Question:
Discuss about the Embracing Customer Relationship Management.
ABC is an Australian based private tourist network that attracts more than 200,000 families in a span on one year. The business includes the primary tourist attractions that can be visited along one of major Australian highways. The business serves the customers that are from Australian and also from other international locations. There are many loopholes present in the current system that is followed for the management and execution of the business activities. This leads to the inability to meet the customer expectations. One of the major drawbacks of the current system is the inability to be accessed on the mobile platforms.
In order to overcome such issues, it has been proposed that an automated system shall be developed with many new functions and features. The four primary areas that will be targeted in this task would be finance management, scheduling activities, human resource management and the customer relationship and interface management. The document is a report for the project that covers the planning and management details around the project.
The project will be managed by using and applying the project management methodology as Project Management Body of Knowledge (PMBOK). The project will be completed in a series of phases as initiation, planning, development, testing, documentation and closure.
PMBOK methodology has five phases as initiation, planning, execution, control and closure. The activities that come under PMBOK will be applied and synced with the project phases. There will be many estimates that will be set and decided for the project in the planning phase. These would primarily include schedule, budget, scope and resources.
The initiation stage must cover the feasibility analysis and chartering processes followed by estimation of schedule, budget, scope and resources in the planning phase. The execution must focus upon the management of design, development and integration activities. The control phase must include the review and monitoring along with the implementation and testing processes. The final closure phase must involve the acceptance and sign offs along with the submission of closure report.
Out-of-Scope
Apart from the time estimations, budget estimations and scope management, the following groups or modules will be used and implemented in the project as the modules and the management activities will also be based on the same.
Report Name |
Report Frequency |
Submitted to |
Mode of Reporting |
Daily Status Report |
Daily |
E-mails |
|
Weekly Status Report |
Weekly |
Project Sponsor |
SharePoint |
Change Requests Report |
Bi-Monthly |
Project Manager |
SharePoint |
Defect Report |
Monthly |
Project Manager and Sponsor |
SharePoint |
Closure Report |
Once – At Project Completion |
Project Sponsor |
SharePoint |
There may be many risks that may emerge during the project. An approach will be necessary for the management of the risks and this approach will have numerous phases as graphically represented below.
The above diagram represents the process that shall be used for the management of the risks in this case. The information system that will be developed for ABC Company may have many risks due to the industry type and nature of the project.
The first step in the risk management process shall be the identification of the risks. In this phase or sub-process, all forms of risks irrespective of their nature, type, priority and severity shall be identified and listed. This information and identification shall be performed on the basis of the information that shall be collected from various sources. These sources shall include the project stakeholders, market information, legacy systems etc.
The next sub-process shall be the analysis of the risks. In this sub-process, the risks that are identified shall be analyzed in terms of the project specifications, stages and accomplishment in terms of the likelihood, impact and rank. The risks shall then be evaluated in the third stage in which the risks that may be accepted shall be identified. The ones that cannot be accepted shall be moved to the fourth sub-process as risk treatment.
Risk treatment is a sub-process in which various treatment policies and mechanisms shall be identified and applied. There can be various treatment processes that can be applied in the form of mitigation, avoidance or transfer. The strategy applicable to every risk shall be decided and implemented.
The monitoring and control activities associated with the risks shall be carried out in the last stage with the submission of a closure report.
Risk Name |
Risk Likelihood (1-5, 5 is highest) |
Risk Impact (1-5, 5 is highest) |
Risk Rank (Likelihood * Impact) |
Risk Treatment Strategy |
Security Risks and Attacks |
4 |
4 |
16 |
Risk Avoidance – Use of technical , physical and administrative security controls |
Quality Issues |
2 |
5 |
10 |
Risk Avoidance – Training on quality standards and monitoring of adherence to the standards |
Operational Errors |
5 |
3 |
15 |
Risk Avoidance – Training on operational processes and monitoring of adherence to the standards |
Schedule Overrun |
2 |
5 |
10 |
Risk Avoidance – Tracking of the project activities against the estimated schedule |
Technical Faults |
4 |
3 |
12 |
Risk Mitigation – Use of alternative tools |
Legal/Political Risks |
1 |
5 |
5 |
Risk Avoidance – Training on legal policies and monitoring of adherence to the standards |
Budget Overrun |
4 |
5 |
20 |
Risk Avoidance – Tracking of the project activities against the estimated budget |
The monitoring and review processes shall be carried out by the Project Manager and the senior leadership. These processes must include the execution of the verification and validation techniques to understand the progress of the project, adherence to the best practices along with conflicts, disputes, risks and problems.
These processes must include a review plan prepared in the beginning and the same shall be followed. The results of these processes shall be discussed internally and shall also be informed to the project sponsor.
The success of the project shall be evaluated by using the following methods and techniques:
There will be internal and external resources that will be involved with the project that must be managed correctly. There must be specific approach and steps used for the management of the internal and external resources associated with the project.
The total cost of the project has been estimated to be AUD 75,000. It has been done using bottom up estimation technique and the costs that are allocated are justified because of the analysis involved in the project activities, project resources involved and the time required to complete the project. Per unit cost has been estimated and the assignment has been carefully done so as to meet the project requirements.
For the development of the information system for the private tourist business, the development methodology that shall be used in this case shall be agile methodology for product development. This methodology has been recommended due to the nature of the project and the requirements that need to be accomplished in the project. There are possibilities wherein the project requirements may change or get altered in the advanced stages of the project. With the use of agile methodology, it would be easy to incorporate the changes without any major impacts on the other modules or the overall project progress.
There will be many other advantages that will be offered by the agile methodology to the project. It would make sure that the system that is designed is flexible and scalable in nature. Technology is witnessing many changes and these changes are extremely rapid. It is necessary for the present day systems and applications to be designed and developed in such a manner that the changes can be easily made in future as well. Agile methodology will provide this ability to the system and the incorporation of future scaling will be smooth and hassle free. The transparency and communication with the end users and the project sponsor will also be maintained all throughout the project. This will not be restricted to the final stages of the project only. However, the recommendations and feedback will be collected during every stage and at the end of iteration. This will ensure that the areas of improvement are highlighted and the actions are taken to meet the customer expectations.
The product development will be carried out in the form of iterations which will be referred as sprints. All the project requirements will be broken down in many different sub-requirements and functions and each of these sets will be allocated to the iterations. The requirements of a particular iteration will be met and completed and the final requirement set will be created.
Conclusion
The project has been analyzed in terms of the resources involved, project requirements, nature of the project, project dependencies etc. The management methodology that has been selected for the project as PMBOK will be apt for this case on the basis of these different factors (Greenberger, 2016). There shall also be different trainings that shall be set up and arranged for the project resources. These trainings shall be in association with the new system that will be developed. Also, the trainings on the quality and ethical standards and practices that must be followed shall also be informed and made aware to the project resources.
There will be many changes in the business operations and the way they will be executed. These changes must also be considered and managed using the PMBOK guidelines. The changes must be listed and the corresponding change management approach must be applied for better handling and management. The security issues associated with the project shall be managed by using the various basic and advanced security concepts and tools. These shall include the use of access control mechanisms, intrusion detection systems, authentication systems, firewalls, proxy servers, network monitoring systems, anti-malware tools and many more such controls and measures.
References
Ayiri, G. and Kudzanayi, G. (2017). Embracing Customer Relationship Management (CRM) to Improve Organisational Viability by Small Businesses in Chinhoyi, Zimbabwe. IOSR Journal of Business and Management, 19(01), pp.50-54.
Gagnon, S. (2006). Globalizing Human Resource Management – Paul Sparrow, Chris Brewster and Hilary Harris. Human Resource Management Journal, 16(3), pp.331-332.
Greenberger, L. (2016). Effective Communications for Project Success. Remediation Journal, 26(2), pp.121-128.
Kock, A., Heising, W. and Gemunden, H. (2016). A Contingency Approach on the Impact of Front-End Success on Project Portfolio Success. Project Management Journal, 47(2), pp.115-129.
Mirza, M., Pourzolfaghar, Z. and Shahnazari, M. (2013). Significance of Scope in Project Success. Procedia Technology, 9, pp.722-729.
Muller, R. and Turner, R. (2007). The Influence of Project Managers on Project Success Criteria and Project Success by Type of Project. European Management Journal, 25(4), pp.298-309.
O’Leary, D. (2009). Downloads and citations inIntelligent Systems in Accounting, Finance and Management. Intelligent Systems in Accounting, Finance & Management, 16(1-2), pp.21-31.
Peslak, A. (2012). Information Technology Project Management and Project Success. International Journal of Information Technology Project Management, 3(3), pp.31-44.
Randolph, S. (2013). Projects and Complexity. Project Management Journal, 44(3), pp.e2-e2.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download