Project management idea has been to a great extent created for assessing the advancement of venture and shaping the suitable improvement of venture devices and choices. The advancement of venture operations is being used for understanding the utilization of venture administration devices and choices. The advancement of web applications had been conceivable with the assistance of venture apparatuses and alternatives. The sending of online application and its ideas would be useful for shaping the investigation of the venture instruments and alternatives. The social media research centre had understood the significance of innovation for the venture operations. The improvement of venture would be facilitated by the utilization of venture administration devices and standards.
Project Schedule:
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
Cost |
Implementation of Web Application for Social Media Research Centre |
124 days |
Mon 4/3/17 |
Thu 9/21/17 |
$49,200.00 |
||
Initiation of the project plan |
21 days |
Mon 4/3/17 |
Mon 5/1/17 |
$8,840.00 |
||
Defining the objectives of the project |
2 days |
Mon 4/3/17 |
Tue 4/4/17 |
Systems Analyst |
$1,120.00 |
|
Selecting project operations |
2 days |
Wed 4/5/17 |
Thu 4/6/17 |
2 |
Program Team member |
$800.00 |
Budget estimation of the project |
2 days |
Fri 4/7/17 |
Mon 4/10/17 |
3 |
Program Team member |
$800.00 |
Developing detailed schedule of the project |
2 days |
Tue 4/11/17 |
Wed 4/12/17 |
4 |
Program Team member |
$800.00 |
Charter development |
2 days |
Thu 4/13/17 |
Fri 4/14/17 |
5 |
Program Team member |
$800.00 |
Charter is signed |
1 day |
Mon 4/17/17 |
Mon 4/17/17 |
6 |
Project Manager |
$640.00 |
Project Management Methodology is selected |
2 days |
Tue 4/18/17 |
Wed 4/19/17 |
7 |
Project Manager |
$1,280.00 |
Plan outline is developed |
2 days |
Thu 4/20/17 |
Fri 4/21/17 |
8 |
Team Member |
$560.00 |
Complete Plan is developed |
5 days |
Mon 4/24/17 |
Fri 4/28/17 |
9 |
Team Member |
$1,400.00 |
Plan is approved |
1 day |
Mon 5/1/17 |
Mon 5/1/17 |
10 |
Project Manager |
$640.00 |
Application design |
13 days |
Tue 5/2/17 |
Thu 5/18/17 |
$5,200.00 |
||
Design requirements is evaluated |
3 days |
Tue 5/2/17 |
Thu 5/4/17 |
11 |
Graphic Designer |
$1,200.00 |
Designing platform, tools, and method is selected |
4 days |
Fri 5/5/17 |
Wed 5/10/17 |
13 |
Graphic Designer |
$1,600.00 |
Outline of design is developed |
2 days |
Thu 5/11/17 |
Fri 5/12/17 |
14 |
Graphic Designer |
$800.00 |
Design is completed |
4 days |
Mon 5/15/17 |
Thu 5/18/17 |
15 |
Graphic Designer |
$1,600.00 |
Development of the Database |
17 days |
Fri 5/19/17 |
Mon 6/12/17 |
$7,120.00 |
||
Requirement analysis of the database |
2 days |
Fri 5/19/17 |
Mon 5/22/17 |
16 |
Database Administrator |
$800.00 |
Integration of the database with the design |
4 days |
Tue 5/23/17 |
Fri 5/26/17 |
18 |
Database Administrator |
$1,600.00 |
Selection of Storage drive |
2 days |
Mon 5/29/17 |
Tue 5/30/17 |
19 |
Database Administrator |
$800.00 |
Database creation is completed |
7 days |
Wed 5/31/17 |
Thu 6/8/17 |
20 |
Database Administrator |
$2,800.00 |
Database is reviewed |
2 days |
Fri 6/9/17 |
Mon 6/12/17 |
21 |
Systems Analyst |
$1,120.00 |
Application Development |
33 days |
Tue 6/13/17 |
Thu 7/27/17 |
$13,520.00 |
||
Analyzing the application platform |
2 days |
Tue 6/13/17 |
Wed 6/14/17 |
22 |
Application Programmer |
$800.00 |
Evaluation of the development tools |
4 days |
Thu 6/15/17 |
Tue 6/20/17 |
24 |
Application Programmer |
$1,600.00 |
Programing |
11 days |
Wed 6/21/17 |
Wed 7/5/17 |
25 |
Application Programmer |
$4,400.00 |
Completion of the coding |
9 days |
Thu 7/6/17 |
Tue 7/18/17 |
26 |
Application Programmer |
$3,600.00 |
Development of the application |
5 days |
Wed 7/19/17 |
Tue 7/25/17 |
27 |
Application Programmer |
$2,000.00 |
Application is reviewed |
2 days |
Wed 7/26/17 |
Thu 7/27/17 |
28 |
Systems Analyst |
$1,120.00 |
Testing Phase |
9 days |
Fri 7/28/17 |
Wed 8/9/17 |
$4,320.00 |
||
Alpha testing |
3 days |
Fri 7/28/17 |
Tue 8/1/17 |
29 |
Quality Assurance Tester |
$1,440.00 |
Beta testing |
3 days |
Wed 8/2/17 |
Fri 8/4/17 |
31 |
Quality Assurance Tester |
$1,440.00 |
Errors are evaluated |
3 days |
Mon 8/7/17 |
Wed 8/9/17 |
32 |
Quality Assurance Tester |
$1,440.00 |
Final Documentation and Training |
30 days |
Thu 8/10/17 |
Wed 9/20/17 |
$10,200.00 |
||
Results of testing is developed in report |
6 days |
Thu 8/10/17 |
Thu 8/17/17 |
33 |
Team Member |
$1,680.00 |
Project Closure and progress documents are created |
4 days |
Fri 8/18/17 |
Wed 8/23/17 |
35 |
Team Member |
$1,120.00 |
Training Manuals are developed |
5 days |
Thu 8/24/17 |
Wed 8/30/17 |
36 |
Team Member |
$1,400.00 |
Training is being given |
15 days |
Thu 8/31/17 |
Wed 9/20/17 |
37 |
Program Team member |
$6,000.00 |
Closure |
1 day |
Thu 9/21/17 |
Thu 9/21/17 |
38 |
$0.00 |
The advancement of venture exercises had been framed for shaping the suitable web application execution for the Social Media Research Centre. The venture had been expected to finish within 8 months. The aggregate number of days for the venture is 124 days. The laborers needed to frame savvy advancement of operations and capacities. The periphery esteem had been considered for 20%.
The constraints of the venture are the calendars, and asset allotment. The distribution of asset is a noteworthy hotspot for the improvement of the venture exercises. The restriction of venture spending plan to be not as much as AUD 50,000 would likewise fill the need of venture operations. The venture is likewise booked to finish in 8 months of span.
The estimation of spending plan is being produced by utilizing asset designation in the venture. The advancement of venture operations is being framed for shaping backing to the improvement of venture operations. There are some advancement models that would help in facilitating the elements of improvement of operations. The immediate expenses would be assessed in the venture of estimation of spending plan. The straightforward and simple to utilize venture would frame the suit improvement of venture in the association. The immediate costs like pay rates of colleagues, expenses of materials, and different expenses would serve the known knowns of the venture. The questions in the venture incorporate money related hazard administration exercises. These obscure variables would help in creating framework balance extend.
Risk Name |
Risk Type |
Status |
Responsible person |
Likelihood |
Impact |
Mitigation Strategy |
Design error |
Negative |
Active |
Designer |
Likely |
High |
Proper planning and efficient design is required |
Improper resource allocation |
Negative |
Active |
Project Manager |
Likely |
Moderate |
Understanding of allocated budget and available resource should be efficient |
Privacy and security issue |
Negative |
Active |
Security expert |
Possible |
Severe |
Proper encryption strategy using |
Early completion |
Positive |
Active |
Project manager |
Rare |
Minor |
After the early development review should be done properly |
The quality administration plan can be created by taking after the goals of the venture and creating affirmation articulation. The targets to take after venture are,
The 3 quality issues of venture are,
Security: It is the most essential question that faces the issues of improvement of operations at web-based social networking research focus
Execution: The elements of framework would be incongruent with the advancement of operations
Quality of performance: The affirmation of value is being accomplished for framing the savvy advancement of venture quality issues.
Closure and Evaluation:
Project Name: Implementation of Web Application for Social Media Research Centre |
Completion period: 8 Months |
|
Project Manager: [Enter Your name] |
Project budget: AUD 49200.00 |
|
Activities |
Due Date |
Person responsible |
The storage at Social Media Center would be developed |
Database Administrator |
|
Development of project plan for project activities |
Planner |
|
Charter creations for the project |
Project Manger |
|
Risk register is developed |
Quality team |
|
Training is developed |
Team member |
|
Supporting the plan and forming employees operations |
Team Member |
|
Final Project Report is made |
Program manger |
|
Develop Documents for Lesson Learned Documents |
Team member |
|
Develop Training Documents |
Sales Expert |
|
Handover of team reports for signing |
Program manager |
|
sign off team members |
Team members |
References:
de Carvalho, M. M., Patah, L. A., & de Souza Bido, D. (2015). Project management and its effects on project success: Cross-country and cross-industry comparisons. International Journal of Project Management, 33(7), 1509–1522. https://doi.org/10.1016/j.ijproman.2015.04.004
Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), 1377–1392. https://doi.org/10.1016/j.ijproman.2015.03.005
Kostalova, J., Tetrevova, L., & Svedik, J. (2015). Support of Project Management Methods by Project Management Information System. Procedia – Social and Behavioral Sciences, 210, 96–104. https://doi.org/10.1016/j.sbspro.2015.11.333
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Echeverría Lazcano, A. M., & Villanueva, P. (2014). Project risk management methodology for small firms. International Journal of Project Management, 32(2), 327–340. https://doi.org/10.1016/j.ijproman.2013.05.009
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: Linking Project Management Performance and Project Success. International Journal of Project Management, 32(2), 202–217. https://doi.org/10.1016/j.ijproman.2013.05.012
Schwalbe, K. (2014). Information Technology Project Management. Course Tecnhnology, 1–527.
Schwindt, C., & Zimmermann, J. (2015). Project management and scheduling. Handbook on Project Management and Scheduling Vol. 1. https://doi.org/10.1007/978-3-319-05443-8
Špundak, M. (2014). Mixed Agile/Traditional Project Management Methodology – Reality or Illusion? Procedia – Social and Behavioral Sciences, 119, 939–948. https://doi.org/10.1016/j.sbspro.2014.03.105
Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), 1382–1394. https://doi.org/10.1016/j.ijproman.2013.07.006
Turner, R. (2014). Gower Handbook of Project Management 5th edition. In Gower Handbook of Project Management (pp. 19–33). https://doi.org/10.1016/S0263-7863(01)00077-1
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download