Project aim
The aim of the project is to develop a project plan for the construction program of three blocks of building. The focus should be given on analysing the project progress report by evaluating the cost variance and schedule variance.
Project Objective
The objectives of this paper are:
The graph below shows the work status of all the resources used in the development of the project:
The graph below shows the utilization of resources in an effective manner:
Resource sheet:
Resource Name |
Type |
Material Label |
Initials |
Group |
Max. Units |
Std. Rate |
Ovt. Rate |
Cost/Use |
Accrue At |
Base Calendar |
Project Charter |
Work |
|
P |
|
100% |
$90.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Project Owner |
Work |
|
P |
|
100% |
$100.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Project Manager |
Work |
|
P |
|
100% |
$80.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Construction Manager |
Work |
|
C |
|
100% |
$65.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Design Engineer |
Work |
|
D |
|
100% |
$40.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Contractor |
Work |
|
C |
|
100% |
$60.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Quality Inspector |
Work |
|
Q |
|
100% |
$50.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Administrator |
Work |
|
A |
|
100% |
$30.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Site Engineer |
Work |
|
S |
|
100% |
$45.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Finance Manager |
Work |
|
F |
|
100% |
$75.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Resource Name |
Type |
Material Label |
Initials |
Group |
Max. Units |
Std. Rate |
Ovt. Rate |
Cost/Use |
Accrue At |
Base Calendar |
Project Charter |
Work |
|
P |
|
100% |
$90.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Project Owner |
Work |
|
P |
|
100% |
$100.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Project Manager |
Work |
|
P |
|
200% |
$80.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Construction Manager |
Work |
|
C |
|
500% |
$65.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Design Engineer |
Work |
|
D |
|
200% |
$40.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Contractor |
Work |
|
C |
|
400% |
$60.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Quality Inspector |
Work |
|
Q |
|
200% |
$50.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Administrator |
Work |
|
A |
|
200% |
$30.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Site Engineer |
Work |
|
S |
|
400% |
$45.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Finance Manager |
Work |
|
F |
|
100% |
$75.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Task Name |
Duration |
Start |
Finish |
Resource Names |
Cost |
Construction of the three storey building |
182 days |
Wed 07-11-18 |
Thu 18-07-19 |
|
$646,680.00 |
Project planning |
12 days |
Wed 07-11-18 |
Thu 22-11-18 |
|
$19,360.00 |
Project proposal |
3 days |
Wed 07-11-18 |
Fri 09-11-18 |
Project Charter,Project Owner |
$4,560.00 |
Approval off the project proposal |
3 days |
Mon 12-11-18 |
Wed 14-11-18 |
Project Charter,Project Owner |
$4,560.00 |
Project funding process |
2 days |
Thu 15-11-18 |
Fri 16-11-18 |
Project Charter,Project Owner,Finance Manager |
$4,240.00 |
Approval of the project funds |
2 days |
Mon 19-11-18 |
Tue 20-11-18 |
Finance Manager,Project Charter,Project Owner |
$4,240.00 |
Appointment of the CADD architecture |
2 days |
Wed 21-11-18 |
Thu 22-11-18 |
Administrator,Project Manager |
$1,760.00 |
Designing Phase |
19 days |
Fri 23-11-18 |
Wed 19-12-18 |
|
$14,720.00 |
Development of the conceptual design |
7 days |
Fri 23-11-18 |
Mon 03-12-18 |
Design Engineer,Project Manager |
$6,720.00 |
Engineering drawing preparation |
10 days |
Fri 23-11-18 |
Thu 06-12-18 |
Design Engineer |
$3,200.00 |
Final Architectural Design |
6 days |
Fri 07-12-18 |
Fri 14-12-18 |
Design Engineer |
$1,920.00 |
Finalization of the construction design |
3 days |
Mon 17-12-18 |
Wed 19-12-18 |
Design Engineer,Project Manager |
$2,880.00 |
Construction phase |
136 days |
Thu 20-12-18 |
Thu 27-06-19 |
|
$262,800.00 |
Set up of the site |
10 days |
Thu 20-12-18 |
Wed 02-01-19 |
Administrator,Construction Manager,Project Manager,Site Engineer |
$17,600.00 |
Excavation |
12 days |
Thu 03-01-19 |
Fri 18-01-19 |
Contractor,Construction Manager,Site Engineer |
$16,320.00 |
Foundation bases |
15 days |
Fri 04-01-19 |
Thu 24-01-19 |
Contractor,Construction Manager,Site Engineer |
$20,400.00 |
Setting of the steel frame |
10 days |
Wed 16-01-19 |
Tue 29-01-19 |
Construction Manager,Contractor,Site Engineer |
$13,600.00 |
Pre-cast floor 1 |
15 days |
Wed 30-01-19 |
Tue 19-02-19 |
Construction Manager,Design Engineer,Site Engineer |
$18,000.00 |
Precast of floor 2 |
15 days |
Wed 20-02-19 |
Tue 12-03-19 |
Construction Manager,Contractor,Site Engineer,Quality Inspector |
$26,400.00 |
Construction of the stairs |
21 days |
Wed 13-03-19 |
Wed 10-04-19 |
Construction Manager,Contractor,Site Engineer |
$28,560.00 |
Roofing |
12 days |
Thu 11-04-19 |
Fri 26-04-19 |
Construction Manager,Contractor,Site Engineer |
$16,320.00 |
Foundation of the external walls |
10 days |
Mon 29-04-19 |
Fri 10-05-19 |
Construction Manager,Contractor,Site Engineer |
$13,600.00 |
Ground Floor Slab |
10 days |
Mon 13-05-19 |
Fri 24-05-19 |
Construction Manager,Contractor,Site Engineer |
$13,600.00 |
External Block Work ground floor |
7 days |
Mon 27-05-19 |
Tue 04-06-19 |
Construction Manager,Contractor,Site Engineer |
$9,520.00 |
Internal Ground work Ist and 2nd floor |
7 days |
Wed 05-06-19 |
Thu 13-06-19 |
Construction Manager,Contractor,Site Engineer |
$9,520.00 |
Floor Finishes |
5 days |
Fri 14-06-19 |
Thu 20-06-19 |
Construction Manager,Contractor,Site Engineer |
$6,800.00 |
Brickwork Grd floor |
7 days |
Wed 05-06-19 |
Thu 13-06-19 |
Construction Manager,Contractor,Site Engineer |
$9,520.00 |
Brickwork 1st floor |
7 days |
Wed 05-06-19 |
Thu 13-06-19 |
Construction Manager,Contractor,Site Engineer |
$9,520.00 |
Brickwork 2nd floor |
5 days |
Wed 05-06-19 |
Tue 11-06-19 |
Construction Manager,Contractor,Site Engineer |
$6,800.00 |
Window grd floor |
5 days |
Fri 14-06-19 |
Thu 20-06-19 |
Construction Manager,Contractor,Site Engineer |
$6,800.00 |
Window 1st floor |
5 days |
Fri 14-06-19 |
Thu 20-06-19 |
Construction Manager,Contractor,Site Engineer |
$6,800.00 |
Window 2nd floor |
4 days |
Fri 14-06-19 |
Wed 19-06-19 |
Construction Manager,Contractor,Site Engineer |
$5,440.00 |
RWP connection |
2 days |
Thu 20-06-19 |
Fri 21-06-19 |
Construction Manager,Contractor,Site Engineer |
$2,720.00 |
Straw Panels |
2 days |
Mon 24-06-19 |
Tue 25-06-19 |
Construction Manager,Contractor,Site Engineer |
$2,720.00 |
Clear Site |
2 days |
Wed 26-06-19 |
Thu 27-06-19 |
Construction Manager,Administrator,Site Engineer |
$2,240.00 |
Inspection phase |
125 days |
Fri 04-01-19 |
Thu 27-06-19 |
|
$130,000.00 |
Inspection of the site progress |
125 days |
Fri 04-01-19 |
Thu 27-06-19 |
Project Manager,Quality Inspector |
$130,000.00 |
Administration phase |
136 days |
Fri 21-12-18 |
Fri 28-06-19 |
|
$190,400.00 |
Administration of the project development |
136 days |
Fri 21-12-18 |
Fri 28-06-19 |
Administrator,Construction Manager,Project Manager |
$190,400.00 |
Development and operational phase |
15 days |
Fri 28-06-19 |
Thu 18-07-19 |
|
$29,400.00 |
Completion of the construction program |
7 days |
Fri 28-06-19 |
Mon 08-07-19 |
Construction Manager,Contractor,Site Engineer |
$9,520.00 |
Project closure |
5 days |
Tue 09-07-19 |
Mon 15-07-19 |
Construction Manager,Project Charter,Project Manager,Project Owner |
$13,400.00 |
Handover for Operation |
3 days |
Tue 16-07-19 |
Thu 18-07-19 |
Project Charter,Project Manager,Project Owner |
$6,480.00 |
Gantt chart:
The following table shows the cost variance of the developed project:
Construction of the three storey building |
182 days |
07-Nov-18 |
18-Jul-19 |
$6,46,680.00 |
43.87 days |
07-Nov-18 |
NA |
$1,44,160.00 |
$3,320.00 |
Project planning |
12 days |
07-Nov-18 |
22-Nov-18 |
$19,360.00 |
11 days |
07-Nov-18 |
21-Nov-18 |
$15,720.00 |
$3,640.00 |
Project proposal |
3 days |
07-Nov-18 |
09-Nov-18 |
$4,560.00 |
3 days |
07-Nov-18 |
09-Nov-18 |
$4,560.00 |
$0.00 |
Approval off the project proposal |
3 days |
12-Nov-18 |
14-Nov-18 |
$4,560.00 |
2 days |
12-Nov-18 |
13-Nov-18 |
$3,040.00 |
$1,520.00 |
Project funding process |
2 days |
15-Nov-18 |
16-Nov-18 |
$4,240.00 |
2 days |
15-Nov-18 |
16-Nov-18 |
$4,240.00 |
$0.00 |
Approval of the project funds |
2 days |
19-Nov-18 |
20-Nov-18 |
$4,240.00 |
1 day |
19-Nov-18 |
19-Nov-18 |
$2,120.00 |
$2,120.00 |
Appointment of the CADD architecture |
2 days |
21-Nov-18 |
22-Nov-18 |
$1,760.00 |
2 days |
20-Nov-18 |
21-Nov-18 |
$1,760.00 |
$0.00 |
Designing Phase |
19 days |
23-Nov-18 |
19-Dec-18 |
$14,720.00 |
23 days |
21-Nov-18 |
21-Dec-18 |
$19,520.00 |
($4,800.00) |
Development of the conceptual design |
7 days |
23-Nov-18 |
03-Dec-18 |
$6,720.00 |
9 days |
21-Nov-18 |
04-Dec-18 |
$8,640.00 |
($1,920.00) |
Engineering drawing preparation |
10 days |
23-Nov-18 |
06-Dec-18 |
$3,200.00 |
9 days |
21-Nov-18 |
04-Dec-18 |
$2,880.00 |
$320.00 |
Final Architectural Design |
6 days |
07-Dec-18 |
14-Dec-18 |
$1,920.00 |
7 days |
05-Dec-18 |
13-Dec-18 |
$2,240.00 |
($320.00) |
Finalization of the construction design |
3 days |
17-Dec-18 |
19-Dec-18 |
$2,880.00 |
6 days |
14-Dec-18 |
21-Dec-18 |
$5,760.00 |
($2,880.00) |
Construction phase |
136 days |
20-Dec-18 |
27-Jun-19 |
$2,62,800.00 |
29.92 days |
21-Dec-18 |
NA |
$59,360.00 |
$4,480.00 |
Set up of the site |
10 days |
20-Dec-18 |
02-Jan-19 |
$17,600.00 |
9 days |
21-Dec-18 |
03-Jan-19 |
$15,840.00 |
$1,760.00 |
Excavation |
12 days |
03-Jan-19 |
18-Jan-19 |
$16,320.00 |
10 days |
04-Jan-19 |
17-Jan-19 |
$13,600.00 |
$2,720.00 |
Foundation bases |
15 days |
04-Jan-19 |
24-Jan-19 |
$20,400.00 |
15 days |
04-Jan-19 |
24-Jan-19 |
$20,400.00 |
$0.00 |
Setting of the steel frame |
10 days |
16-Jan-19 |
29-Jan-19 |
$13,600.00 |
7 days |
16-Jan-19 |
NA |
$9,520.00 |
$0.00 |
Pre-cast floor 1 |
15 days |
30-Jan-19 |
19-Feb-19 |
$18,000.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
Precast of floor 2 |
15 days |
20-Feb-19 |
12-Mar-19 |
$26,400.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
Construction of the stairs |
21 days |
13-Mar-19 |
10-Apr-19 |
$28,560.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
Roofing |
12 days |
11-Apr-19 |
26-Apr-19 |
$16,320.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
Foundation of the external walls |
10 days |
29-Apr-19 |
10-May-19 |
$13,600.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
Ground Floor Slab |
10 days |
13-May-19 |
24-May-19 |
$13,600.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
External Block Work ground floor |
7 days |
27-May-19 |
04-Jun-19 |
$9,520.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
Internal Ground work Ist and 2nd floor |
7 days |
05-Jun-19 |
13-Jun-19 |
$9,520.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
Floor Finishes |
5 days |
14-Jun-19 |
20-Jun-19 |
$6,800.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
Brickwork Grd floor |
7 days |
05-Jun-19 |
13-Jun-19 |
$9,520.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
Brickwork 1st floor |
7 days |
05-Jun-19 |
13-Jun-19 |
$9,520.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
Brickwork 2nd floor |
5 days |
05-Jun-19 |
11-Jun-19 |
$6,800.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
Window grd floor |
5 days |
14-Jun-19 |
20-Jun-19 |
$6,800.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
Window 1st floor |
5 days |
14-Jun-19 |
20-Jun-19 |
$6,800.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
Window 2nd floor |
4 days |
14-Jun-19 |
19-Jun-19 |
$5,440.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
RWP connection |
2 days |
20-Jun-19 |
21-Jun-19 |
$2,720.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
Straw Panels |
2 days |
24-Jun-19 |
25-Jun-19 |
$2,720.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
Clear Site |
2 days |
26-Jun-19 |
27-Jun-19 |
$2,240.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
Inspection phase |
125 days |
04-Jan-19 |
27-Jun-19 |
$1,30,000.00 |
14 days |
07-Jan-19 |
NA |
$14,560.00 |
$0.00 |
Inspection of the site progress |
125 days |
04-Jan-19 |
27-Jun-19 |
$1,30,000.00 |
14 days |
07-Jan-19 |
NA |
$14,560.00 |
$0.00 |
Administration phase |
136 days |
21-Dec-18 |
28-Jun-19 |
$1,90,400.00 |
25 days |
21-Dec-18 |
NA |
$35,000.00 |
$0.00 |
Administration of the project development |
136 days |
21-Dec-18 |
28-Jun-19 |
$1,90,400.00 |
25 days |
21-Dec-18 |
NA |
$35,000.00 |
$0.00 |
Development and operational phase |
15 days |
28-Jun-19 |
18-Jul-19 |
$29,400.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
Completion of the construction program |
7 days |
28-Jun-19 |
08-Jul-19 |
$9,520.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
Project closure |
5 days |
09-Jul-19 |
15-Jul-19 |
$13,400.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
Handover for Operation |
3 days |
16-Jul-19 |
18-Jul-19 |
$6,480.00 |
0 days |
NA |
NA |
$0.00 |
$0.00 |
The table below shows the schedule variance of the project:
Task Name |
Baseline Duration |
Actual Duration |
Actual Start |
Actual Finish |
SV |
Construction of the three storey building |
182 days |
43.87 days |
07-Nov-18 |
NA |
($1,040.00) |
Project planning |
12 days |
11 days |
07-Nov-18 |
21-Nov-18 |
$0.00 |
Project proposal |
3 days |
3 days |
07-Nov-18 |
09-Nov-18 |
$0.00 |
Approval off the project proposal |
3 days |
2 days |
12-Nov-18 |
13-Nov-18 |
$0.00 |
Project funding process |
2 days |
2 days |
15-Nov-18 |
16-Nov-18 |
$0.00 |
Approval of the project funds |
2 days |
1 day |
19-Nov-18 |
19-Nov-18 |
$0.00 |
Appointment of the CADD architecture |
2 days |
2 days |
20-Nov-18 |
21-Nov-18 |
$0.00 |
Designing Phase |
19 days |
23 days |
21-Nov-18 |
21-Dec-18 |
$0.00 |
Development of the conceptual design |
7 days |
9 days |
21-Nov-18 |
04-Dec-18 |
$0.00 |
Engineering drawing preparation |
10 days |
9 days |
21-Nov-18 |
04-Dec-18 |
$0.00 |
Final Architectural Design |
6 days |
7 days |
05-Dec-18 |
13-Dec-18 |
$0.00 |
Finalization of the construction design |
3 days |
6 days |
14-Dec-18 |
21-Dec-18 |
$0.00 |
Construction phase |
136 days |
29.92 days |
21-Dec-18 |
NA |
$0.00 |
Set up of the site |
10 days |
9 days |
21-Dec-18 |
03-Jan-19 |
$0.00 |
Excavation |
12 days |
10 days |
04-Jan-19 |
17-Jan-19 |
$0.00 |
Foundation bases |
15 days |
15 days |
04-Jan-19 |
24-Jan-19 |
$0.00 |
Setting of the steel frame |
10 days |
7 days |
16-Jan-19 |
NA |
$0.00 |
Pre-cast floor 1 |
15 days |
0 days |
NA |
NA |
$0.00 |
Precast of floor 2 |
15 days |
0 days |
NA |
NA |
$0.00 |
Construction of the stairs |
21 days |
0 days |
NA |
NA |
$0.00 |
Roofing |
12 days |
0 days |
NA |
NA |
$0.00 |
Foundation of the external walls |
10 days |
0 days |
NA |
NA |
$0.00 |
Ground Floor Slab |
10 days |
0 days |
NA |
NA |
$0.00 |
External Block Work ground floor |
7 days |
0 days |
NA |
NA |
$0.00 |
Internal Ground work Ist and 2nd floor |
7 days |
0 days |
NA |
NA |
$0.00 |
Floor Finishes |
5 days |
0 days |
NA |
NA |
$0.00 |
Brickwork Grd floor |
7 days |
0 days |
NA |
NA |
$0.00 |
Brickwork 1st floor |
7 days |
0 days |
NA |
NA |
$0.00 |
Brickwork 2nd floor |
5 days |
0 days |
NA |
NA |
$0.00 |
Window grd floor |
5 days |
0 days |
NA |
NA |
$0.00 |
Window 1st floor |
5 days |
0 days |
NA |
NA |
$0.00 |
Window 2nd floor |
4 days |
0 days |
NA |
NA |
$0.00 |
RWP connection |
2 days |
0 days |
NA |
NA |
$0.00 |
Straw Panels |
2 days |
0 days |
NA |
NA |
$0.00 |
Clear Site |
2 days |
0 days |
NA |
NA |
$0.00 |
Inspection phase |
125 days |
14 days |
07-Jan-19 |
NA |
($1,040.00) |
Inspection of the site progress |
125 days |
14 days |
07-Jan-19 |
NA |
($1,040.00) |
Administration phase |
136 days |
25 days |
21-Dec-18 |
NA |
$0.00 |
Administration of the project development |
136 days |
25 days |
21-Dec-18 |
NA |
$0.00 |
Development and operational phase |
15 days |
0 days |
NA |
NA |
$0.00 |
Completion of the construction program |
7 days |
0 days |
NA |
NA |
$0.00 |
Project closure |
5 days |
0 days |
NA |
NA |
$0.00 |
Handover for Operation |
3 days |
0 days |
NA |
NA |
$0.00 |
Activity |
Foundation of the external walls |
Description of the method |
The systematic conceptual design should be prepared for developing the foundation of the external walls so that project can be effectively completed within the proposed time and cost (Tonder, and Bekker, 2014). The parametric vale of the external wall should be analysed by the contractor (Monnappa, 2017). |
Resources used |
Project manager, Construction manager, contractor, site engineer |
Quantity |
2 gangs |
Output |
Activity will be completed on time and cost |
Time |
10 days |
Risk Identification |
Risks Recognition |
Risks Factors |
Risks Evaluation |
Control Measures |
Lack of coordination among the project activities |
High |
Team Coordination |
High |
Identifying the gaps in the resource management program (McDonald, and et. al., 2013) |
Lack of communication |
Medium |
No effective communication tools |
Medium |
Formal and informal communication tools should be deployed (Mansfield community, 2013) |
Employees risks |
Low |
Resistance from employees |
Medium |
The grievances and conflict of the employees should be identified (Kaziliunas, 2012) |
Kaziliunas, A. (2012). Problems while implementing quality management system for a sustainable development of organization. 1st ed. [ebook] Online. Available at: https://www.su.lt/bylos/mokslo_leidiniai/ekonomika/2012_4_28/kaziliunas.pdf [Accessed on 26 Oct, 2018]
Mansfield Community. (2013). Introduction to project management. 1st ed. [ebook] Online. Available at:https://www.mansfield.vic.gov.au/Libraries/Community_Development/Intro_to_Project_Management_Manual.sflb.ashx [Accessed on 26 Oct, 2018]
McDonald, K., Sundaram, V., Bravata, D., Lewis, R., and Lin, N. (2013). Closing the quality gap: A critical analysis of quality improvement strategies. Journal of object technology, 7(9). Available at: https://www.ncbi.nlm.nih.gov/books/NBK44015/[Accessed on 26 Oct, 2018]
Monnappa. (2017). Project scope management: What it is and why it is important. 1st ed. [ebook] Online. Available at: https://www.simplilearn.com/project-scope-management-importance-rar89-article [Accessed on 26 Oct, 2018]
Otieno, F. (2014). The role of monitoring and evaluation in projects. 1st ed. [ebook] Online. Available at: https://www.irbnet.de/daten/iconda/CIB8942.pdf [Accessed on 26 Oct, 2018]
Tonder, J., and Bekker, M. (2014). Analysis of a methodology to obtain a work breakdown structure built up from interdependent key project deliverable package. 1st ed. [ebook] Online. Available at: https://c.ymcdn.com/sites/www.projectmanagement.org.za/resource/resmgr/conference_proceedings_2002/10.pdf [Accessed on 26 Oct, 2018]
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download