In the past, building and construction works were measured using manual techniques. Units of length were provided by the human body. This included: inch – equivalent to the measure of thumb; foot – was taken to be 15.3% of a human body’s height; cubit – equivalent to the length of forearm (from the bottom of elbow to the middle finger’s tip); yard – equivalent to one human pace or stride; and miles – equivalent to 1,000 paces (Byju’s, 2017).
This continued until the introduction of metric system of measurement where works were measured in various measuring units like meters, grams and liters (Shrivastava, 2017). With the metric system, works were measured using different devices such as meter stick, ruler, measuring tape (tape measure), odometer, caliper, surveyor’s wheel, thread pitch gauge, pacing, metric scale, measuring rod, Gunter’s chain, etc. The main challenge with the traditional techniques of measurement was that measurement references or standards varied from one place to another and they largely depended on the watchfulness of the person taking the measurements. These techniques did not have standard procedures of taking measurements nor sheets (dimension papers) of recording the measured data.
The main challenges of traditional measurement techniques were overcome by the introduction of Standard Method of Measurement (SMM), which was published in 1922. This method provided a uniform localized basis for measurement of building works (Akbar, et al., 2015); (Akbar, et al., 2015). The method was used to provide detailed estimate of building works by using the following data: details of the work such as plans, cross-sections and elevation drawings; specifications of the work showing the exact type of building materials to be used; and the rates of works measured.
The SMM was implemented by following these steps: taking out quantities, squaring out, and abstracting (Nani, et al., 2008). Taking out quantities involves taking measurement off from the drawings and entering them on dimension paper or measurement sheet. The measurements taken out depend on the unit of measurement. For instance, if it is excavation, taking out quantities would involve measuring the length, width and depth of the excavation. Squaring out involves using the measurements taken out to calculate areas, volumes, weights, etc., and obtaining their total sin the desired units. For example, if it is excavation, the volume is obtained by multiplying the length, width and depth of the area to be excavated. Abstracting involves transferring the results obtained from squaring out and entering them in special sheets with rate column prepared for pricing (Civil Engineer, (n.d.)).
The SMM specifies the information that should be used to describe the structure to be measured; define the unit of measurement to be used for each item being measured (such as number, meter, m2, m3, tonnes, etc.); provides specific rules on what should be included in each item being measured; defines the terms of measurement to be used so as to avoid disputes; permits development of familiarity so as to make measurements easier and quicker; and provides a guidelines for cross-referencing (Hansen & Salim, 2015). There are seven editions of SMM.
In 2013, SMM7 was replaced by the NRM suite (New Rules of Measurement). The NRM suite provides a set of standard measurement rules to be adopted when measuring works. These rules are applicable when estimating cost, planning cost, procurement and other cost-related measurement throughout the lifecycle of the building project. There are three volumes of NRM suite: NRM 1 – which outlines that order for estimating and planning costs for building works; NRM 2 – which provides details on how building works should be measured; and NRM 3 – which outlines the order for estimating and planning costs for building maintenance works.
The NRM suite provides cost estimating guidance for various elements such as preliminaries, substructure, superstructure, mechanical and electrical services, drainage and external works, site development, furniture and equipment, consultant’s fees, and contingency (Royal Institution of Chartered Surveyors, 2012). NRM suite helps in taking accurate measurements and cross-checking them with the design specifications of the contract (Canadian Insttiute of Quantity Surveyors, 2014).
Today, most of the building works measurements are done using computer software and other technological tools (McDonnell, 2010). This has made building works measurement easier, quicker, more efficient and more accurate.
Question 2
Question 2(a): Take off list
The take-off list of the Gables substructure up to and including the DPC and floor slab insulation comprises of the following: site preparation, excavation, working space, earthwork support, concrete, masonry work, DPC and slab insulation. The take-off list of the Gables substructure plus the measurement units are as provided below:
Take-off list |
Unit |
NRM2 Reference |
Preliminary site work |
Item/Nr |
5.1 |
Clearing vegetation on site |
M2 |
5.4 |
Removing trees, plants and tree stumps |
Nr |
5.2/5.3 |
Preparing the site |
Nr/M2 |
5.5 |
Excavation of topsoil |
M3 |
5.6 |
Disposal of topsoil |
M3 |
5.9 |
Excavation to reduce level |
M3 |
5.7 |
Disposing spoil |
M3 |
5.9 |
Excavation of pits |
M3 |
5.7 |
Excavation of trenches (with width > 300mm) |
M3 |
5.7 |
Excavation of trenches (with width < 300mm) |
M |
5.7 |
Working below ground water level |
Item |
6.1 |
Working below water level |
Item |
6.1 |
Breaking any obstructions |
M3 |
7.9 |
Filling to excavation |
M3 |
5.11 |
Allowance for working space to excavation |
M2 |
5.14 |
Support for earthworks |
M2 |
5.8 |
Ground and surface water disposal |
Item |
6.1 |
Levelling and compaction of excavation bottom |
M2 |
6.9 |
Foundation formworks |
M2 |
8.3 |
Foundation reinforcements |
Kg |
8.4 |
Foundation concreting |
M3 |
8.2 |
Foundation block work or brickwork |
M2 |
8.5 |
Block work or brickwork projections |
M |
14.5 |
Foundation rubblework |
M2 |
14.2 |
Rubblework projections |
M |
14.5 |
Damp proofing course (DPC) |
M2 |
4.17 |
Ground levelling and compacting |
M2 |
6.9 |
Hardcore bed (filling to make desired levels) |
M3 |
6.9 |
Hardcore bed surface compacting and blinding |
M2 |
5.12 |
Vertical damp proof membrane (DPM) |
M2 |
5.16 |
Horizontal damp proof membrane (DPM) |
M2 |
5.16 |
Floor slab insulation |
M2 |
19.1 |
Concrete floor slab |
M3 |
11.1 |
Screeding |
M2 |
28.1 |
Adjustment of topsoil to foundations exterior |
M3 |
5.5 |
Question 2(b): Take-off dimensions
The relevant take-off dimensions are as follows:
Take-off list |
Unit |
Dimensions |
Description |
Preliminary site work |
Item/Nr |
1 |
Determining ground conditions and locating existing underground services |
Clearing vegetation on site |
M2 |
182.167 Deduct (25.042) 157.125 |
Clearing the site of all vegetation and disposing off site |
Removing trees, plants and tree stumps |
Nr |
5 |
Girth between 0.5m and 1.5m, 1.5m and 3m, and over 3m. |
Preparing the site |
Nr/M2 |
1 |
Lifting turf so as to prepare th required thickness |
Excavation of topsoil |
M3 |
235.688 |
Bulk excavation not exceeding 2m |
Disposal of topsoil |
M3 |
117.844 |
Carting away excavated material from the site |
Excavation to reduce level |
M3 |
85.325 |
Excavation of different depths |
Disposing spoil |
M3 |
125.5 |
Carting away spoil materials |
Excavation of pits |
M3 |
7.854 |
Excavation to determine underground services |
Excavation of trenches (with width > 300mm) |
M3 |
5.015 |
Excavating foundation trenches (width > 300mm) |
Excavation of trenches (with width < 300mm) |
M3 |
3.594 |
Excavating foundation trenches (width < 300mm) |
Working below ground water level |
Item |
1 |
Boreholes |
Working below water level |
Item |
1 |
Site area to be dewatered |
Breaking any obstructions |
Hr |
6 |
Rig standing |
Filling to excavation |
M3 |
78.563 Deduct (13.814) 64.749 |
Filling thickness <500mm deep |
Allowance for working space to excavation |
M2 |
28.697 |
Working space around all excavation <300mm and >300mm |
Support for earthworks |
M2 |
15.648 |
Support to excavation faces with a maximum depth of 305mm |
Ground and surface water disposal |
Item |
1 |
Dewatering of surface and ground water from the site |
Levelling and compaction of excavation bottom |
M2 |
182.167 |
The whole excavated area to be compacted |
Foundation formworks |
M2 |
41.443 |
Metallic or wooden formworks |
Foundation reinforcements |
Kg |
446.972 |
Steel reinforcement of different sizes (twisted bars) |
Foundation concreting |
M3 |
41.443 |
Concreting foundation <300mm and >300mm |
Foundation block work or brickwork |
M2 |
72.468 |
Foundation wall of 800mm |
Block work or brickwork projections |
M2 |
36.234 |
Vertical projections |
Foundation rubblework |
M2 |
18.117 |
Made from natural stone |
Rubblework projections |
M |
9.059 |
Horizontal projections |
Damp proofing course (DPC) |
M2 |
157.125 |
DPC to include the entire floor area, including walls |
Ground levelling and compacting |
M2 |
157.125 |
The whole floor area to be levelled and compacted |
Hardcore bed (filling to make desired levels) |
M3 |
47.138 |
Hardcore bed of thickness 300mm |
Hardcore bed surface compacting and blinding |
M2 |
157.125 |
The hardcore to b compacted appropriately |
Vertical damp proof membrane (DPM) |
M2 |
18.795 |
The vertical DPM of 1000 gauge to cover walls in wet areas of up to 500m (bathroom and kitchen) |
Horizontal damp proof membrane (DPM) |
M2 |
157.125 |
The horizontal DPM of 1000 gauge to cover the whole floor area |
Floor slab insulation |
M2 |
157.125 |
To cover the entire floor area |
Concrete floor slab |
M3 |
23.569 |
Slab to be 150mm thick |
Screeding |
M2 |
7.856 |
Screed of thickness 50mm |
Adjustment of topsoil to foundations exterior |
M3 |
26.416 |
The topsoil to be of depth 500mm |
Question 2(d): Abstracting
The bill of quantities of the house is provided in the table below:
Item |
Unit |
Quantity |
Rate (£) |
Total Cost (£) |
Preliminary site work |
Item/Nr |
1 |
10,200 |
10,200 |
Clearing vegetation on site |
M2 |
157.125 |
0.34 |
53.45 |
Removing trees, plants and tree stumps |
Nr |
5 |
53.52 |
267.60 |
Preparing the site |
Nr/M2 |
1 |
5,000 |
5,000 |
Excavation of topsoil |
M3 |
235.688 |
50 |
11,784.40 |
Disposal of topsoil |
M3 |
117.844 |
41 |
4,831.65 |
Excavation to reduce level |
M3 |
85.325 |
1.08 |
92.20 |
Disposal of spoil |
M3 |
125.5 |
41 |
5,145.50 |
Excavation of pits |
M3 |
7.854 |
9.41 |
73.95 |
Excavation of trenches (with width > 300mm) |
M3 |
5.015 |
41.15 |
206.40 |
Excavation of trenches (with width < 300mm) |
M3 |
3.594 |
31.04 |
111.60 |
Working below ground water level |
Item |
1 |
5,100 |
5,100 |
Working below water level |
Item |
1 |
5,100 |
5,100 |
Breaking any obstructions |
Hr |
6 |
33 |
198 |
Filling to excavation |
M3 |
64.749 |
1.5 |
97.15 |
Allowance for working space to excavation |
M2 |
28.697 |
4.06 |
116.55 |
Support for earthworks |
M2 |
15.648 |
17.69 |
276.85 |
Ground and surface water disposal |
Item |
1 |
2,500 |
2,500 |
Levelling and compaction of excavation bottom |
M2 |
182.167 |
3.50 |
637.60 |
Foundation formworks |
M2 |
41.443 |
25.32 |
1,049.35 |
Foundation reinforcements |
Kg |
298.33 |
888.62 |
265,099.05 |
Foundation concreting |
M3 |
41.443 |
350 |
14,505.05 |
Foundation block work or brickwork |
M2 |
72.468 |
140 |
10,145.55 |
Block work or brickwork projections |
M2 |
36.234 |
36.47 |
1,321.50 |
Foundation rubblework |
M2 |
18.117 |
87.79 |
1,590.50 |
Rubblework projections |
M |
9.059 |
143.48 |
1,299.80 |
Damp proofing course (DPC) |
M2 |
157.125 |
5.99 |
941.20 |
Ground levelling and compacting |
M2 |
157.125 |
37.24 |
5,851.35 |
Hardcore bed (filling to make desired levels) |
M3 |
47.138 |
30.62 |
1,443.40 |
Hardcore bed surface compacting and blinding |
M2 |
157.125 |
2.48 |
389.70 |
Vertical damp proof membrane (DPM) |
M2 |
18.795 |
5.99 |
112.60 |
Horizontal damp proof membrane (DPM) |
M2 |
157.125 |
5.99 |
941.20 |
Floor slab insulation |
M2 |
157.125 |
33.62 |
5,282.55 |
Concrete floor slab |
M3 |
23.569 |
160 |
3,771.05 |
Screeding |
M2 |
7.856 |
16.30 |
128.10 |
Adjustment of topsoil to foundations exterior |
M3 |
26.416 |
1,950 |
51,511.20 |
Total |
417,176.05 |
Question 2(d): Centre and perimeter lines
Centre-line of cavity: the thickness of cavity is 100mm. Therefore the centre-line is calculated from the internal perimeter of the cavity as follows:
((2 x 10,500) + (2 x 3,466.7)) + (4 x (2 x 100/2) = (21,000 + 6,933.4) + (4 x 2(50)) = 27,933.4 + 400 = 28,333.4mm = 28.33m
Length of external trench: this the external perimeter of the external trench line and it is calculated as follows:
(2 x 14,000) + (2 x 8,000) = 28,000 + 16,000 = 44,000mm = 44m
Length of internal trench line: this the external perimeter of the internal trench line and it is calculated as follows:
(2 x 12,100) + (2 x 5,600) = 24,200 + 11,200 = 35,400mm = 35.4m
Centre-line of external brick wall: the thickness of external brick wall is 305mm. Therefore the centre-line is calculated from external perimeter of the internal brick wall as follows:
((2 x 14,000) + (2 x 8,000)) – (4 x (2 x 305/2) = (28,000 + 16,000) – (4 x 2(152.5)) = 44,000 – 1220 = 42,780mm = 42.78m
Centre-line of internal brick wall: the thickness of internal brick wall is 100mm. Therefore the centre-line is calculated from external perimeter of the internal brick wall as follows:
((2 x 12,100) + (2 x 5,600)) – (4 x (2 x 100/2) = (24,200 + 11,200) – (4 x 2(50)) = 35,400 – 400 = 35,000mm = 35m
Centre-line of earth backfill: the thickness or width of earth backfill is 150mm. Therefore the centre-line is calculated from the external perimeter of the external brick wall as follows:
((2 x 14,000) + (2 x 8,000)) + (4 x (2 x 150/2) = (28,000 + 16,000) + (4 x 2(75)) = 44,000 + 600 = 44,600mm = 44.6m.
The importance of calculating the centre-line is to obtain the actual length of the excavation or masonry work (brickwork or block work) to be done. The total centre-line length is then then used to calculate the volume of excavation, masonry work or concrete to be used in the foundation or wall. The centre-line can also be used to calculate volume of DPC, plinth beam, wall plaster, paint and other superstructure elements. The financial consequence of centre-line is that it prevents overestimation, thus reducing chances of material wastage or buying excess materials. In other words, use of centre-line saves money by preventing overestimation of materials to be used.
Question 3
Question 3(a): Most appropriate cost estimating methods
The most appropriate method for estimating cost of a hospital o bowling alley is unit method. This methods is based on the personal units of the structure. The total cost of the building is determined by multiplying the total number of personal units with the cost per unit. Some of the personal units include: number of beds in the hospital, number of alleys in the bowling alley, number of operating rooms, number of laboratory rooms, number of consultation rooms, number of delivery rooms, number of registration or customer care desks, number of parking spaces, number of dressing/changing rooms, etc. Therefore the main processes of unit method is to identify the personal units of the building and the approximate cost of each personal unit. The cost per personal unit can be obtained from property developers, local municipalities, quantity surveyors, building and construction societies, etc.
The most appropriate method for estimating cost of a hospital o bowling alley is empirical costing methods. These methods are based on the estimator’s knowledge, experience and skills, and available data (Charkiewicz, 2011). These methods calculate cost estimates using data from previous similar projects (Riddell, 2017). It is usually a paper-based or software system. In this method, a quantity surveyor inputs characteristic details of the project (such as type of building, size of the building, type of building materials for various components, type of finishes, etc.)
into the system, which then estimates the cost of the building based on the type of the project. Empirical cost estimation methods are very fast and accurate because they draw from existing data of past similar projects. An example of empirical cost estimation method is Building Cost Information Service (BCIS) of the Royal Institution of Chartered Surveyors (RICS) (Smartsheet, 2018).
The most appropriate estimation method for a 10m x 6m bungalow is superficial floor area method. This method is also referred to as square meter method and it only requires sketch designs of the building with internal gross floor areas. The total cost of the project is determined by multiplying the gross floor area of the building by the construction cost per m2 in the region. The construction cost per m2 data can be provided by building experts in the region (such as consulting quantity surveyors), property developers, building societies and local municipalities (Estimation QS, 2018).
It is important to note that construction cost per m2 varies from one region to another and is also dependent on the type of building and other details such as desired finishes and equipment to be installed. Some of the advantages of this method include: it relies on sketch drawings of the architect, it is faster, it relies of the building plan’s gross floor area, it can incorporate the current building index, and estimates are based on similar projects completed in the past. Disadvantages include: it ignores the building’s aerial configuration, total wall perimeter, the building’s floor-to-ceiling height, and type and area of wall finishes. This method is also referred to as cubic foot and square foot estimation method (Cullen, 2016).
Question 3(b): Gantt chart
A Gantt chart is a very important tool in the management of construction projects (Geraldi & Lechter, 2012). The tool helps project managers to plan and schedule activities and resources for successful completion of projects (Mind Tools, 2018). Besides planning and scheduling, Gantt charts are also used to track progress of the project (Olivieri, et al., 2018); (Tran, 2015). The Gantt chart gives a visual presentation of the schedule of various project activities thus making it easier for project managers to know when they should complete certain tasks and how to plan for the activities ahead (Damci, et al., 2013).
The Gantt chart for the substructure of the house in this scenario is as shown in Figure 1 below. The Gantt chart has been prepared in excel.
References
Akbar, A., Mohammad, M., Ahmad, N. & Maisyam, M., 2015. Adopting Standardization in Construction Environment: Standard Method of Measurement (SMMs). Procedia – Social and Behavioral Sciences, 170(27), pp. 37-48.
Akbar, A., Mohammad, M., Talib, N. & Maisham, M., 2015. The Implication of the Standard Method of Measurement (SMMs) for Building Works Toward Contractors’ Works. In: R. Hassan, et al. eds. Construction Contract Management. Singapore: Springer, pp. 149-161.
Byju’s, 2017. Conventional Methods of Measurements.
Canadian Insttiute of Quantity Surveyors, 2014. Method of Measurement of Construction Works. 8th ed. Ontario: Canadian Insttiute of Quantity Surveyors.
Charkiewicz, T., 2011. Cost Estimating Methods: Empirical, Comparative, Statistical and Standards.
Civil Engineer, (n.d.). Standard Method of Measurement of Building Works
Cullen, S., 2016. Estimating.
Damci, A., Arditi, D. & Ploat, G., 2013. Resource leveling in line-of-balance scheduling. Computer-Aided Civil and Infrastructure Engineering, 28(9), pp. 679-692.
Estimation QS, 2018. 4 Common Estimating Methods Used by Quantity Surveyors and Construction Cost Engineers.
Geraldi, J. & Lechter, T., 2012. Gantt charts revisited: A critical analysis of its roots and implications to the management of projects today. International Journal of Managing Projects in Business, 5(4), pp. 578-594.
Hansen, S. & Salim, A., 2015. The importance of standard method of measurement in Indonesian construction industry,. International Journal of Technology and Engineering Studies, 1(4), pp. 123-128.
McDonnell, F. P., 2010. The Relevance of Teaching Traditional Measurement Techniques to Undergraduate Quantity Surveying Students. Journal for Education in the Built Environment, Volume 20, pp. 1-15.
Mind Tools, 2018. Gantt Charts.
Nani, G; Edwards, P; Adjei-Kumi, T; Badu, E; & Amoah, P., 2008. Customisation and Desirable Characteristics of a Standard Method of Measurement for Building Works in Ghana. Construction Economics , 8(2).
Olivieri, H., Seppanen, O. & Granja, A., 2018. Improving workflow and resource usage in construction schedules through location-based management system (LBMS). Construction Management and Economics, 36(2), pp. 109-124.
Riddell, T., 2017. Coost Estimation Techniques in Construction Projects.
Royal Institution of Chartered Surveyors, 2012. RICS New Rules of Measurement, UK: Royal Institution of Chartered Surveyors.
Shrivastava, S., 2017. Measurement Units of Length, Mass and Time in India Through the Ages. International Journal of Physical and Social Science, 7(5), pp. 39-48.
Smartsheet, 2018. The Ultimate Guide to Project Cost Estimating.
Tran, L., 2015. The Importance of the Gantt Chart and the Critical Path for Project Management.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download