Schedule management has been made for scheduling the project operations and functions in terms of the project management concepts and principles. The major inputs of the plan include the use of project management concepts and plans for the development of the operations and scheduling the operations of the project in time phase. The deployment of the schedule management had been helpful for the deployment of the smart processes and functions for the project. The brainstorming of the ideas had been helpful for deployment of faster and smoother operations of the schedule management. Schedule management had been formed for forming the effective and smart operations of the project.
The resources identification had been formed for developing the schedule management for the project operations and configuring of the timeline of activities. The review of the project had been helped by the process of gathering of the historical information in the project and considering how the resources would be utilized and exhausted for the completion of the operations. The quality of the project operations had been managed by the deployment of the activities and tasks. The production of the tasks would be helpful for the management of the resources in the operations. The duration of the operations and activities of the project are dependent on the schedule made for the implementation of the project.
The realistic time estimates had been helpful for the deployment of the project operations. The time estimates had been formed with the deployment of the activities in the project and operations included in the project. The estimation of the time had been formed for the management of the functions of the project and deployment of the expert’s judgement had been formed. The reviews of the experts had been caused for the deployment of the faster services and functions in the project operations.
The scheduling of the project in the times line is affected by the delays in timed operations. It is prominent that the deployment of the time had been delayed by the formation of the project schedule. The issues included in the project scheduling are non-compliance of the timely activities and remote access of the project operations. The deployment of a schedule is dealt with resource allocation and project management.
The project schedule had been created by the use of Gantt chart and the functions of the scheduled operations. The project schedule had been formed by following five simple steps for the operations of the project. The steps included in the project are defining activities, sequencing them in a proper way, estimating the resources of the activity, estimating the durations of the activities, and developing schedule of operations. These steps are followed by the use of the development of the project operations and aligning the time of the operations. The project operations are scheduled for aligning the activities of the project by the use of these steps.
Stakeholder’s communication has a very crucial impact on the operations of the project. The communication processes can be completed by the use of emails, social media options, reports, and face-to-face conversations. The face-to-face communication can be held at the time of meetings and formation of the effective communication. The benefits of the various methods of the communication are faced in terms of ease of channelling the deployment of the tools and methods. The emails are generally used for the channelizing the effective methods for the transfer of the project information. The agreement of the stakeholders have been largely dependent on the methods of conversation and talking among the members.
The project schedule could be managed by the deployment of the faster data processing and facilitation. The project schedule can be managed by the use of project charter and project analysis. The deployment of the project operations is largely dependent on the scheduling and management. The tools and processes had been largely developed for the implications of the business organizations. The finals conclusion of the project schedule had bene helpful for the formation of systematic and progressive conclusion of the project.
The change request can be implemented by the use of change management approach. The change management had been helpful for the deployment of the effective and congruent tools for the project operations. The meetings have been helpful for the development of the project operations and passing the scheduled operations.
The roles and responsibilities of the project operations had been helpful for the deployment of the successful completion of the projects. The individual members of the project had separate roles and responsibilities. The project managers had to make sure that the operations of the project must be carried on and there is no issues in the project. The deployment of the successful planning and processes is dependent on the project planner and coordinator. The team members are responsible for the vital and important options of the project. The budgeter had to manage the resources and keep the operations of the project intact.
The records had been helpful for the deployment of the risk assessment in the project. It is important for keeping the records of the project at high level. The assessment of the operations had been helpful for the alignment of the functions in the project. The records of the project had costed the deployment of the time management in the project. The time management activities had caused for the reviewing of the project operations. It is important for keeping the deployment of the management functions in the project.
The schedule management issues had been helpful for the deployment of the schedule management in the operations of the project. The use of the functions had caused the identification of the future improvements and functions. The issues of the project can be sorted by the use of the change management processes.
WBS |
Task Name |
Duration |
Start |
Finish |
Resource Names |
0 |
Installation of Wireless Data System |
132 days |
Wed 15-02-17 |
Thu 17-08-17 |
|
1 |
Initial Phase |
13 days |
Wed 15-02-17 |
Fri 03-03-17 |
|
1.1 |
Analysing the requirements of the project |
4 days |
Wed 15-02-17 |
Mon 20-02-17 |
System Analyst |
1.2 |
Formation of the Requirement framework |
4 days |
Tue 21-02-17 |
Fri 24-02-17 |
Graphic Designer |
1.3 |
Getting the Project Approved |
5 days |
Mon 27-02-17 |
Fri 03-03-17 |
Project Manager |
2 |
Planning Phase |
34 days |
Mon 06-03-17 |
Thu 20-04-17 |
|
2.1 |
Analysing the requirements and market |
7 days |
Mon 06-03-17 |
Tue 14-03-17 |
Program Team Member_1 |
2.2 |
Selecting the devices |
5 days |
Wed 15-03-17 |
Tue 21-03-17 |
Web system Expert |
2.3 |
Selecting the technique for system development |
4 days |
Wed 22-03-17 |
Mon 27-03-17 |
Application Programmer |
2.4 |
Available source analysis |
5 days |
Tue 28-03-17 |
Mon 03-04-17 |
Program Team Member_2 |
2.5 |
Task allocation process |
4 days |
Tue 04-04-17 |
Fri 07-04-17 |
Project Manager |
2.6 |
Allocating the resource documentation |
5 days |
Mon 10-04-17 |
Fri 14-04-17 |
Program Team Member_2 |
2.7 |
Development planning |
4 days |
Mon 17-04-17 |
Thu 20-04-17 |
Project Manager |
3 |
Executing the project deployment |
67 days |
Fri 21-04-17 |
Mon 24-07-17 |
|
3.1 |
Making prototype of the system |
15 days |
Fri 21-04-17 |
Thu 11-05-17 |
Application Programmer |
3.2 |
Creating the user interface |
15 days |
Fri 12-05-17 |
Thu 01-06-17 |
Graphic Designer |
3.3 |
Creating the database |
15 days |
Fri 02-06-17 |
Thu 22-06-17 |
Database Administrator |
3.4 |
Database testing |
12 days |
Fri 23-06-17 |
Mon 10-07-17 |
Quality Assurance Tester |
3.5 |
Application testing with the sales process |
10 days |
Tue 11-07-17 |
Mon 24-07-17 |
Project Manager |
4 |
Final documentation of the project |
16 days |
Tue 25-07-17 |
Tue 15-08-17 |
|
4.1 |
Making documents for the project progress |
7 days |
Tue 25-07-17 |
Wed 02-08-17 |
Program Team Member_1 |
4.2 |
Making report for CEO |
4 days |
Thu 03-08-17 |
Tue 08-08-17 |
Program Team Member_2 |
4.3 |
Training manual creation |
2 days |
Wed 09-08-17 |
Thu 10-08-17 |
Quality Assurance Tester |
4.4 |
Training the sales representatives |
3 days |
Fri 11-08-17 |
Tue 15-08-17 |
Team Member_2 |
5 |
Project Closure |
2 days |
Wed 16-08-17 |
Thu 17-08-17 |
Project Deliverables: The project deliverable include the formation of an ERP system for the operations of the project. The ERP system implementation include the formation of the data entry in the project. The project management tools have been helpful for the deployment of the effective planning in the project operations.
Project Schedule Progress: The project schedule progress has affected the deployment of the resources and their allocation. The deployment of the project schedule had been helpful for minimizing the risk factors and improving the interdependencies in the project. The costing of the project had been helpful for the deployment of the schedule of the project. The quality of the project had been helpful for the formation of the interdependencies of the project operations.
Deliverable monitoring: The monitoring of the deliverable had been helpful for the functioning of the project schedule. The use of the project schedule had been helpful for the deployment of the faster and effective monitoring of the project schedule.
Inform the stakeholders: The communication processes can be completed by the use of emails, social media options, reports, and face-to-face conversations. The face-to-face communication can be held at the time of meetings and formation of the effective communication. The emails are generally used for the channelizing the effective methods for the transfer of the project information. The agreement of the stakeholders has been largely dependent on the methods of conversation and talking among the members.
Maintain Project Objectives: Project management operations and tools can be used for the formation of the effective and smart operations for the project scheduling.
Discussion: The assignment had been made for making us understand the various concepts of the project tools and functions. The deployment of the effective and efficient tools had been helpful for the completion of the project. The use of the project management concepts had helped in forming the solutions to the effective and influential development of future projects and operations. The future project schedule should be helpful for the systematic and effective planning.
Bassi, A. (2015). General Management Principles in the Project Management Context. In Managing Intellectual Capital and Innovation for Sustainable and Inclusive Society: Managing Intellectual Capital and Innovation; Proceedings of the MakeLearn and TIIM Joint International Conference 2015. ToKnowPress.
Boud, D., Cohen, R., & Sampson, J. (Eds.). (2014). Peer learning in higher education: Learning from and with each other. Routledge.
Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.
Devaux, S. A. (2015). Total project control: a practitioner’s guide to managing projects as investments. Total project control: a practitioner’s guide to managing projects as investments.
Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), 291-298.
Kendrick, T. (2015). Identifying and managing project risk: essential tools for failure-proofing your project. AMACOM Div American Mgmt Assn.
Kerzner, H. R. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Marchewka, J. T. (2014). Information technology project management. John Wiley & Sons.
Pathan, A. S. K. (Ed.). (2016). Security of self-organizing networks: MANET, WSN, WMN, VANET. CRC press.
Phillips, J. (2013). PMP, Project Management Professional (Certification Study Guides). McGraw-Hill Osborne Media.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.
Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.
www.grandwineonline.com, (2017). Grand Wine & Spirits. Retrieved 14 January 2017, from https://www.grandwineonline.com/australia/
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download