |
1.1 |
|
Market Analysis |
Business Analysis |
1.1.2 |
Land Finding |
Business Analysis |
1.1.3 |
Negotiation on land acquisition |
Market Analysis, Land finding |
1.1.4 |
Analyzing market target |
Market Analysis |
1.1.5 |
Scope Identification |
Market Analysis |
1.1.6 |
Planning Phase |
1.2 |
|
Objectives |
Analyzing market target, Scope identification |
1.2.1 |
Scope |
Scope Identification, Objectives |
1.2.2 |
Resources |
Scope Identification |
1.2.3 |
Budget |
Scope Identification |
1.2.4 |
Timeline |
Scope, Resources ad Budget |
1.2.5 |
Contractors |
Budget |
1.2.6 |
Donors |
Budget |
1.2.7 |
Contingency plan |
Budget |
1.2.8 |
Project Draft |
Timeline |
1.2.9 |
Draft Approval |
Contractors |
1.2.10 |
Execution Phase |
1.3 |
|
Land Approvals |
Depends on the completion of initial planning and starting work. |
1.3.1 |
Site Planning |
1.3.2 |
|
Engineering designs |
Land Approvals |
1.3.2.1 |
Engineering Resources |
Land Approvals |
1.3.2.2 |
Construction Materials |
Engineering Designs |
1.3.2.3 |
Resource Transportations |
Engineering Designs |
1.3.2.4 |
Safety Measures |
Resource Transportation |
1.3.2.5 |
Stakeholder assigning |
Safety measures |
1.3.3 |
Informing stakeholders to execute projects |
Stakeholder assigning |
1.3.4 |
Land is ready for construction |
Depends on informing the stakeholders to execute project. |
1.3.5 |
Warehouse Management |
1.3.6 |
|
Stock requirement analysis |
Can be started after the land is ready for construction |
1.3.6.1 |
Establishment of the pathways |
Stock requirement analysis |
1.3.6.2 |
Establishing conveyors |
Establishment of the pathways |
1.3.6.3 |
Engineering Modification |
Establishing conveyors |
1.3.6.4 |
Warehouse Facility completion |
Engineering Modification |
1.3.7 |
Drive through |
1.3.8 |
|
Designing pathways for vehicles |
Completion of the warehouse facility |
1.3.8.1 |
Establishing conveyors platform |
Depends on designing pathways for vehicles |
1.3.8.2 |
Managing warehouse and conveyors |
Establishing conveyors platform |
1.3.8.3 |
Completing Drive through |
Managing warehouse and conveyors |
1.3.9 |
Retail stores functioning |
1.3.10 |
|
Storing stocks |
Depends on completing the drive through |
1.3.10.1 |
Preparation of stocks transfer from warehouse to conveyors |
Storing stocks |
1.3.10.2 |
Developing Order system |
Preparation of stocks transfer from warehouse to conveyors |
1.3.10.3 |
Developing billing system |
Developing order system |
1.3.10.4 |
Retail store completion |
Developing billing system |
1.3.11 |
Electrical and construction activities |
1.3.12 |
|
Preparing power supply connections |
Retail store completion |
1.3.12.1 |
Establishing motors and electrical components |
Preparing power supply connections |
1.3.12.2 |
Assigning separate team for functioning of the components |
Establishing motors and electrical components |
1.3.12.3 |
Assigning technicians and human resources |
Assigning separate team for functioning of the components |
1.3.12.4 |
Delivering electrical and other works successfully |
Assigning technicians and human resources |
1.3.12.5 |
Project Closure Phase |
1.4 |
|
Project documentation |
Delivering electrical and other works successfully |
1.4.1 |
Learnings gained |
Project Documentation |
1.4.2 |
Stakeholder releasing |
Learnings gained |
1.4.3 |
Resource releasing |
Stakeholder releasing |
1.4.4 |
Opening ceremony |
Resource releasing |
1.4.5 |
Activity |
Resources Required |
Clarification |
Initiation Phase |
||
Business Analysis |
Business Analyst |
The business analyst takes care of the project businesses |
Market Analysis |
Market Analyst |
Special positions are assigned to people to analyze the market trends and targets |
Land Finding |
Civil engineer and Project Manager |
Civil engineers has the best knowledge about land that will be suitable for concerned project. The project manager also needs to be involved in this process. |
Negotiation on land acquisition |
Business Analyst, Civil engineer, Project heads and Project Manager |
To deal with government policies and regulations all the mentioned resources are required. The project head and the project managers are required to involve in all the decision-making processes. |
Analyzing market target |
Business Analyst, Civil engineer, Project heads and Project Manager |
Business analysts analyze the market targets. |
Scope Identification |
Civil engineer, Project heads and Project Manager |
The scope of the project is analyzed by authorities that control the projects and the civil engineer who is the main person for the construction project. |
Planning Phase |
||
Objectives |
Civil engineer, electrical engineer, Market Analyst, Project Head and Project Manager |
The objectives of the project are set by civil engineers, electrical engineers, market analysts and the project heads. |
Scope |
Civil engineer, electrical engineer, Market Analyst, Project Head and Project Manager |
Same goes for the scope of the project. Civil engineers are the main builders of the project. |
Resources |
Civil engineer, electrical engineer, Market Analyst, Project Head and Project Manager |
The resources that will be required to develop the project will be determined by all the mentioned resources. |
Budget |
Civil engineer, electrical engineer, Market Analyst, Project Head and Project Manager |
The project managers will fix the budget of the project. |
Timeline |
Civil engineer, electrical engineer, Market Analyst, Project Head and Project Manager |
The division of the project and preparation of the timeline will be performed by the project managers and various engineers. |
Contractors |
Civil engineer, electrical engineer, Market Analyst, Project Head and Project Manager |
The main stakeholders of the project determine contractors. |
Donors |
Project Head and Project Manager |
The donors that will make investments in the project are determined by the project stakeholders like project manager and project head. |
Contingency plan |
Project Head and Project Manager |
The risks of the project will be mitigated by the project head and the managers |
Project Draft |
Project Head and Project Manager |
The draft of the project is prepared by the main stakeholders of the project. |
Draft Approval |
Project Head and Project Manager |
The draft approval is the vital part of the project and needs to be done by the managers and the heads. |
Execution Phase |
||
Land Approvals |
Business Analyst, Market Analyst, Project Head, Project Manager and Transportation |
Land approval should also be performed after finding the appropriate land that is perfectly suitable for the project. Therefore, land approval is a vital part and needs to be approved by specialists. |
Site Planning |
||
Engineering designs |
Civil engineer, Electrical engineer, Miscellaneous materials and Project Manager |
The architectural design is mainly performed by the civil engineer and the power supply connections are done by the electrical engineers. |
Engineering Resources |
Civil engineer, Electrical engineer, Miscellaneous materials and Project Manager |
The engineering resources are also demanded by the civil and electrical engineers. Apart from these resources, miscellaneous resources are also that are determined by the project manager. |
Construction Materials |
Civil engineer, Electrical engineer, Miscellaneous materials and Project Manager |
The construction of Drive through super market requires constructing the pathway. The materials that will be required are identified by civil engineers. The electrical components and motors required are identified by electrical engineers. |
Resource Transportations |
Civil engineer, Electrical engineer, Miscellaneous materials and Project Manager |
The transportation of the materials will be identified by the civil and electrical engineers and the project managers. |
Safety Measures |
Civil engineer, Electrical engineer, Miscellaneous materials and Project Manager |
The safety of human labours are determined by civil and electrical engineers. |
Stakeholder assigning |
Civil engineer, Electrical engineer, Miscellaneous materials and Project Manager |
Determination of proper stakeholders are determined by the mentioned resources. |
Informing stakeholders to execute projects |
Project Heads and Project Managers |
After assigning stakeholders, the project head and the project managers are informed for the start of the project. |
Land is ready for construction |
||
Warehouse Management |
||
Stock requirement analysis |
Business Analyst, Market Analyst, Project heads and Project manager |
Warehouse management is done by the business analyst who analyses the stock requirement of the project. |
Establishment of the pathways |
Civil engineer, Construction Materials, Construction resources, Electrical Engineer, Miscellaneous Materials, Project Manager, Transportation |
The pathway for drive through super market will be constructed using the construction materials by the civil engineers and electrical engineers. |
Establishing conveyors |
Civil engineer, Construction Materials, Construction resources, Electrical Engineer, Miscellaneous Materials, Project Manager, Transportation |
The conveyor for drive through super market will be constructed using the construction materials by the civil engineers and electrical engineers. |
Engineering Modification |
Civil engineer, Construction Materials, Construction resources, Electrical Engineer, Miscellaneous Materials, Project Manager, Transportation |
The modification in architectural design can only be performed with the help of construction materials, miscellaneous materials by civil and electrical engineers. The project manager is involved in almost all the actions of the project. |
Warehouse Facility completion |
||
Drive through |
||
Designing pathways for vehicles |
Civil engineer, Construction resources, Project manager and Transportation |
The pathway for drive through super market will be constructed using the construction materials by the civil engineers and electrical engineers. |
Establishing conveyors platform |
Civil engineer, Construction resources, Project manager and Transportation |
The conveyor for drive through super market will be constructed using the construction materials by the civil engineers and electrical engineers. |
Managing warehouse and conveyors |
Civil engineer, Construction resources, Project manager and Transportation |
The warehouse manager manages the warehouse and the conveyor. |
Completing Drive through |
||
Retail stores functioning |
||
Storing stocks |
Business Analyst, Project heads and Project manager |
The stocks including the stocks of raw materials and products are stored by the managers. |
Preparation of stocks transfer from warehouse to conveyors |
Human Labours, Business Analyst, Market Analyst, Project Head, Project Manager and Transportation |
Stocks are transferred from warehouse to conveyors by human labourers guided by business and market analysts, project head and project manager. |
Developing Order system |
Market Analyst, Project head, Project manager and software engineer |
The order system will be developed by software engineers. |
Developing billing system |
Market Analyst, Project head, Project manager and software engineer |
The billing system will also be developed by software engineers. |
Retail store completion |
||
Electrical and construction activities |
||
Preparing power supply connections |
Construction materials, construction resources, electrical engineer and miscellaneous materials |
The power supply connections will be mainly designed by the electrical engineers. |
Establishing motors and electrical components |
Construction materials, construction resources, electrical engineer, miscellaneous materials, Project Manager and Transportation |
Electrical and construction activities are mainly done by the electrical engineers. Construction and miscellaneous materials are required for the construction purpose. The project manager guides the engineers in this process. |
Assigning separate team for functioning of the components |
Business Analyst, Civil engineer, Electrical engineer, Project head and Project Manager |
The tasks are divided among various stakeholders by forming a team. |
Assigning technicians and human resources |
Business Analyst, Civil engineer, Electrical engineer, Project head and Project Manager |
The mentioned activity is performed by the analysts, civil and electrical engineers, project head and the project manager. |
Delivering electrical and other works successfully |
||
Project Closure Phase |
||
Project documentation |
Business Analyst, Civil engineer, Electrical engineer, Market Analyst, Project Manager and Software engineer |
The project documentation is performed by the analysts, civil and electrical engineers, project head and the project manager. |
Learnings gained |
Business Analyst, Civil engineer, Electrical engineer, Market Analyst, Project Manager and Software engineer |
The learnings or the knowledge from the project is gained by the business analyst, engineers and the project manager. |
Stakeholder releasing |
Business Analyst, Market Analyst, Project Head and Project Manager |
This activity can be mainly performed by the project head and the managers. However, the business and the market analyst is also involved in this process. |
Resource releasing |
Business Analyst, Market Analyst, Project Head and Project Manager |
This activity can be mainly performed by the project head and the managers. However, the business and the market analyst is also involved in this process. |
Opening ceremony |
Outline Number |
Task Name |
Duration |
1 |
Drive Through Super Market |
261 days |
1.1 |
First phase: Initiation |
9 days |
1.1.1 |
Business Analysis |
3 days |
1.1.2 |
Market Analysis |
3 days |
1.1.3 |
Land finding |
2 days |
1.1.4 |
Negotiation on Land acquisition |
3 days |
1.1.5 |
Anlaysing market target |
3 days |
1.1.6 |
Scope Identification |
2 days |
1.2 |
Second Phase: Planning |
7 days |
1.2.1 |
Objectives |
2 days |
1.2.2 |
Scope |
2 days |
1.2.3 |
Resources |
1 day |
1.2.4 |
Budget |
2 days |
1.2.5 |
Timeline |
1 day |
1.2.6 |
Contractors |
2 days |
1.2.7 |
Donors |
1 day |
1.2.8 |
contingency plan |
1 day |
1.2.9 |
project draft |
1 day |
1.2.10 |
draft approval |
1 day |
1.2.11 |
M1: Completing initial planning and starting work |
0 days |
1.3 |
Third Phase: Execution |
218 days |
1.3.1 |
Land approvals |
3 days |
1.3.2 |
Site planning |
6 days |
1.3.2.1 |
Engineering designs |
2 days |
1.3.2.2 |
Engineering resources |
2 days |
1.3.2.3 |
Construction materials |
3 days |
1.3.2.4 |
Resource transportations |
2 days |
1.3.2.5 |
Safety measures |
2 days |
1.3.3 |
Stakeholder assigning |
2 days |
1.3.4 |
informing stakeholders to execute project |
1 day |
1.3.5 |
M2: Land ready for construction |
0 days |
1.3.6 |
Warehouse management |
63 days |
1.3.6.1 |
stock requirement analysis |
16 days |
1.3.6.2 |
establishment of the pathways |
14 days |
1.3.6.3 |
establishing conveyors |
16 days |
1.3.6.4 |
Engineering modification |
17 days |
1.3.7 |
M3: warehouse facility completion |
0 days |
1.3.8 |
Drive through |
66 days |
1.3.8.1 |
Designing pathways for vehicles |
30 days |
1.3.8.2 |
Establishing conveyors platform |
19 days |
1.3.8.3 |
Managing the warehouse and conveyors |
17 days |
1.3.9 |
M4: completing drive through |
0 days |
1.3.10 |
Retail stores functioning |
66 days |
1.3.10.1 |
Storing stocks |
15 days |
1.3.10.2 |
Preparation of stocks transfer from warehouse to conveyors |
20 days |
1.3.10.3 |
Developing Order System |
17 days |
1.3.10.4 |
Developing Billing System |
14 days |
1.3.11 |
M5: Retail store completion |
0 days |
1.3.12 |
Electrical and construction activities |
11 days |
1.3.12.1 |
preparing power supply connections |
2 days |
1.3.12.2 |
Establishing motors and electrical components |
2 days |
1.3.12.3 |
Assigning separate team for functioning of the components |
5 days |
1.3.12.4 |
Assigning technicians and human resources |
2 days |
1.3.12.5 |
M6: Delivering electrical and other works successfully |
0 days |
1.4 |
Fourth Phase: Project Closure |
32 days |
1.4.1 |
Project Documentation |
11 days |
1.4.2 |
Learnings gained |
7 days |
1.4.3 |
stakeholder releasing |
8 days |
1.4.4 |
resource releasing |
6 days |
1.4.5 |
M7: Opening ceremony |
0 days |
From the above table it can be said that the total time that will be required for the completion of the project is 261 days. As per the work breakdown structure the project will commence on 31st December, 2019 if the project will start on 1st January, 2019.
Resource Profile and over allocated resources:
Human Resources |
Name |
Phone Number |
Resource Over allocation |
Business Analyst |
David Gin |
(02) 7010 1111 |
Over allocated |
Market Analyst |
Laura Herman |
(03) 7010 5678 |
|
Civil Engineer |
William Phillips |
(07) 5551 5678 |
|
Electrical Engineer |
Noah Smith |
(02) 9876 5432 |
|
Software Engineer |
Oliver Bishop |
(07) 9577 3265 |
|
Project Head |
Olivia Roberts |
(02) 5553 5895 |
Over allocated |
Project Manager |
Ava Hansmeier |
(07) 7010 1121 |
Over allocated |
Contractor |
Amelia Bratt |
(03) 9875 3568 |
Over allocated |
Abdul Rahman, I., Memon, A. H., Karim, A., & Tarmizi, A. (2013). Significant factors causing cost overruns in large construction projects in Malaysia. Journal of Applied Science, 13(2), 286-293.
Ali, M., Sales, A. B. I. C. L., Barwick, J., Digirolamo, L., Australia, C. R., Officer, D. R., … & Khalid, A. (2017). School of Business.
Alinaitwe, H., Apolot, R., & Tindiwensi, D. (2013). Investigation into the causes of delays and cost overruns in Uganda’s public sector construction projects. Journal of Construction in Developing Countries, 18(2), 33.
Asiedu, R. O., & Alfen, H. W. (2013). Assessing the frequency of factors engendering cost overruns using frequency indices and factor analysis for public building projects in Ghana. Journal of International Real Estate and Construction Studies ISSN, 2153, 6813.
Azarm, R. (2013). Material Status Index for Tracking and Progress Reporting of Construction Projects (Doctoral dissertation, Concordia University).
Basari, I. (2017). Estimation Risk of High Risk Building Project on Contractor. IPTEK Journal of Engineering, 3(2).
Calvo, N., Varela-Candamio, L., & Novo-Corti, I. (2014). A dynamic model for construction and demolition (C&D) waste management in Spain: Driving policies based on economic incentives and tax penalties. Sustainability, 6(1), 416-435.
Duggan, T., & Patel, D. (2013). Design-build project delivery market share and market size report. RCD/RSMeans Market Intelligence, Norwell, MA.
Erbil, Y., Ak?nc?türk, N., & Acar, E. (2013). Inter-organizational context of the innovation process and the role of architectural designers as system integrators: case evidence from Turkey. Architectural Engineering and Design Management, 9(2), 77-94.
Fedorko, G., Molnar, V., Grincova, A., Dovica, M., Toth, T., Husakova, N., … & Kelemen, M. (2014). Failure analysis of irreversible changes in the construction of rubber–textile conveyor belt damaged by sharp-edge material impact. Engineering Failure Analysis, 39, 135-148.
Flanagan, R., Jewell, C., Lu, W., & Pekericli, K. (2014). Auto-ID—Bridging the physical and the digital on construction projects. Chartered Institute of Building (ISBN 1853800191).
Han, M. Y., Chen, G. Q., Shao, L., Li, J. S., Alsaedi, A., Ahmad, B., … & Ji, X. (2013). Embodied energy consumption of building construction engineering: case study in E-town, Beijing. Energy and Buildings, 64, 62-72.
Irizarry, J., Karan, E. P., & Jalaei, F. (2013). Integrating BIM and GIS to improve the visual monitoring of construction supply chain management. Automation in Construction, 31, 241-254.
Jazebi, F., & Rashidi, A. (2013). An automated procedure for selecting project managers in construction firms. Journal of Civil Engineering and Management, 19(1), 97-106.
Kelly, J., Male, S., & Graham, D. (2014). Value management of construction projects. John Wiley & Sons.
Kikwasi, G. (2013, February). Causes and effects of delays and disruptions in construction projects in Tanzania. In Australasian Journal of Construction Economics and Building-Conference Series (Vol. 1, No. 2, pp. 52-59).
Kuo, Y. C., & Lu, S. T. (2013). Using fuzzy multiple criteria decision making approach to enhance risk assessment for metropolitan construction projects. International Journal of Project Management, 31(4), 602-614.
Kwatsima, S. A. (2015). An Investigation into the Causes of Delay in Large Civil Engineering Projects in Kenya (Doctoral dissertation).
Lee, J. H., Song, J. H., Oh, K. S., & Gu, N. (2013). Information lifecycle management with RFID for material control on construction sites. Advanced engineering informatics, 27(1), 108-119.
Liou, C. S. (2014). Rent-seeking at home, capturing market share abroad: the domestic determinants of the transnationalization of china state construction engineering corporation. World Development, 54, 220-231.
Mok, K. Y., Shen, G. Q., & Yang, J. (2015). Stakeholder management studies in mega construction projects: A review and future directions. International Journal of Project Management, 33(2), 446-457.
Pimenova, A., Kuzmina, S., Morozova, N., & Mottaeva, A. (2016). The functional model approach to the consulting for vertically-integrated construction group. In MATEC Web of Conferences (Vol. 73, p. 07018). EDP Sciences.
Porwal, A., & Hewage, K. N. (2013). Building Information Modeling (BIM) partnering framework for public construction projects. Automation in Construction, 31, 204-214.
Ribeiro, P., Paiva, A., Varajão, J., & Dominguez, C. (2013). Success evaluation factors in construction project management—some evidence from medium and large Portuguese companies. KSCE Journal of Civil Engineering, 17(4), 603-609.
Sweis, G. J. (2013). Factors affecting time overruns in public construction projects: The case of Jordan. International journal of business and management, 8(23), 120.
Taylan, O., Bafail, A. O., Abdulaal, R. M., & Kabli, M. R. (2014). Construction projects selection and risk assessment by fuzzy AHP and fuzzy TOPSIS methodologies. Applied Soft Computing, 17, 105-116.
Tezel, A., Koskela, L., Tzortzopoulos, P., Formoso, C. T., & Alves, T. (2015). Visual management in Brazilian construction companies: taxonomy and guidelines for implementation. Journal of management in engineering, 31(6), 05015001.
Turner, R. (2016). Gower handbook of project management. Routledge.
Vasilyeva-Lyulina, A., Onishi, M., & Kobayashi, K. (2015). Delay analysis methods for construction projects: Mathematical modelling. Int. J. Transp, 3(1), 27-36.
Vrhovec, S. L., Hovelja, T., Vavpoti?, D., & Krisper, M. (2015). Diagnosing organizational risks in software projects: Stakeholder resistance. International journal of project management, 33(6), 1262-1273.
Walker, A. (2015). Project management in construction. John Wiley & Sons.
Yeheyis, M., Hewage, K., Alam, M. S., Eskicioglu, C., & Sadiq, R. (2013). An overview of construction and demolition waste management in Canada: a lifecycle analysis approach to sustainability. Clean Technologies and Environmental Policy, 15(1), 81-91.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download