The following assignment would consider the project of “Implementation of Teaching and Learning System in High Quality Institute” and the report would comprise of system development lifecycle, work breakdown structure, Pert Chart, Entities and their attributes, ER diagram, NPV, Payback Period, and ROI Calculation.
The development of the effective project plan for the project of “Implementation of Teaching and Learning System in High Quality Institute” can be developed by using the traditional agile methodology for system development life cycle. The development of the agile methodology would be helpful for forming the development of the effective implication of the Business processes and formation of the unique support for the development. The following diagram would show the iterative agile software development lifecycle for the project,
Figure 1: Agile Software Development Life Cycle
(Source:
The agile software development lifecycle comprise of 6 phases namely requirements, plan, design, develop, release, and track & monitor phase. The completion of the phases would be based for the development of the final deliverable for the project. The phases has been explained below,
WBS |
Task Name |
0 |
Implementation of Teaching and Learning System in High Quality Institute |
1 |
Requirements |
1.1 |
Analysis of Requirements |
1.2 |
Initiation Documentation |
1.3 |
Charter Documents |
2 |
Plan |
2.1 |
Outline of plan |
2.2 |
Activity Scheduling |
2.3 |
Complete Planning |
3 |
Design |
3.1 |
Design Outline |
3.2 |
Design Review |
3.3 |
Complete Design Development |
3.4 |
Design Simulation |
4 |
Develop |
4.1 |
IT infrastructure development |
4.2 |
Server Development and Network Device Installation |
4.3 |
Switches and Routers are installed |
4.4 |
Software Development for ULS and PLS |
4.5 |
Testing Procedure Development |
4.6 |
Database System is developed |
5 |
Release |
5.1 |
Registration system is developed |
5.2 |
Tracking system is formed |
5.3 |
Bug and Error is reviewed |
5.4 |
Final system development |
6 |
Track and Monitor |
6.1 |
Monitoring system is developed |
6.2 |
Review of processes |
6.3 |
Tracking function development |
The work breakdown structure for the project of “Implementation of Teaching and Learning System in High Quality Institute” is shown below,
Figure 2: Work Breakdown Structure
The pert chart development would require the use of the activities, their early start date, early finish date, late start date, late finish date, and total slack. The following table would be used for the development of the pert chart for the project of “Implementation of Teaching and Learning System in High Quality Institute”,
WBS |
Task Name |
Early Start |
Early Finish |
Late Start |
Late Finish |
Total Slack |
0 |
Implementation of Teaching and Learning System in High Quality Institute |
Wed 8/1/18 |
Tue 10/9/18 |
Wed 8/1/18 |
Tue 10/9/18 |
0 days |
1 |
Requirements |
Wed 8/1/18 |
Wed 8/15/18 |
Wed 8/1/18 |
Fri 8/17/18 |
0 days |
1.1 |
Analysis of Requirements |
Wed 8/1/18 |
Fri 8/3/18 |
Wed 8/1/18 |
Fri 8/3/18 |
0 days |
1.2 |
Initiation Documentation |
Mon 8/6/18 |
Thu 8/9/18 |
Fri 9/28/18 |
Wed 10/3/18 |
39 days |
1.3 |
Charter Documents |
Fri 8/10/18 |
Wed 8/15/18 |
Thu 10/4/18 |
Tue 10/9/18 |
39 days |
2 |
Plan |
Mon 8/6/18 |
Fri 8/17/18 |
Mon 8/6/18 |
Mon 8/27/18 |
0 days |
2.1 |
Outline of plan |
Mon 8/6/18 |
Tue 8/7/18 |
Mon 8/6/18 |
Tue 8/7/18 |
0 days |
2.2 |
Activity Scheduling |
Wed 8/8/18 |
Fri 8/10/18 |
Wed 8/8/18 |
Fri 8/10/18 |
0 days |
2.3 |
Complete Planning |
Mon 8/13/18 |
Fri 8/17/18 |
Tue 8/21/18 |
Mon 8/27/18 |
6 days |
3 |
Design |
Mon 8/13/18 |
Mon 8/27/18 |
Mon 8/13/18 |
Mon 8/27/18 |
0 days |
3.1 |
Design Outline |
Mon 8/13/18 |
Wed 8/15/18 |
Mon 8/13/18 |
Wed 8/15/18 |
0 days |
3.2 |
Design Review |
Thu 8/16/18 |
Fri 8/17/18 |
Thu 8/16/18 |
Fri 8/17/18 |
0 days |
3.3 |
Complete Design Development |
Mon 8/20/18 |
Thu 8/23/18 |
Mon 8/20/18 |
Thu 8/23/18 |
0 days |
3.4 |
Design Simulation |
Fri 8/24/18 |
Mon 8/27/18 |
Fri 8/24/18 |
Mon 8/27/18 |
0 days |
4 |
Develop |
Tue 8/28/18 |
Wed 9/19/18 |
Tue 8/28/18 |
Tue 10/9/18 |
0 days |
4.1 |
IT infrastructure development |
Tue 8/28/18 |
Fri 8/31/18 |
Tue 8/28/18 |
Fri 8/31/18 |
0 days |
4.2 |
Server Development and Network Device Installation |
Mon 9/3/18 |
Fri 9/7/18 |
Mon 9/3/18 |
Fri 9/7/18 |
0 days |
4.3 |
Switches and Routers are installed |
Mon 9/10/18 |
Wed 9/12/18 |
Mon 9/10/18 |
Wed 9/12/18 |
0 days |
4.4 |
Software Development for ULS and PLS |
Mon 9/3/18 |
Mon 9/10/18 |
Tue 10/2/18 |
Tue 10/9/18 |
21 days |
4.5 |
Testing Procedure Development |
Thu 9/13/18 |
Tue 9/18/18 |
Thu 9/13/18 |
Tue 9/18/18 |
0 days |
4.6 |
Database System is developed |
Thu 9/13/18 |
Wed 9/19/18 |
Wed 10/3/18 |
Tue 10/9/18 |
14 days |
5 |
Release |
Wed 9/19/18 |
Mon 10/1/18 |
Wed 9/19/18 |
Tue 10/2/18 |
0 days |
5.1 |
Registration system is developed |
Wed 9/19/18 |
Fri 9/21/18 |
Wed 9/19/18 |
Fri 9/21/18 |
0 days |
5.2 |
Tracking system is formed |
Mon 9/24/18 |
Thu 9/27/18 |
Mon 9/24/18 |
Thu 9/27/18 |
0 days |
5.3 |
Bug and Error is reviewed |
Mon 9/24/18 |
Tue 9/25/18 |
Tue 9/25/18 |
Wed 9/26/18 |
1 day |
5.4 |
Final system development |
Wed 9/26/18 |
Mon 10/1/18 |
Thu 9/27/18 |
Tue 10/2/18 |
1 day |
6 |
Track and Monitor |
Fri 9/28/18 |
Tue 10/9/18 |
Fri 9/28/18 |
Tue 10/9/18 |
0 days |
6.1 |
Monitoring system is developed |
Fri 9/28/18 |
Tue 10/2/18 |
Fri 9/28/18 |
Tue 10/2/18 |
0 days |
6.2 |
Review of processes |
Wed 10/3/18 |
Fri 10/5/18 |
Wed 10/3/18 |
Fri 10/5/18 |
0 days |
6.3 |
Tracking function development |
Mon 10/8/18 |
Tue 10/9/18 |
Mon 10/8/18 |
Tue 10/9/18 |
0 days |
Figure 3: Pert Chart
The ER diagram for the project would include the following entities and their attributes,
The ER diagram for the project of “Implementation of Teaching and Learning System in High Quality Institute” is shown below,
Figure 4: ER diagram
The NPV, Payback Period, and ROI for the project of “Implementation of Teaching and Learning System in High Quality Institute” is shown below,
Cost benefit analysis |
||||||
Year 0 |
Year 1 |
Year 2 |
Year 3 |
Year 4 |
Year 5 |
|
Value of benefits |
$0 |
$7,000 |
$7,000 |
$7,000 |
$7,000 |
$7,000 |
Development cost |
($20,000) |
$750 |
$800 |
$770 |
$750 |
$730 |
Annual Expenses |
$0 |
($2,000) |
($2,000) |
($2,000) |
($2,000) |
($2,000) |
Net benefit/costs |
$10,000 |
$0 |
$0 |
$0 |
$0 |
$0 |
Net cash flow |
($10,000) |
$5,750 |
$5,800 |
$5,770 |
$5,750 |
$5,730 |
Discount factors |
||||||
Discount rate |
6% |
|||||
Year Index |
0 |
1 |
2 |
3 |
4 |
5 |
Discount factor |
1 |
0.94 |
0.89 |
0.84 |
0.79 |
0.75 |
Discounted flows |
||||||
Cost |
($20,000) |
($1,887) |
($1,780) |
($1,679) |
($1,584) |
($1,495) |
Benefit |
$10,000 |
$6,604 |
$6,230 |
$5,877 |
$5,545 |
$5,231 |
Net |
($10,000) |
$4,717 |
$4,450 |
$4,198 |
$3,960 |
$3,736 |
Cumulative |
($10,000) |
($5,283) |
($833) |
$3,365 |
$7,326 |
$11,062 |
Net present value |
$11,062 |
|||||
ROI |
33% |
|||||
Payback Analysis |
||||||
Years |
Months |
|||||
1 |
14 |
|||||
Payback Period in Years |
2.30 |
Conclusion
The following assignment had considered the project of “Implementation of Teaching and Learning System in High Quality Institute” and the report had been providing the details of system development lifecycle, work breakdown structure, Pert Chart, Entities and their attributes, ER diagram, NPV, Payback Period, and ROI Calculation.
References
Edwards Jr, T. V. (2017). APPLICATION OF AGILE METHODOLOGY TO ELECTROMECHANICAL DESIGN: A CASE STUDY. In Proceedings of the International Annual Conference of the American Society for Engineering Management. (pp. 1-5). American Society for Engineering Management (ASEM).
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.
Kerzner, H. (2018). Project management best practices: Achieving global excellence. John Wiley & Sons.
Leach, L. P. (2014). Critical chain project management. Artech House.
Lock, D. (2017). The essentials of project management. Routledge.
Mahadevan, L., Kettinger, W. J., & Meservy, T. O. (2015). Running on Hybrid: Control Changes when Introducing an Agile Methodology in a Traditional” Waterfall” System Development Environment. CAIS, 36, 5.
Meredith, J. R., Mantel, S. J., Shafer, S. M., & Sutton, M. M. (2014). Project management in practice. Wiley.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.
Nicholas, J. M., & Steyn, H. (2017). Project management for civil engineering, business and technology. Routledge.
Steinke, G. H., Al-Deen, M. S., & LaBrie, R. C. (2017). NNOVATING INFORMATION SYSTEM DEVELOPMENT METHODOLOGIES WITH DESIGN THINKING. In Proceedings of the 5th International Conference on Applied Innovations in IT (pp. 51-55).
Turner, J. R. (2014). Handbook of project-based management(Vol. 92). New York, NY: McGraw-hill.
Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.
Essay Writing Service Features
Our Experience
No matter how complex your assignment is, we can find the right professional for your specific task. Contact Essay is an essay writing company that hires only the smartest minds to help you with your projects. Our expertise allows us to provide students with high-quality academic writing, editing & proofreading services.Free Features
Free revision policy
$10Free bibliography & reference
$8Free title page
$8Free formatting
$8How Our Essay Writing Service Works
First, you will need to complete an order form. It's not difficult but, in case there is anything you find not to be clear, you may always call us so that we can guide you through it. On the order form, you will need to include some basic information concerning your order: subject, topic, number of pages, etc. We also encourage our clients to upload any relevant information or sources that will help.
Complete the order formOnce we have all the information and instructions that we need, we select the most suitable writer for your assignment. While everything seems to be clear, the writer, who has complete knowledge of the subject, may need clarification from you. It is at that point that you would receive a call or email from us.
Writer’s assignmentAs soon as the writer has finished, it will be delivered both to the website and to your email address so that you will not miss it. If your deadline is close at hand, we will place a call to you to make sure that you receive the paper on time.
Completing the order and download