ATA is a non-profit organization that offering support and facilities to improve the lifestyle of people to maintain the effectiveness and sustainability. The organization has designed and implemented the solar project at East Timor. The current essay will provide information about budget, resources, and methodologies that used for monitoring and tracking of the system that implemented by the organization. Moreover, the essay will provide data about the time and cost that required for reporting to the higher committees. The essay will also justify the use of data and consideration of a specified structure to present the data.
Table 1: Schedule of tasks
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
Cost |
Project |
21 days |
Fri 14-09-18 |
Fri 12-10-18 |
$1,416.00 |
||
Identification of standards for project |
3 days |
Fri 14-09-18 |
Tue 18-09-18 |
Manager |
$240.00 |
|
Consideration of implementation process |
1 day |
Wed 19-09-18 |
Wed 19-09-18 |
2 |
Technical staff |
$40.00 |
Determination of quality standards |
2 days |
Thu 20-09-18 |
Fri 21-09-18 |
3 |
Supervisor |
$128.00 |
Training to staff |
3 days |
Mon 24-09-18 |
Wed 26-09-18 |
2,4 |
Manager |
$240.00 |
Collection of feedback |
1 day |
Thu 27-09-18 |
Thu 27-09-18 |
3,4,5 |
Administrator staff |
$56.00 |
Meeting with working staff |
1 day |
Fri 28-09-18 |
Fri 28-09-18 |
6 |
Manager |
$80.00 |
Checking of progress in project |
2 days |
Mon 01-10-18 |
Tue 02-10-18 |
6,7 |
Supervisor |
$128.00 |
Identification of areas for improvement |
2 days |
Wed 03-10-18 |
Thu 04-10-18 |
7,8 |
Technical staff |
$80.00 |
Communication to senior team |
1 day |
Fri 05-10-18 |
Fri 05-10-18 |
9 |
Administrator staff |
$56.00 |
Planning for improvement |
3 days |
Mon 08-10-18 |
Wed 10-10-18 |
10 |
Manager |
$240.00 |
Implementation of changes |
2 days |
Thu 11-10-18 |
Fri 12-10-18 |
11 |
Supervisor |
$128.00 |
The monitoring of project operations and activities for solar East Timor is essential for maintaining the higher efficiency and effective utilization of resources. According to the given scenario, the Kate is looking for a good plan for scheduling of cost and approach of the team members (Kerzner & Kerzner, 2017). The strategy for monitoring and control of the functions of the project suggest that the consideration of project performance metrics and quality standards are essential for identification of areas of lacking and action to overcome them. The proper planning for monitoring and tracking of the information about the progress of the project, the Kate should consider the above planning. This kind of approach will help her to identify the issues and areas of improvement according to proposed standards of the solar project and offer the training to the staff members about the proper utilization of resources and management of functions (Bayona,, Saboya, & Bustamante, 2018).
The cost of monitoring and progress tracking planning would be $1,416.00 and time is 21 days. The identification of project progress will be done against the determined international standards and approach of the team members (Harrison, & Lock, 2017). The proper collection and analysis of feedback through meeting will provide the actual idea about the progress and issues with an individual. The project manager will also provide training for managing the functions and monitor the approach of the individual to complete the tasks in the given time period and cost (Lewis, 2016). The major advantages of monitoring and controlling strategy for the project will involve the identification of actions, process, and activities according to the proposed plan for the project.
Table 2: Project team members
Client team |
Project team |
Sponsor |
Project manager |
Employees |
Project team |
Management team |
Technical team |
Internal expert team |
Administrator |
Supervisor |
These are key members from both sides who will contribute in governing the project and proper implementation of requirements to achieve the goals. The leading governing bodies will provide the advice and guidelines according to the input of the identified members of these team members.
Table 3: Reporting format
Initiator |
Title |
Report type |
Delivery method |
Format |
Recipients |
Frequency |
Project manager |
Project |
Planning |
Online |
Business report |
Sponsor |
Weekly |
Technical team |
Development |
Requirement design and analysis |
Online |
Progress report |
Project manager |
Daily |
Supervision |
Quality and approach |
Achievement of standards and requirements |
Online |
Monitoring report |
Manager and governing team members |
Weekly |
Testing team |
Compatibility and standards |
Effectiveness of Solar project |
Online |
Achievement and closure |
Technical team and project manager |
Weekly |
In order to manage the project progress and supervision according to standards and quality determined for the project, the reporting format of project will involve the project manager, technical team, supervisor and testing team. These are key members of governing team of project about Solar project who will develop plan, analyze the current and future conditions and requirements as well as identify the progress according to determined standards. These members will collect and document the data and information in particular format and share with the reporting authority. This kind of process will help to understand the progress, issues and support to provide the essential guidelines for managing the project. Moreover, the communication of report and documents will be done through online methods that are cost and time effective for sender and receiver. Moreover, the proper consideration of reporting format and frequency of the reporting will improve the effectiveness of the project.
Table 4: Risk register
Unpredictable Risks |
Predictable Risks |
Non-Technical Risks |
Technical Risks |
Legal Risks |
Natural Disasters |
Budget Risks |
Accidents on the event |
Are the Pre-project Activities viable? |
Risk for not fulfilling the contract |
Man-Made Disaster |
Workers Availability |
Workers Misconduct |
All tools working well? |
Breach of rules and regulations |
Deliverables are on track? |
Cost Fluctuation |
Availability of required technicians |
||
Environmental Impacts |
Absenteeism of management staff |
System Freezing |
||
Loss of potential |
Risk specific to technology (Issues in equipments and system approach for solar system) |
Changes in the political scenario |
Risk management is an essential part of project management and implementation. The project manager needs to identify and develop the plan for managing the risks for gaining the desired results from the solar project of East Timor (Haimes, 2015). The major risks that could affect the progress of the current project are financial, human resources and environmental impact. The manager Kate needs to focus on these risks to maintain the flow of project activities and the achievement of the goals (Neves, Silva, & Connors, 2014).
The communication with stakeholders is important for maintaining the efficiency and effectiveness in the project. The project manager of ATA, solar East Timor will conduct meetings with groups and individual for managing the activities and implementation of changes to gain the success in the project (Snyder, & Dionisio, 2017). Moreover, use of the online system for sharing the data and managing communication will be good for the manager to track the progress and collection of documents for reporting to the senior management. The online communication with project stakeholders is good in terms of monitoring and increasing the control over the actions according to time and cost allocated for each task (Scheer, and et al., 2014).
For the project, the Kate has adopted the democratic leadership style that has helped to involve all team members in decision making and implementation of the plan. For the monitoring and better controlling of the project, this type of leadership is beneficial as she can collect the 360-degree feedback for each action and provide the progress report to the CEO of the organization. Being a young woman manager, it would be difficult for her to order and make the decisions individually, therefore the democratic leadership will help her to gain the support and communicate the information to staff members (Anderson, & Sun, 2017).
For proper monitoring and control over the project, it is recommended to the project manager to maintain the proper communication with key members and governing team. The real time sharing of data and information will help to maintain the operations related to solar project up to the standards and help to achieve the goals more efficient manner. Moreover, regular meeting and brainstorming sessions will also support to gain knowledge about key issues and planning of them to minimize the cost and time for completing the project.
Conclusion
From the study, it has been carried out that monitoring and controlling of the project is important for the project manager to track the project progress and meet the objectives. The approach that Kate has used for monitoring and controlling of the activities after implementation of the plan would be useful to analyze the progress and craft improvement in areas of lacking. Moreover, the communication and leadership functions of the manager are discussed in the essay to overcome the risk and manage the tasks.
References
Anderson, M. H., & Sun, P. Y. (2017). Reviewing leadership styles: Overlaps and the need for a new ‘full?range’theory. International Journal of Management Reviews, 19(1), 76-96.
Bayona, S., Saboya, N., & Bustamante, J. (2018, June). Application of PMBOK in the development of research. In 2018 13th Iberian Conference on Information Systems and Technologies (CISTI). IEEE.
Haimes, Y. Y. (2015). Risk modeling, assessment, and management. John Wiley & Sons.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Lewis, N. S. (2016). Research opportunities to advance solar energy utilization. Science, 351(6271), aad1920.
Neves, D., Silva, C. A., & Connors, S. (2014). Design and implementation of hybrid renewable energy systems on micro-communities: a review on case studies. Renewable and Sustainable Energy Reviews, 31, 935-946.
Scheer, D., Benighaus, C., Benighaus, L., Renn, O., Gold, S., Röder, B., & Böl, G. F. (2014). The distinction between risk and hazard: understanding and use in stakeholder communication. Risk Analysis, 34(7), 1270-1285.
Snyder, C., & Dionisio, C. S. (2017). A project manager’s book of forms: A companion to the PMBOK guide. John Wiley & Sons.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download