The paper mainly focusses on setting up broadband services for a small city of Australia in order to provide proper facility of internet connection. It is identified that the plan was mainly set for providing appropriate internet connection facility to the people who mainly lives far way from the area of city. With the help of this plan, the people can be able to get the facility of internet connection. In addition to this, it is identified that the project will be mainly commenced on 29-05-18 and will be successfully completed within 70 days and thus the assumed end date of the project will be around 03-09-18. The main objectives of the project include:
The requirements for setting up the broadband services is mainly categorized into functional and non-functional requirements.
Non-Functional requirements
The non-functional requirements that are needed for setting up the broadband services are listed in the table below:
Reliability: The internet connection that is mainly provided by setting up the broadband services must be reliable so that the customers can trust the connection.
Availability: The service of internet connection must be 24×7 so that the users can be able to utilize the service of internet connection whenever they generally need it.
Performance: High speed of internet connection must be provided so that the users get satisfied with the service of internet connection facility.
Functional requirements
The functional requirements that are generally required for setting appropriate service of broadband are mainly listed below:
Authentication: Proper facility of authentication must be present so that before utilizing the facility, the users must login into their account.
External interface: Proper external interface like firewall must be present in order to avoid data access by unauthorized users.
Historical data: The facility of historical data access must be present so that historical data can be accessed whenever necessary.
Business rules: Proper business rules needs to be applied while setting up the broadband service so that the project will get aligned with the need of the organization.
The project team members who are involved within the project are listed in the table below:
Title |
Skills |
Project manager |
The project manager is mainly responsible of setting up the service of broadband by managing as well as handling the activities of the project within the expected end date. |
Network analyst |
They are generally responsible for installation, designing layout and for maintaining all the components of the network within the system. |
Network engineer |
The network engineers are mainly responsible for maintaining, implementing, supporting as well as developing the network for providing the service of internet connection. |
Workers |
The workers are generally engaged within the project so that the work that are required to be done for setting up the broadband facility can be appropriate set. |
Project planner |
The project planner is generally responsible for tracking as well as planning the schedule as well as budget of the entire project. |
Network administrator |
They are responsible for installing the network and for maintaining as well as repairing the entire network within the computer systems. |
The scope of the project is listed below:
It is identified that in order to set up proper broadband facility within the city of Australia, duration of 70 days is generally needed. The entire project duration is listed in the table that is provided below:
WBS |
Task Name |
Duration |
Start |
Finish |
0 |
Setting up broadband facility in a small city of Australia |
70 days |
Tue 29-05-18 |
Mon 03-09-18 |
1 |
Project initiation phase |
6 days |
Tue 29-05-18 |
Tue 05-06-18 |
1.1 |
Business case development |
2 days |
Tue 29-05-18 |
Wed 30-05-18 |
1.2 |
Feasibility study |
1 day |
Thu 31-05-18 |
Thu 31-05-18 |
1.3 |
Project charter establishment |
2 days |
Fri 01-06-18 |
Mon 04-06-18 |
1.4 |
Team members appointment |
1 day |
Tue 05-06-18 |
Tue 05-06-18 |
2 |
Planning phase |
14 days |
Wed 06-06-18 |
Mon 25-06-18 |
2.1 |
Meeting with client |
3 days |
Wed 06-06-18 |
Fri 08-06-18 |
2.2 |
Client overview |
2 days |
Mon 11-06-18 |
Tue 12-06-18 |
2.3 |
Project plan development |
2 days |
Wed 13-06-18 |
Thu 14-06-18 |
2.4 |
Development of resource and financial plan |
3 days |
Fri 15-06-18 |
Tue 19-06-18 |
2.5 |
Quality plan for the project |
1 day |
Wed 20-06-18 |
Wed 20-06-18 |
2.6 |
Risk management plan development |
2 days |
Thu 21-06-18 |
Fri 22-06-18 |
2.7 |
Communication plan development |
1 day |
Mon 25-06-18 |
Mon 25-06-18 |
3 |
Analysis of project |
8 days |
Thu 28-06-18 |
Mon 09-07-18 |
3.1 |
Analyzing project requirements |
3 days |
Thu 28-06-18 |
Mon 02-07-18 |
3.2 |
Analysis of project requirements |
2 days |
Tue 03-07-18 |
Wed 04-07-18 |
3.3 |
Analysis of project budget’ |
3 days |
Thu 05-07-18 |
Mon 09-07-18 |
4 |
Project development phase |
17 days |
Tue 10-07-18 |
Wed 01-08-18 |
4.1 |
Hardware and software selection |
5 days |
Tue 10-07-18 |
Mon 16-07-18 |
4.2 |
Design of network |
9 days |
Tue 17-07-18 |
Fri 27-07-18 |
4.3 |
Raw materials procurement |
3 days |
Mon 30-07-18 |
Wed 01-08-18 |
5 |
Implementation phase |
13 days |
Thu 02-08-18 |
Mon 20-08-18 |
5.1 |
Hardware installation |
5 days |
Thu 02-08-18 |
Wed 08-08-18 |
5.2 |
Developing connection with the help of cable |
6 days |
Thu 09-08-18 |
Thu 16-08-18 |
5.3 |
Installation of software |
2 days |
Fri 17-08-18 |
Mon 20-08-18 |
6 |
Testing phase |
7 days |
Tue 21-08-18 |
Wed 29-08-18 |
6.1 |
White box testing |
4 days |
Tue 21-08-18 |
Fri 24-08-18 |
6.2 |
Black box testing |
3 days |
Mon 27-08-18 |
Wed 29-08-18 |
7 |
Closure phase |
3 days |
Thu 30-08-18 |
Mon 03-09-18 |
7.1 |
Project delivery |
1 day |
Thu 30-08-18 |
Thu 30-08-18 |
7.2 |
Stakeholder sign off |
1 day |
Fri 31-08-18 |
Fri 31-08-18 |
7.3 |
Project documentation |
1 day |
Mon 03-09-18 |
Mon 03-09-18 |
The resources that are required for the project are listed below:
Hardware: The hardware that are needed for the project include:
Software: The software requirements for setting up broadband facility are as follows:
Human resource: The human resources who are mainly engaged with the project are listed below:
Resource Name |
Cost |
Project manager |
$60.00/hr |
Network analyst |
$50.00/hr |
Network engineers |
$55.00/hr |
Workers |
$45.00/hr |
Project planner |
$50.00/hr |
Network administrator |
$50.00/hr |
WBS |
Task Name |
Duration |
Resource Names |
Cost |
0 |
Setting up broadband facility in a small city of Australia |
70 days |
$193,920.00 |
|
1 |
Project initiation phase |
6 days |
$3,200.00 |
|
1.1 |
Business case development |
2 days |
Project manager |
$960.00 |
1.2 |
Feasibility study |
1 day |
Project planner |
$400.00 |
1.3 |
Project charter establishment |
2 days |
Project manager |
$960.00 |
1.4 |
Team members appointment |
1 day |
Project manager, Project planner |
$880.00 |
2 |
Planning phase |
14 days |
$7,360.00 |
|
2.1 |
Meeting with client |
3 days |
Project manager |
$1,440.00 |
2.2 |
Client overview |
2 days |
Project planner |
$800.00 |
2.3 |
Project plan development |
2 days |
Project manager |
$960.00 |
2.4 |
Development of resource and financial plan |
3 days |
Project planner |
$1,200.00 |
2.5 |
Quality plan for the project |
1 day |
Network analyst |
$400.00 |
2.6 |
Risk management plan development |
2 days |
Project manager, Workers |
$1,680.00 |
2.7 |
Communication plan development |
1 day |
Project manager, Project planner |
$880.00 |
3 |
Analysis of project |
8 days |
$9,440.00 |
|
3.1 |
Analyzing project requirements |
3 days |
Network engineers, Network analyst, Workers |
$3,600.00 |
3.2 |
Analysis of project requirements |
2 days |
Network administrator, Network analyst, Network engineers, Workers |
$3,200.00 |
3.3 |
Analysis of project budget’ |
3 days |
Project manager, Project planner |
$2,640.00 |
4 |
Project development phase |
17 days |
$72,960.00 |
|
4.1 |
Hardware and software selection |
5 days |
Network peripherals [1], Servers[1], Hardware[1] |
$63,000.00 |
4.2 |
Design of network |
9 days |
Network analyst, Network engineers |
$7,560.00 |
4.3 |
Raw materials procurement |
3 days |
Network administrator, Network analyst |
$2,400.00 |
5 |
Implementation phase |
13 days |
$93,000.00 |
|
5.1 |
Hardware installation |
5 days |
Network administrator, Network engineers, Workers |
$6,000.00 |
5.2 |
Developing connection with the help of cable |
6 days |
Network peripherals [1], Servers [1] |
$51,000.00 |
5.3 |
Installation of software |
2 days |
Servers [1], Software [1] |
$36,000.00 |
6 |
Testing phase |
7 days |
$5,480.00 |
|
6.1 |
White box testing |
4 days |
Network administrator, Network analyst |
$3,200.00 |
6.2 |
Black box testing |
3 days |
Network analyst, Workers |
$2,280.00 |
7 |
Closure phase |
3 days |
$2,480.00 |
|
7.1 |
Project delivery |
1 day |
Network administrator, Network analyst, Workers |
$1,160.00 |
7.2 |
Stakeholder sign off |
1 day |
Project manager |
$480.00 |
7.3 |
Project documentation |
1 day |
Project manager, Workers |
$840.00 |
The quality plan checklist is provided below:
Quality item |
Verification |
|
Yes |
No |
|
Does the project utilize proper plan of quality management? |
Yes |
— |
Does project quality metrics are generally approved? |
Yes |
—- |
Does the metrics of the project is controllable as well as reportable? |
Yes |
—- |
Does all the stakeholders of the project receive the access for the project quality plan |
—– |
No |
Does quality related documentation is created? |
Yes |
—– |
The stakeholder analysis is considered as of the conflict resolution procedure for accessing the impact of the decision of various relevant parties.
Stakeholders |
Power |
Interest |
Project manager |
High |
High |
Network analyst |
low |
High |
Network engineers |
High |
High |
Workers |
Low |
Low |
Project planner |
Low |
High |
Network administrator |
High |
High |
Audience |
Messages |
Vehicle |
Frequency |
Responsibility |
Project team members |
Providing information about the goals as well as objectives of the project |
Face to face |
Once |
Project manager |
Network engineer |
Provides information about the technical challenges that they face while setting up the service. |
|
Monthly |
Team members |
Project planner |
Discusses about the status of the project |
E-mail, face to face |
Weekly |
Project team leaders |
Risk |
Description |
Impact |
Probability |
Responsibility |
Mitigation |
Budget shortfall |
Due to inappropriate utilization of project budget, shortening of budget is generally faced. |
High |
High |
Financial manager |
Earned value analysis must be conducted for tracking the budget. |
Technical issue |
Due to inappropriate set up, number of technical challenges can occur. |
High |
High |
Network analyst |
In order to avoid this issue, it is quite important to create proper set up for the broadband service. |
Incorrect connection |
Due to incorrection connection number of technical issues occur |
High |
Medium |
Network analyst |
Proper connection must be created with the cable for mitigating the issue. |
Inappropriate management |
Due to inappropriate skills and experience of the network administrator, it become quite difficult to manage the project effectively. |
Medium |
Medium |
Hr manager |
It is quite necessary to recruit experienced network administrator. |
After conducting proper analysis, number of ethical issues as well as challenges are generally identified. The ethical issues include:
Data loss: It is identified that if the data that is stored get lost then it will generally create ethical issues.
Unauthorized access: If any users enters the network without proper authorization then it can be considered as ethical issues.
The activities that are generally used in order to deploy the set up for the broadband service is provided in the table below:
WBS |
Task Name |
4 |
Project development phase |
4.1 |
Hardware and software selection |
4.2 |
Design of network |
4.3 |
Raw materials procurement |
5 |
Implementation phase |
5.1 |
Hardware installation |
5.2 |
Developing connection with the help of cable |
5.3 |
Installation of software |
6 |
Testing phase |
6.1 |
White box testing |
6.2 |
Black box testing |
It is identified that it is assumed that the project will get finished within 14 weeks but as the project manager want earlier finish date and therefore the project is crashed for 2 weeks. It is found that after crashing the duration of the project gets minimized by 2 weeks and thus the duration that is needed for finishing the project will be around 12 weeks that is mainly reflected with the help of screenshot that is provided below:
Stakeholders |
Signature |
Project manager |
<Please Fill> |
Network analyst |
<Please Fill> |
Network engineers |
<Please Fill> |
Workers |
<Please Fill> |
Project planner |
<Please Fill> |
Network administrator |
<Please Fill> |
After reviewing the project properly, it is identified that the duration that is needed for setting up the broadband service will be around 12 weeks after crashing. It is found that the project will get successfully finished within the expected timeline. As it is analyzed that number of ethical issues are associated with the project and in order to resolve the issues, following recommendations are generally provided below:
Authentication: Proper authentication must be provided for avoiding data loss and unauthorized access.
Firewall: The firewall assists in avoiding unauthorized access of information and thus helps in resolving ethical issues
[1] Badewi, A. The impact of project management (PM) and benefits management (BM) practices on project success: Towards developing a project benefits governance framework. International Journal of Project Management, 34(4), pp.761-778, 2016
[2] Calvo-Mora, A., Navarro-García, A. and Periañez-Cristobal, R. Project to improve knowledge management and key business results through the EFQM excellence model. International Journal of Project Management, 33(8), pp.1638-1651, 2015.
[3] Chih, Y.Y. and Zwikael, O. Project benefit management: A conceptual framework of target benefit formulation. International Journal of Project Management, 33(2), pp.352-362, 2015.
[4] Costantino, F., Di Gravio, G. and Nonino, F. Project selection in project portfolio management: An artificial neural network model based on critical success factors. International Journal of Project Management, 33(8), pp.1744-1754, 2015.
[5] De Carvalho, M.M., Patah, L.A. and de Souza Bido, D. Project management and its effects on project success: Cross-country and cross-industry comparisons. International Journal of Project Management, 33(7), pp.1509-1522, 2015.
[6] Heldman, K. PMP: project management professional exam study guide. John Wiley & Sons, 2018.
[7] Hornstein, H.A. The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), pp.291-298, 2015.
[8] Joslin, R. and Müller, R. Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), pp.1377-1392, 2015
[9] Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P. Project risk management methodology for small firms. International journal of project management, 32(2), pp.327-340, 2014.
[10] Mir, F. A., & Pinnington, A. H. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217, 2014.
[11] Riol, H. and Thuillier, D. Project management for academic research projects: balancing structure and flexibility. International Journal of Project Organisation and Management, 7(3), pp.251-269, 2015.
[12] Samset, K. and Volden, G.H. Front-end definition of projects: Ten paradoxes and some reflections regarding project management and project governance. International Journal of Project Management, 34(2), pp.297-313, 2016.
[13] Svejvig, P. and Andersen, P. Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), pp.278-290, 2015.
[14] Too, E. G., & Weaver, P. The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), 1382-1394, 2014
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download