New developments and changes allow the community to be upgraded and adopt new behaviors those can result in the enhancement of the life living of the individuals within the society. Development of the marina near Jamestown wharf has been considered one of the best approach for attracting the tourists and promotes tourism in the Saint Helena Island. The purpose of this report is to highlight the aspects related to the stakeholders and communication management within the project considering the successful and efficient delivery of the project. A business case is also proposed considering the various deliverables of the project.
Interviewing the stakeholders via questionnaire can be regarded as the best approach for this project delivery and set of questions were distributed for identifying the problems those are expected to be faced by them after connecting with the project. Following are the results of the interview:
Name |
Stakeholder |
Roles |
Responsibilities |
Interest |
Impact |
Louie Phillips |
Head of the Project |
Manage all the stakeholders and make better decision-making |
Consider every stakeholder while decision-making |
High |
Very High |
Aimee Curtis |
Project Manager |
Manage the roles and responsibilities of the stakeholders associated within the project |
Every stakeholder is assigned with the duties and jobs as per their capability of project delivery |
Very High |
Very High |
Morgan Norris |
Architect |
Develop the design of the entire transformation as per the need |
Consider all the natural aspects and develop a sophisticated and long running model for the establishment |
Medium |
High |
Erin Newton |
Resource Manager |
Manage the resources necessary for the delivery of the project |
All the resources necessary for the project delivery is available throughout the project lifecycle |
Medium |
High |
Emily Houghton |
Business Analyst |
Analyze the tourism market in the local and global environment |
Effectively propose the results for the implementation of the changes |
High |
High |
Charlie Nixon |
Market Analyst |
Analyze the internal and external markets for identifying the problems and solution |
Propose a best course of action for enhancing the market condition |
Medium |
Medium |
Georgina Doherty |
Promotional Manager |
Promote the new growth and development at St. Helena Marina |
Promote the objective and outcomes in efficient and effective manner |
High |
Medium |
Louie Arnold |
Civil Engineers |
Deliver the civil engineering and construction works |
Keep the civil construction risks far away from the project |
Very High |
High |
– |
Local community |
Avail the services being presented |
Provide necessary suggestions and feedback |
Low |
High |
– |
UK Government |
Provide loans and legal agreement to proceed with the project |
Provide enough funds and all the necessary legal allowance |
High |
High |
Issues raised in the development of this project can be listed as:
Stakeholder issues: assigning stakeholders with proper skills and knowledge related to the same sector can be an issue while executing the project as in manner to adhere maximum efficiency from the jobs of the stakeholders, it is necessary to assign the roles and responsibilities as per their capabilities.
Communication issues: proper communication needs to be established considering the discussion on the ongoing project, related issues, and solution for the successful delivery of the project. it is an obvious factor to look the project from different perspectives so an effective communication management plan is necessary for the development and growth of a successful project.
Political issues: This is a very big project and hence, needs various construction and modifications for which outsourcing becomes the crucial factor for the successful deployment of the project. The project needs to be politically clear in manner to assure not any further obstacle in the growth and development of the project.
Environmental issues: The entire project will need to be completed on an island and hence, the logistics is a genuine problem that should be eliminated before the project execution starts and manage the exchange of the resources throughout the project lifecycle.
The purpose of this task is to summarize the current situation of the island and propose a planned and effective business case that can reflect the aspects of the proposed project. the delivery of the project should be an effective and efficient follow of the activities that can be helpful in b ringing out maximum profit for the UK government.
The proposed project will be establishing a marina that will have all types of the fantasy that is always loveable by the tourist while thinking of visiting an island. It will provide a sophisticated model for the logistics and transport in manner to be connected with the outside world. Berthing facilities will be enhanced through increasing the berth capacities. There will be establishment of the bars, restaurants, parking, residential apartments, online taxi services and many more.
Government will be funding the entire growth and production of the project. Further attempts can be made to get more funds through promoting the private companies through offering advertisement in the exchange of the financial help.
In-scope objectives of the project are:
Out-scope objectives are:
Brainstorming, regular meetings, discussing weekly report, regular meetings, and other medium of interactions will be utilized for the delivery of the stakeholder management.
WBS |
Task Name |
Duration |
Start |
Finish |
1 |
St. Helena Marina Development |
781 days |
Wed 5/23/18 |
Wed 5/19/21 |
1.1 |
Phase 1: Project Initiation |
130 days |
Wed 5/23/18 |
Tue 11/20/18 |
1.1.6 |
Milestone 1: Approval for the project |
0 days |
Tue 11/20/18 |
Tue 11/20/18 |
1.2 |
Phase 2: Project Planning |
127 days |
Wed 11/21/18 |
Thu 5/16/19 |
1.2.9 |
Milestone 2: project planning Completed |
0 days |
Thu 5/16/19 |
Thu 5/16/19 |
1.3 |
Phase 3: Project Execution |
357 days |
Fri 5/17/19 |
Mon 9/28/20 |
1.3.9 |
Milestone 3: Project Execution completed |
0 days |
Mon 9/28/20 |
Mon 9/28/20 |
1.4 |
Phase 4: Monitoring and Auditing |
110 days |
Tue 9/29/20 |
Mon 3/1/21 |
1.4.6 |
Milestone 4: completed |
0 days |
Mon 3/1/21 |
Mon 3/1/21 |
1.5 |
Phase 5: Project Closure |
57 days |
Tue 3/2/21 |
Wed 5/19/21 |
1.5.6 |
Milestone 5 completed |
0 days |
Wed 5/19/21 |
Wed 5/19/21 |
WBS |
Task Name |
Duration |
Start |
Finish |
1 |
St. Helena Marina Development |
781 days |
Wed 5/23/18 |
Wed 5/19/21 |
1.1 |
Phase 1: Project Initiation |
130 days |
Wed 5/23/18 |
Tue 11/20/18 |
1.1.1 |
Analyzing the current problem |
15 days |
Wed 5/23/18 |
Tue 6/12/18 |
1.1.2 |
Proposing solution |
25 days |
Wed 6/13/18 |
Tue 7/17/18 |
1.1.3 |
Identifying the feasibility of the proposed solution |
20 days |
Wed 7/18/18 |
Tue 8/14/18 |
1.1.4 |
Proposing the Proposal of the project |
25 days |
Wed 8/15/18 |
Tue 9/18/18 |
1.1.5 |
loan approval from the UK government |
45 days |
Wed 9/19/18 |
Tue 11/20/18 |
1.1.6 |
Milestone 1: Approval for the project |
0 days |
Tue 11/20/18 |
Tue 11/20/18 |
1.2 |
Phase 2: Project Planning |
127 days |
Wed 11/21/18 |
Thu 5/16/19 |
1.2.1 |
Enlisting the requirements |
25 days |
Wed 11/21/18 |
Tue 12/25/18 |
1.2.2 |
Identifying the resources |
30 days |
Wed 12/26/18 |
Tue 2/5/19 |
1.2.3 |
Preparing work Breakdown Structure |
10 days |
Wed 2/6/19 |
Tue 2/19/19 |
1.2.4 |
Assigning Architect |
7 days |
Wed 2/20/19 |
Thu 2/28/19 |
1.2.5 |
Identifying key stakeholders |
15 days |
Fri 3/1/19 |
Thu 3/21/19 |
1.2.6 |
Developing the schedule |
15 days |
Fri 3/22/19 |
Thu 4/11/19 |
1.2.7 |
Assigning Stakeholders role and responsibility |
10 days |
Fri 4/12/19 |
Thu 4/25/19 |
1.2.8 |
Estimating the budget of the project |
15 days |
Fri 4/26/19 |
Thu 5/16/19 |
1.2.9 |
Milestone 2: project planning Completed |
0 days |
Thu 5/16/19 |
Thu 5/16/19 |
1.3 |
Phase 3: Project Execution |
357 days |
Fri 5/17/19 |
Mon 9/28/20 |
1.3.1 |
Design of the Marina Complex |
60 days |
Fri 5/17/19 |
Thu 8/8/19 |
1.3.2 |
Propose the design for approval |
7 days |
Fri 8/9/19 |
Mon 8/19/19 |
1.3.3 |
Implement the Mooring Facilities |
60 days |
Tue 8/20/19 |
Mon 11/11/19 |
1.3.4 |
Establishing the berthing facilities |
70 days |
Tue 11/12/19 |
Mon 2/17/20 |
1.3.5 |
Develop permanent birthing facilities |
65 days |
Tue 2/18/20 |
Mon 5/18/20 |
1.3.6 |
Establishing sheltered Marina complex |
40 days |
Tue 5/19/20 |
Mon 7/13/20 |
1.3.7 |
Implementing government facilities |
30 days |
Tue 7/14/20 |
Mon 8/24/20 |
1.3.8 |
Arrangements for service, fuel and repairing facilities |
25 days |
Tue 8/25/20 |
Mon 9/28/20 |
1.3.9 |
Milestone 3: Project Execution completed |
0 days |
Mon 9/28/20 |
Mon 9/28/20 |
1.4 |
Phase 4: Monitoring and Auditing |
110 days |
Tue 9/29/20 |
Mon 3/1/21 |
1.4.1 |
evaluating every activity |
15 days |
Tue 9/29/20 |
Mon 10/19/20 |
1.4.2 |
Project Evaluation checklist |
20 days |
Tue 10/20/20 |
Mon 11/16/20 |
1.4.3 |
Identifying modifications |
30 days |
Tue 11/17/20 |
Mon 12/28/20 |
1.4.4 |
Implementing changes |
20 days |
Tue 12/29/20 |
Mon 1/25/21 |
1.4.5 |
Reviewing the project activities |
25 days |
Tue 1/26/21 |
Mon 3/1/21 |
1.4.6 |
Milestone 4: completed |
0 days |
Mon 3/1/21 |
Mon 3/1/21 |
1.5 |
Phase 5: Project Closure |
57 days |
Tue 3/2/21 |
Wed 5/19/21 |
1.5.1 |
Project Documentation |
15 days |
Tue 3/2/21 |
Mon 3/22/21 |
1.5.2 |
Stakeholder sign off |
7 days |
Tue 3/23/21 |
Wed 3/31/21 |
1.5.3 |
Stakeholder releasing from contract |
10 days |
Thu 4/1/21 |
Wed 4/14/21 |
1.5.4 |
resource releasing |
10 days |
Thu 4/15/21 |
Wed 4/28/21 |
1.5.5 |
Lessons learned documentation |
15 days |
Thu 4/29/21 |
Wed 5/19/21 |
1.5.6 |
Milestone 5 completed |
0 days |
Wed 5/19/21 |
Wed 5/19/21 |
WBS |
Task Name |
Duration |
Resource Names |
Cost |
1 |
St. Helena Marina Development |
781 days |
$2,121,760.00 |
|
1.1 |
Phase 1: Project Initiation |
130 days |
$207,600.00 |
|
1.1.1 |
Analyzing the current problem |
15 days |
Business Analyst, Market Analyst, Project Manager |
$19,800.00 |
1.1.2 |
Proposing solution |
25 days |
Business Analyst, Market Analyst, Project Manager, Architect, Civil Engineers |
$53,000.00 |
1.1.3 |
Identifying the feasibility of the proposed solution |
20 days |
Business Analyst, Market Analyst, Project Manager, Architect, Civil Engineers |
$42,400.00 |
1.1.4 |
Proposing the Proposal of the project |
25 days |
Business Analyst, Market Analyst, Project Manager |
$33,000.00 |
1.1.5 |
loan approval from the UK government |
45 days |
Business Analyst, Market Analyst, Project Manager |
$59,400.00 |
1.1.6 |
Milestone 1: Approval for the project |
0 days |
$0.00 |
|
1.2 |
Phase 2: Project Planning |
127 days |
$337,280.00 |
|
1.2.1 |
Enlisting the requirements |
25 days |
Architect, Business Analyst, Civil Engineers, Market Analyst, Project Manager, Resource Manager, Resources[1], Promotional Manager |
$174,000.00 |
1.2.2 |
Identifying the resources |
30 days |
Architect, Civil Engineers, Project Manager, Resource Manager |
$55,200.00 |
1.2.3 |
Preparing work Breakdown Structure |
10 days |
Architect, Civil Engineers, Project Manager, Resource Manager |
$18,400.00 |
1.2.4 |
Assigning Architect |
7 days |
Architect, Civil Engineers, Project Manager, Resource Manager |
$12,880.00 |
1.2.5 |
Identifying key stakeholders |
15 days |
Architect, Civil Engineers, Project Manager, Resource Manager |
$27,600.00 |
1.2.6 |
Developing the schedule |
15 days |
Architect, Civil Engineers, Project Manager, Resource Manager |
$27,600.00 |
1.2.7 |
Assigning Stakeholders role and responsibility |
10 days |
Project Manager |
$6,000.00 |
1.2.8 |
Estimating the budget of the project |
15 days |
Project Manager, Resource Manager |
$15,600.00 |
1.2.9 |
Milestone 2: project planning Completed |
0 days |
$0.00 |
|
1.3 |
Phase 3: Project Execution |
357 days |
$1,248,000.00 |
|
1.3.1 |
Design of the Marina Complex |
60 days |
Architect, Civil Engineers, Resources[1] |
$148,000.00 |
1.3.2 |
Propose the design for approval |
7 days |
Architect, Civil Engineers, Resources[1] |
$105,600.00 |
1.3.3 |
Implement the Mooring Facilities |
60 days |
Architect, Civil Engineers, Resources[1], Human Labor, Promotional Manager |
$181,600.00 |
1.3.4 |
Establishing the berthing facilities |
70 days |
Architect, Civil Engineers, Resources[1], Human Labor, Promotional Manager |
$195,200.00 |
1.3.5 |
Develop permanent birthing facilities |
65 days |
Architect, Civil Engineers, Resources[1], Human Labor, Promotional Manager |
$188,400.00 |
1.3.6 |
Establishing sheltered Marina complex |
40 days |
Architect, Civil Engineers, Resources[1], Human Labor, Promotional Manager |
$154,400.00 |
1.3.7 |
Implementing government facilities |
30 days |
Architect, Civil Engineers, Resources[1], Human Labor, Promotional Manager |
$140,800.00 |
1.3.8 |
Arrangements for service, fuel and repairing facilities |
25 days |
Architect, Civil Engineers, Resources[1], Human Labor, Promotional Manager |
$134,000.00 |
1.3.9 |
Milestone 3: Project Execution completed |
0 days |
$0.00 |
|
1.4 |
Phase 4: Monitoring and Auditing |
110 days |
$269,600.00 |
|
1.4.1 |
evaluating every activity |
15 days |
Business Analyst, Market Analyst, Project Manager, Resource Manager |
$26,400.00 |
1.4.2 |
Project Evaluation checklist |
20 days |
Architect, Business Analyst, Civil Engineers, Market Analyst, Project Manager, Resource Manager |
$51,200.00 |
1.4.3 |
Identifying modifications |
30 days |
Architect, Business Analyst, Civil Engineers, Market Analyst, Project Manager, Resource Manager |
$76,800.00 |
1.4.4 |
Implementing changes |
20 days |
Architect, Business Analyst, Civil Engineers, Market Analyst, Project Manager, Resource Manager |
$51,200.00 |
1.4.5 |
Reviewing the project activities |
25 days |
Architect, Business Analyst, Civil Engineers, Market Analyst, Project Manager, Resource Manager |
$64,000.00 |
1.4.6 |
Milestone 4: completed |
0 days |
$0.00 |
|
1.5 |
Phase 5: Project Closure |
57 days |
$59,280.00 |
|
1.5.1 |
Project Documentation |
15 days |
Project Manager, Resource Manager |
$15,600.00 |
1.5.2 |
Stakeholder sign off |
7 days |
Project Manager, Resource Manager |
$7,280.00 |
1.5.3 |
Stakeholder releasing from contract |
10 days |
Project Manager, Resource Manager |
$10,400.00 |
1.5.4 |
resource releasing |
10 days |
Project Manager, Resource Manager |
$10,400.00 |
1.5.5 |
Lessons learned documentation |
15 days |
Project Manager, Resource Manager |
$15,600.00 |
1.5.6 |
Milestone 5 completed |
0 days |
$0.00 |
The project will be delivered within the expected time and budget and all the proposals will be approved by the stakeholders. Waterfall methodology will be utilized and hence, the next activity will be dependent on the completion of the previous activities. Quality evaluation, and project evaluation have not been considered for this business case.
Regular meeting in every week will be executed considering the presence of every necessary stakeholder in manner to measures and identify the growth and development of the project.
The project manager should follow the budget and schedule as proposed in the above report considering the proper and effective delivery of the project in far efficient and effective manner.
Following the case study, I get to know that establishing such big project needs an experienced and educated manager that can deliver the project activities through utilizing the knowledge and ideas related to the project management. I also identified that no matter what big picture we consider for the delivery of the project, it can always be extended for the better and effective consideration of the scope and project delivery. While identifying the business case I get to know that researching about the project, its impact, and other aspects are very crucial and vital for the consideration of the delivery of the project. I understand that cost and schedule are the crucial constraints those should be considered while delivering any single activity throughout the project.
Ahern, T., Leavy, B., & Byrne, P. J. (2014). Complex project management as complex problem solving: A distributed knowledge management perspective. International Journal of Project Management, 32(8), 1371-1381.
Beringer, C., Jonas, D., & Kock, A. (2013). Behavior of internal stakeholders in project portfolio management and its impact on success. International Journal of Project Management, 31(6), 830-846.
Bresnen, M. (2016). Institutional development, divergence and change in the discipline of project management. International journal of project management, 34(2), 328-338.
Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.
Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), 291-298.
Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), 1377-1392.
Kaiser, M. G., El Arbi, F., & Ahlemann, F. (2015). Successful project portfolio management beyond project selection techniques: Understanding the role of structural alignment. International Journal of Project Management, 33(1), 126-139.
Kerzner, H. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Leach, L. P. (2014). Critical chain project management. Artech House.
Lock, M. D. (2014). The essentials of project management. Ashgate Publishing, Ltd..
Martinsuo, M. (2013). Project portfolio management in practice and in context. International Journal of Project Management, 31(6), 794-803.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International Journal of Project Management, 32(2), 202-217.
Reiss, G. (2013). Project management demystified: Today’s tools and techniques. Routledge.
Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), 278-290.
Teller, J., & Kock, A. (2013). An empirical investigation on how portfolio risk management influences project portfolio success. International Journal of Project Management, 31(6), 817-829.
Todorovi?, M. L., Petrovi?, D. ?., Mihi?, M. M., Obradovi?, V. L., & Bushuyev, S. D. (2015). Project success analysis framework: A knowledge-based approach in project management. International Journal of Project Management, 33(4), 772-783.
Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), 1382-1394.
Turner, J. R. (2014). The handbook of project-based management (Vol. 92). New York, NY: McGraw-hill.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download