A.The standard forms of contracts used in the construction industry of UK are designed in a manner so as to make certain that the three basic requirements for the success of the project are proper met, and these three are time, cost and quality. These are crucial for avoiding any disputes which could have a negative impact over the project. In order for the parties to avoid disputes under construction contract, there is a need to follow the time aspect. There is a need for the contracting parties to abide by the time frame provided in the contract otherwise a dispute would be raised. Thus, the parties need to avoid any kind of delays in order to avoid conflict being raised between the parties (Haar, Levine and Laney, 216).
At the end of the day, the construction contracts are merely contracts and thus there formation requires the presence of basic elements of contract, which are provided under the common law of contract. These include offer, acceptance, consideration, clarity, consent, capacity and intention of the parties (Clarke and Clarke, 2016). In context of the time element, it is important for the parties to state in a clear manner in the contract the time map or the important dates related to the construction project. In case there is an ambiguity in this, the same could result in the contract being inoperable. Also, where the time period covered under the contract is not followed properly, the other party can bring an action of breach of contract and claim damages from the other party, in form of monetary compensation (Stone and Devenney, 2017). The best option in this regard is to follow the standard forms of contract and the details of time as are required under such contracts, to be followed (Haar, Levine and Laney, 216). There is a need to follow the standard provisions regarding time in the JCT Standard Building Contracts, which includes headings like adjustment of completion date. Stating this clearly would help in avoiding disputes, which could be raised due to lack of clarity on this issue. There is a need to structure the provisions of time and delay extensively. This is in context of possession of site, progress of work, completion of work and the like (Law Teacher, 2018).
In order to avoid any kind of dispute from being raised between the parties, the standard contract form provides the parties to clearly state the starting date, the date of completion, the accessing date and if required, any sectional completion. Both the JCT and the NEC provide the damages to be awarded for the late competition of project by the contractor. It is crucial for the parties to thus provide these details in a clear manner and follow them properly to avoid any dispute being raised in the future. The contractor needs to submit the master programme for the execution of work, whilst the NEC requires a more detailed set of documents in this regard. It is thus important to adopt one of these and follow them properly, to avoid the chances of breach of contract being raised (NEC, 2017). Under the Construction and Regeneration Act, 1996, the contracting parties are given with a statutory right for referring their disputes to adjudication (UK Legislation, 2017). So, instead of doing to the court, the parties should opt for alternative dispute resolution method to resolve the matter.
Where a dispute is raised, in cases of delay, there is a need to analyse the fault of the parties. When it so happens that a contractor is delayed owing to two events in which one is his own fault and one is the risk of the employer, the employer gets the entitlement to extension of time. This approach was given in Henry Boot Construction (UK) Ltd v Malmaison Hotel (Manchester) Ltd (1999) 70 ConLR 32, QBD (TCC). As per this approach, in cases where the contract is silent on the entitlement of contractor to extension of time, the contractor-risk event and the employer-risk event become concurrent, where both of these cause delay in the construction work. And in such cases, the contractor is entitled to be given an extension of time for entire period. Thus, the employer needs to avoid such instances where they make a mistake, along with the contractor, as the project would be extended for the entire period. This is particularly a negative implication as along with time, resources also have to be deployed to correct the mistake, which results in additional costs. Another key aspect which has to be avoided by the employer is for their delay to take place before the contractors, as that would result in the contract being given their float, instead of being deprived of the same, as was held in Royal Brompton Hospital National Service Trust v Hammond & Ors (No. 9) (2002) EWHC 2037 (TCC) (ICLG, 2017). Another important aspect is London Borough of Merton v Stanley Hugh Leach Ltd which provided that architects have to consider the events which could result in delays and for grant of proper extension of time. This is particularly in context of the clause 2.29 mentioned relevant events (Law Teacher, 2018).
B.The main issue of this case revolves around the legal implications owing to the accident which took place on the company under the tort law of negligence.
Negligence is covered under the common law of tort, which denotes a civil wrong done. In negligence, there is a breach of duty of care owed by one person to another person which results in injury or harm to the other person, particularly when the risk of harm was foreseeable in a reasonable manner (Turner, 2013). When a case of negligence is made by the plaintiff before the court, the court awards them with damages for such harm caused, which could be both physical and economical (Greene, 2013). It is not easy to establish a case of negligence and the plaintiff is required to show before the court that there was presence of certain key elements, like the duty of care being owed, the breach of it, harm or injury being caused, reasonable foreseeability of harm or injury, proximity between parties, and direct causation (Best, Barnes and Kahn-Fogel, 2014).
For establishing a duty of care, reference needs to be placed on the leading matter of Donoghue v Stevenson [1932] UKHL 100, or as is known as the “Snail in the Bottle” case. In this case, Donoghue had been served with ginger beer bottle at a cafe, which was purchased by her friend, and the same had been manufactured by the defendant. Upon drinking the concoction, Donoghue fell sick and sued the defendant, as the bottle had a dead snail in it. The court held the presence of duty of care for defendant towards the plaintiff as there was both proximity and reasonable foreseeability of such harm (Kolah, 2013). A contaminated drink is bound to make the consumer ill; the consumer manufacturer relationship has proximity; and there was also direct causation here as the plaintiff fell sick due to the defendant’s failure in upholding his duty (Statsky, 2011).
The next step is to show is that this duty was contravened and it resulted in harm for the other party. In this matter, reference needs to be made to Paris v Stepney Borough Council [1951] AC 367. In this case, the defendant was aware that the plaintiff was blind in one eye, and still they failed in making available the necessary safety gear to the plaintiff. When the plaintiff was carrying on the work for the defendant, a rusty bolt fell in his eye and blinded him completely. This was seen as a breach of duty of care by the defendant, resulting in significant injury for the plaintiff, which was not remote (Martin and Lancer, 2013).
Vicarious liability is also a crucial principle based on which the employer can be made liable for the acts of the employee, provided they are undertaken within the scope of employment by the employee (Lunney and Oliphant, 2013).
In the given case study, the workers were undertaking the work on the site, and so anything they did there became the responsibility of the company due to the principle of vicarious liability. It was their duty to carry on the work in a careful and diligent manner, as not doing so was reasonable foreseeable to cause economic and physical harm to the parties in proximity to such site. When they mistakenly cut the wire, resulting in power outrage, any loss which reasonably resulted from this would be the liability of the company. The economic loss sustained by the shop owner would thus be the liability of the company. And where the shop owner brings a case before the court, he would have to be awarded the claimed upon amount of damages.
Thus, the company would be liable to pay the shop owner, the sum of 50,000 towards the damages incurred by them, owing to the negligence of workers, which becomes the liability of the company due to operation of principle of vicarious liability. However for the opportunity loss, damages cannot be claimed. Thus, it is advised to the company to pay the claimed upon amount, and avoid the costs of litigation.
C.Alternative Dispute Resolution (ADR) is the manner of solving disputes, by adopting certain forms of it, without going for a formal mode of litigation. The two key forms of ADR are arbitration and mediation (Nolan-Haley, 2013).
In arbitration, the disputes between the contractor and sub-contractor are solved by referring the matter to an arbitrator, or arbitration panel. In the construction industry, often the construction contracts cover an arbitration clause, which provides the name of the arbitrator, or the manner in which the arbitration panel would be adopted. The decision of arbitration is known as the arbitration award and this has to be followed by the parties (Gramberg, 2006). Where the construction contract provides for arbitration to be used for solving the disputes, the matter has to be referred to the arbitration before litigation is adopted. An example of adjudication clause which can be included in the contract is given below (CIArb, 2017):
“Within 7 days of the Notice the Referring Party shall refer the dispute to the adjudicator”
There are a number of merits and demerits of opting for arbitration as a method of solving disputes. The merits include the confidentiality and privacy of matter, as these are not recorded publically as is done with litigation; it not only saves times, but also the costs; and the arbitrator can be selected by the disputes parties based on their choice. The demerits of arbitration include the lack of arbitration award being legally binding, as is the case with the court orders; a person cannot appeal against arbitration award and would have to make a case before the court, which beats the advantage of this method being cost and time efficient; and often this process replicates court procedures, making it a lengthy process (Ware, 2016).
The other form of ADR which can be opted in cases of disputes in construction industry is mediation. In this form, the parties in the dispute take the matter before a mediator, who attempts to solve the dispute through the use of different negotiation skills and techniques. As is the case with arbitration, this form also is cost effective and confidential. And again, the decision of mediator cannot be imposed upon the parties, which means that the dispute has to be taken to the court for the same to be resolved. The choice of mediator can also result in another dispute, which is not a problem in arbitration cases, as in cases of dispute, the parties to arbitration chose one arbitrator each and these chosen arbitrators mutually chose the final arbitrator, making an arbitration panel of three arbitrators (Kramer, 2016).
References
Best, A., Barnes, D.W., and Kahn-Fogel, N. (2014) Basic Tort Law: Cases Statutes and Problems. 4th ed. Frederick, MD: Wolters Kluwer Law & Business.
CIArb. (2017) Dispute Resolution Clauses. [Online] CIArb. Available from: https://www.ciarb.org/docs/default-source/das/contract-clause.pdf [Accessed on: 19/12/17]
Clarke, P., and Clarke, J (2016) Contract Law: Commentaries, Cases and Perspectives. 3rd ed. South Melbourne: Oxford University Press.
Gramberg, G.V. (2006) Managing Workplace Conflict: Alternative Dispute Resolution in Australia. New South Wales: The Federation Press.
Greene, B. (2013) Course Notes: Tort Law. Oxon: Routledge.
Haar, R.T., Levine, M., and Laney, A. (2016) Construction Insurance and UK Construction Contracts. 3rd ed. Oxon: Routledge.
ICLG. (2017) Construction & Engineering 2017. [Online] ICLG. Available from: https://iclg.com/practice-areas/construction-and-engineering-law/construction-and-engineering-2017/england [Accessed on: 19/12/17]
Kolah, A. (2013) Essential Law for Marketers. 2nd ed. United States: Kogan Page Limited.
Kramer, H. S. (2016) Alternative Dispute Resolution in the Work Place. New York: Law Journal Press.
Law Teacher. (2018) Time And Delay Related Provisions Under JCT. [Online] Law Teacher. Available from: https://www.lawteacher.net/free-law-essays/contract-law/time-and-delay-related-provisions-under-jct-contract-law-essay.php [Accessed on: 19/01/18]
Lunney, M., and Oliphant, K. (2013) Tort Law: Text and Materials. 5th ed. Oxford: Oxford University Press.
Martin, J., and Lancer, D. (2013) AQA Law for AS Fifth Edition. 5th ed. Oxon: Hachette UK.
NEC. (2017) A comparison of NEC and JCT. [Online] NEC. Available from: https://www.neccontract.com/getmedia/3d1b7c3f-097d-4504-8b1f-5a944dbc19dc/A-comparison-of-NEC-and-JCT.pdf.aspx [Accessed on: 19/12/17]
Nolan-Haley, J.M. (2013) Alternative Dispute Resolution in a Nutshell. 4th ed. Minnesota: West Academic.
Statsky, W.P. (2011) Essentials of Torts. 3rd ed. New York: Cengage Learning.
Stone, R., and Devenney, J. (2017) The Modern Law of Contract. 12th ed. Oxon: Routledge.
Turner, C. (2013) Unlocking Torts. 3rd ed. Oxon: Routledge.
UK Legislation. (2017) Housing Grants, Construction and Regeneration Act 1996. [Online] UK Legislation. Available from: https://www.legislation.gov.uk/ukpga/1996/53/contents [Accessed on: 19/12/17]
Ware, S. (2016) Principles of Alternative Dispute Resolution. Minnesota: West Academic.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download